MVLWB Technical Session Snap Lake Mine Final Closure, and Water Licence and Land Permit Renewal July 16 to 18, 2019
FINAL NAL CLOSURE OSURE AND ND RECLAMA ECLAMATION TION PL PLAN
PUBLIC LIC PRESEN ENTATION ION
FINAL NAL CLOSURE OSURE AND ND RECLAMA ECLAMATION TION PL PLAN - - PowerPoint PPT Presentation
FINAL NAL CLOSURE OSURE AND ND RECLAMA ECLAMATION TION PL PLAN MVLWB Technical Session Snap Lake Mine Final Closure, and Water Licence and Land Permit Renewal July 16 to 18, 2019 PUBLIC LIC PRESEN ENTATION ION CONCEPTS CEPTS FOR R
MVLWB Technical Session Snap Lake Mine Final Closure, and Water Licence and Land Permit Renewal July 16 to 18, 2019
PUBLIC LIC PRESEN ENTATION ION
1
self-sustaining ecosystems that are compatible with a healthy environment and with human activities.
ure e criter eria ia have been developed
2
MVLWB Approved
Provided in FCRP Provided in FCRP
Provided in FCRP; incorporates feedback from Nov meeting
4
Site Wide e (SW):
Infras astruc tructure ure (I):
management pond)
North h Pile e (NP):
infrastructure component Under dergr groun
d Mine e (UG):
below ground.
infrastructure component
5
SW2 - Drainage pathways for surface runoff are physically stable.
SW1 – Dust levels safe for people, vegetation, aquatic life and wildlife.
SW3 - Surface runoff and seepage water quality that is safe for people, vegetation, aquatic life, and wildlife. SW4 - Mine areas are physically stable and safe for use by people and wildlife. SW5 - Landscape features (shape and vegetation) match aesthetics of the surrounding natural area. SW6 - Safe passage and use for Caribou and
SW7 - Re-vegetation targeted to priority areas.
6
I1 – Prevent remaining infrastructure from contaminating land or water. I2 – On-site disposal areas are safe for people, wildlife, and vegetation. I3 – Contaminated soils and waste disposal areas that cannot contaminate land and water.
7
NP1 – Prevent PK from entering the surrounding terrestrial and aquatic environment. NP2 – Physically stable PK containment area to limit risk of failure that would affect safety of people or wildlife.
8
UG1 – Flooding of the underground mine will have no impacts to aquatic habitat and community in source lakes. UG2 – Underground mine should not contribute to the contamination of ground or surface water. UG3 – Underground mine workings are physically stable.
10 10
11 11
2019 2019 2020 2020 2021 2021 2022 2022 2023 2023 2024 2024 2025 2025 2026 2026 2027 2027 2028 2028 2029 2029 2030 2030 2031 2031 2032 2032 2033 2033 2034 2034
2035 2035-2045 2045
Demolition Winter Road Water Management System and North Pile Cover Construction (Influent Storage Ponds, Wetlands and spillways) Active Demolition Activity Revegetation, Landforming and Site Stabilization Final Winter Road Owners Team Fully Activated Extended Care and Maintenance Winter Road 1 Post Closure Water Licence Process Monitoring of System Biota Growth and Denitrification
13 13
ages betw etwee een Objectiv jectives, s, Crit iter eria ia and Closu
e Ac Activ ivit itie ies
ages betw etwee een Objectiv jectives, s, Crit iter eria ia and Monit itor
ing Plans
itor
atio ions s in Closu
e Crit iter eria ia
ations of Engage ageme ment t Data ta and Future e Use e and d Ae Aesth sthetic tics s Principle iple
and how the entire application (Water Licence, Land Use Permit, FCRP, Designs and Monitoring Programs) is intertwined.
14 14
Closure Activities Staged Reclamation Security Return Post Closure Monitoring Success Indicators
Are the criteria achieved? Are contingency or remedial actions required?
Final/Complete Reclamation Security Return Criteria Achieved
Reclamation Completion Report Performance Assessment Report
15 15
Revie iewe wer Concern erns
Closure re Objecti tive Origi ginal Closure re Criteri ria Revised Closure re Criteri ria (revise sed criteri ria in blue font) t) Primary ry Reclamati tion
ties (new activiti ties s in blue font) t) Post-Clos
re Inspect ction
/or Monitor toring (new w details in blue font) t)
NP2 – Physically stable PK containment area to limit risk of failure that would affect safety of people or wildlife. 1. Physical Stability Acceptable results, as identified in NP1, of visual monitoring for deformation and degradation for a minimum of three years Post-Closure as part of site geotechnical inspections completed and signed off by a professional engineer. 1. Chemical Stability Not applicable as this is a physical stability
in SW3. 1. Future Use and Aesthetics Future use and aesthetics will be met through physical criteria as described in NP2-1. Final grading will reflect surrounding topography. 1. Physical Stability Acceptable results, as identified in NP1, of visual monitoring for deformation and degradation for a minimum of three years Post- Closure as part of site geotechnical inspections completed and signed off by a professional engineer. 1. Chemical Stability Not applicable as this is a physical stability
SW3. 1. Future Use and Aesthetics Future use and aesthetics will be met through physical criteria as described in NP2-1. Final grading will reflect surrounding topography. Final landscape inspected and submission of as-built conditions in a summary report completed by a professional engineer. Closure geotechnical monitoring. The WMP and North Pile sumps will be covered to stabilize accumulated sediments. Re-grading the slope of the west perimeter embankment of the Starter & East Cells. Infilling of the interior compartments of the Starter & East Cells. Placement of a final cover layer of coarse material over the entire North Pile for erosion protection purposes. Construction of swales and spillways on the final surficial cover of the North Pile to the perimeter ditches and influent storage ponds. Area inspected and as-built drawing is deemed acceptable and signed-off by a professional engineer. Geotechnical inspections (visual) of the site will occur Post-Closure in concert with the site geotechnical inspection and monitoring program. Thermal monitoring will be completed using thermistors that will be installed in the North
required to achieve stable slopes, but may enhance it.
16 16
FCRP
specifically identify the Plans associated with each monitoring program
Plan.
included directly in the criteria to acknowledge engagement data; details are provided in the specific Plan(s).
contingency actions are described Table 5.7 in Section 5.6 of the FCRP.
Revie iewe wer r Concern erns
17 17
18 18
19 19
the criteria must be met in order to demonstrate successful achievement of criteria.
states: Closure criteria may also have a temporal aspect to consider (e.g., a standard may have to be met for a pre-defined number of years).
criteria do not require monitoring beyond successful completion of the objective. If the criteria are not met after the initial three years of monitoring, then monitoring will continue until the criteria are achieved for a three year period.
Revie iewe wer Concern erns
achieved/once performance assessment report has been approved by the Board
20 20
habitat and safe use for people, in designing reclamation activities for chemical stability of surface water and seepage.
fish health, and drinking water quality. These elements have been incorporated in the chemical stability criteria.
terminology, as shown on the next slide
recommended
Revie iewe wer Concern erns
closure criteria and supported by community engagement feedback or TK evidence
21 21
Closu sure Objecti tive Closu sure Criteria Prima mary Reclama mation
ties es Post st-Closu
Insp specti ction
and/or /or Monito toring Site Wide SW4 – Mine e areas are physi ysica cally y sta table and safe for use by peopl
e and wildlife
1. Physical Stability Acceptable results of visual monitoring for deformation and degradation for a minimum of three years Post-Closure as part
professional engineer. 2. Chemical Stability Not applicable as this is a physical objective. Chemical stability is addressed through site wide and infrastructure objectives (SW1, I1, and I3). 3. Future Use and Aesthetics Future use and aesthetics objectives are met through physical stability criteria as described in SW4-1.
Final grading will promote positive drainage towards pre-disturbance drainage pathways where possible. Drainage pathways will be established for long- term stability to avoid issues with erosion. Engineered earthen structures remaining at the site (i.e., North Pile) will be physically stable. See NP closure objectives below for details specific to stability of mine waste areas. Reclamation of fresh water intake facilities, the effluent diffuser and other aquatic habitats per the Fish Habitat Compensation Plan developed in consultation with DFO. Removal of all buildings, equipment, and surface hazards.. Geotechnical inspections (visual) of the site will occur Post- Closure in concert with the site geotechnical inspection and monitoring program. Additional monitoring will
Pile area (See NP closure objectives below).
Revised ed wording: ing: The principle of future use has been considered through identification of chemical stability criteria for surface and seepage water quality to support safe use of water bodies by people, vegetation, aquatic life, and wildlife. Site inspections by SLEMA and community fish-tasting (where requested) will be conducted to provide on-going community input into this objective.
22 22
incorporated in the FCRP.
provides a summary of how the input has been incorporated, and provides cross- reference to the main document of the FCRP.
explicitly demonstrate the linkage between engagement data and the proposed closure
programs
Revie iewe wer Concern erns
23 23
and provides cross-reference to the main document of the FCRP
3. Engagement Plan
Revie iewe wer r Concern erns
24 24
include the following:
design criteria;
highlighted as a concern by stakeholders;
integration of TK with professional engineering judgement; and
monitoring will continue until site stability is achieved.
Revie iewe wer Concern erns