fire station no 8 history legacy working group
play

Fire Station No. 8 History & Legacy Working Group Langston - PowerPoint PPT Presentation

Fire Station No. 8 History & Legacy Working Group Langston Brown Recreation Center March 8, 2018 from 7-9 p.m. Agenda 7:00 7:05 Welcome and Opening Comments 7:10 7:20 Introduction of Members and Support Team 7:20


  1. Fire Station No. 8 History & Legacy Working Group Langston Brown Recreation Center March 8, 2018 from 7-9 p.m.

  2. Agenda • 7:00 – 7:05 Welcome and Opening Comments • 7:10 – 7:20 Introduction of Members and Support Team • 7:20 – 8:00 Process Overview • Charge, Timeline & Process • Fire Station Replacement Project • Q&A • 8:00 – 8:20 Imagining the Future of Fire Station No. 8 • Q&A • 8:20 – 9:00 Public Comment Fire Station No. 8 Walking Tour 2

  3. Working Group Members FS8HL Working Group Members Name ame Affiliation Noah Simon, Chair Fire Station 8 Task Force Jennifer Burgin APS Teacher Lydia Cole Community Member Marguarite Gooden Community Member/Langston Brown CA Edith Gravely Community Member/LHA Saundra Green Community Member/Lee Highway Alliance Wilma Jones Community Member/Langston Brown CA Richard Lolich Lee Highway Alliance Elizabeth Morton Public Art Committee James Schroll PFRC Dale Smith Community Member Kitty Clark Stevenson Community Member Denny Truesdale EPAC Andrew Wenchel, Jr. HALRB, DRC 3 This slide was changed on 3/13/18 to reflect an updated membership list.

  4. Working Group Charge • The FS8HL Working Group will develop a report providing recommendations for how the history and legacy of the Hall’s Hill/High View Park Volunteer Fire Department and Fire Station No. 8 should be celebrated as part of the new fire station to be built at 4845 Lee Highway. 4

  5. Charge (cont.) • Recommendations may address the following elements: • The exterior of the station and site (i.e. distinctive architectural features, signage, creative use of color and materials, lighting, landscaping, paving, public art, possibilities for temporary and permanent interpretative heritage exhibits); • The interior public, non-operational spaces* (i.e. distinctive architectural features, possibilities for temporary and permanent interpretative heritage exhibits, public art, other design elements or features); and • Opportunities for reuse of existing building materials if appropriate to honor history and legacy of the station. • All recommendations will allow Arlington County Fire Department (ACFD operational) requirements to be met and fall within the Key Parameters laid out below. 5

  6. Meeting Procedure and Communication • Presentations and Question & Answer Period • Requests for Information • Public Comment • Report • https://projects.arlingtonva.us/projects/fire-station- no-8-history-legacy-working-group// 6

  7. Working GroupTimeline Kickoff Working Group Meetings Guiding Principles March March-May March-April Subcommittee Work Draft Report Report to County Manger March-April Beginning-Mid May End of May 7

  8. Fire Station No. 8 4845 Lee Highway Arlington, VA 22207 8

  9. Current Conditions of Fire Station No. 8 • Built in 1963 • 2 Bays • Cannot handle required equipment • Insufficient space for current requirements such as gear storage, decontamination area, and training • Limited lockers and change facilities • Inadequate cooking facilities • Insufficient parking • Technology upgrades 9

  10. Fire Station Program • ~ 15,000 Square Feet Building including • 4 Bays Apparatus Bay & Operation spaces • Residential spaces • Administrative rooms • Support areas • Drive Thru Bays • Temporary Fire Station • 12 staff parking • Fuel Island 10

  11. BUDGET FORECAST $000’s FS 8 Base Bldg in 2017-2026 CIP $15,120 $000’s Not Included: Temp Station Land $2,500 Temp Station Construction $1,150 New Fuel Island $1,500 Contingency (15% on above) $ 770 $5,920 $ 5,920 Forecast Cost $21,040 Funds Sources 2016 Referendum $ 1,120 FY16 Carryover $ 2,500 2018 Referendum $17,420 (was $14,000) $21,040 11

  12. SCHEDULE FORECAST SCHEDULE FORECAST 2017 2018 2019 2020 2021 AC TIVITY Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 TAS K ORDE R A/E DE S IGN AND PE RMITTING TE MP GL UP AME ND, RE ZONING 3 PARC E L S TO S 3A, & 2232 FINDING C MAR RFP AE PE RM S TATION RFP PE RM S TATION - DE S IGN & PE RMITTING 2018 RE FE RE NDUM C ONS TRUC T TE MPORARY FIRE S TATION C ofO C ONS TRUC T PE RMANE NT FIRE S TATION & FUE L IS L AND PROC URE ME NT DE S IGN RE ZOING AND 2232 FINDING, PUBL IC PROC E S S C ONS TRUC TION BOARD APPROVAL S PFRC RE VIE W 12

  13. Temporary Fire Station & Construction Zone Temporary Fire Station & Construction Zone 13

  14. Finished Site Condition Finished Site Condition 14

  15. GLUP and Zoning • Existing Fire Station No. 8 parcel – No change from current GLUP and Zoning – Current and S3-A Proposed • Three parcels for temporary station change require GLUP amendment and rezoning from R-6 to S-3A • S-3A: – Consistent with permanent station S-3A zoning – Allows for the program needs (i.e. by- right use, 45’ height maximum) – Typically found adjacent to/surrounded by low residential areas – Precedent: 5 of 10 stations in S3A • Change GLUP for three parcels from “Low Residential’” to “Government and Community Facilities”, consistent with current FS parcel . 15

  16. SCHEDULE FORECAST SCHEDULE FORECAST 2017 2018 2019 2020 2021 AC TIVITY Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 TAS K ORDE R A/E DE S IGN AND PE RMITTING TE MP GL UP AME ND, RE ZONING 3 PARC E L S TO S 3A, & 2232 FINDING C MAR RFP AE PE RM S TATION RFP PE RM S TATION - DE S IGN & PE RMITTING 2018 RE FE RE NDUM C ONS TRUC T TE MPORARY FIRE S TATION C ofO C ONS TRUC T PE RMANE NT FIRE S TATION & FUE L IS L AND PROC URE ME NT DE S IGN RE ZOING AND 2232 FINDING, PUBL IC PROC E S S C ONS TRUC TION BOARD APPROVAL S PFRC RE VIE W 16

  17. Questions & Answers 17

  18. What’s Possible for the Future? 18

  19. Themed Construction 19

  20. Nauck Town Square

  21. Bob Peck Chevrolet

  22. HH/HVP

  23. Walk of Honor 24

  24. Fire Stations

  25. Courthouse Mural 26

  26. Heritage Wall 27

  27. Heritage Walls

  28. Wrap up • Next Task Force Meetings – March 22, 7:00 p.m. – 9:00 p.m. Langston Brown CC – April 5, 7:00 p.m. – 9:00 p.m. Langston Brown CC • Contact Information: Noah Simon Email - noahsimon2012@gmail.com 29

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend