SLIDE 1 Filling line & Lyo Interface (one Isolated system)
‘Case Study’
By Ben Riepe 608-562-7735 briepe@walkerbarrier.com www.walkerbarrier.com
SLIDE 2 Discussion Points
Key design steps of a custom capital Isolator equipment project Dealing with existing equipment for design interface Dealing with existing equipment for design interface Fundamentals of Project Management that drive a successful solution
- IE) design review approval process &
communication of milestones
SLIDE 3 Design Criteria to set the stage for this particular
- application. (note: criteria is different for every
custom application within Pharma facility process)
Do you have a cycle development study involving injectables and/or vaccines? Are you testing phase1 toxicity levels (small runs)? Are you testing phase1 toxicity levels (small runs)? Do you want expanded capabilities for phase3 using a Lyo? Are you limited on space? Do you need to contend with any existing equipment?
SLIDE 4
Step1: Define the room layout – provided by client or A&E Firm
SLIDE 5
Step2: Concept Development (Layout & Flow)
SLIDE 6 Biggest Constraints
- The room layout is fixed (entrance on left side)
- The transfer Isolators are existing (this locks the size
- f these systems & vial capacity)
SLIDE 7 Existing Transfer Isolator
flow system.
(moves from room to room) room)
a remote vHP generator
SLIDE 8
- Feasibility of Isolation HVAC around layout
- What are the necessary filling line speeds & lyo capacity
- How does one transfer vials from filler to lyo
From concept to details
SLIDE 9
- What is the max filler speed needed? 80 vials/min (vol. 10ml)
- What is the max lyo capacity needed? 2000 vials
SLIDE 10 How to transfer from Filler to Lyo under a sterile environment?
- Common layout in Pharma facilities is to have the Filler & Lyo
remote from each other
- Requires either an AGV ‘automatic guided vehicle’ or a sterile
UAF transfer chamber
Solution for this application: Half-suit
SLIDE 11
Half-suit photo example
SLIDE 12
Half-suit layout placed in concept dwg
SLIDE 13
Half-suit (circle) Plan View layout concept
SLIDE 14 Isolated Process (infeed)
Depyrogenation Oven Interface Isolator to pre- sterilize empty vials before transfer from 3-glove to Filler Process doesn’t stop with just the filling, there is a just the filling, there is a chain of Isolation required in many to most cases. Ie) formulation, autoclave,
SLIDE 15 Outfeed Sterility Testing
the Filler to a dedicated Sterility Testing Isolator as well.
- Every piece of Isolated
- Every piece of Isolated
equipment must go through the same design criteria to determine it’s fit, placement, and need.
SLIDE 16 Viable & Non-Viable Monitoring
viable and non-viable monitoring are located inside the Isolator next to the filling head
particulate monitoring probe
- There are (4) viable
- There are (4) viable
monitoring probes within the Isolator
monitoring in the transfer units being that these came direct from a depro oven with sterilized transfer
SLIDE 17 Viable & Non-Viable Monitoring
continued.
thru plate in Isolator, and media is located
- utside the Isolator.
- Easier to have
media outside as media outside as you don’t have to manipulate pieces inside the Isolator and disturb the environment & media change outs are quick and simple
SLIDE 18 Mock Up Construction
Mock ups are an important part of isolator design. Construction is of wood and often uses actual and often uses actual components. Operators can perform ergonomic studies before final design.
SLIDE 19 Mock-up Preparations
Side view showing HVAC stack-up, port placement, & filler layout
SLIDE 20 Mock-up Review
Purpose:
- define ergonomic overlap to process
- confirm integration & equipment fit
- gives a visual of the process
SLIDE 21
Mock-up Ergonomic Testing
SLIDE 22
Mock-up (including internal filler & gloveports for ergo placement)
SLIDE 23
Refine technical details into a 3D print
SLIDE 24
Approval Process
Involves a technical review that targets
Mechanical Interfaces & Mock-up cross reference Controls layout and communication Understanding of utility location & requirements Process flow cross reference Approval to Fabricate from authorized figure @ Client site. (Typically signed approval of a functional and/or design specification, P&ID, and CAD drawing)
SLIDE 25 3D cross sectioning
placed from concept to mock- up to 3D layout.
give good visual give good visual understanding of the design for the customer, it is also used as the basis for the details prints for fabrication.
SLIDE 26 3D layout cross section
with integrated equipment placed into the shell the shell
to client assist in approvals
to vendor alleviate major interferences
SLIDE 27
Approval Process - continued
Need the key decision makers in the capital approval process from start to finish Good ‘team’ decision maker requirements
‘Process Engineer’ Full understanding of client process ‘Project Lead’ Client funding & timing constraints ‘Project Lead’ Client funding & timing constraints ‘Validation Engineer’ – What documentation & testing is required. ‘Safety’ – Has a Haz OP been executed pre-approval
SLIDE 28 Build Process
The fabrication of the shell: view of the interface for the Lyo The fabrication of the shell: view of the interface for the Lyo
Once system Once system is vendor is vendor manufacturin manufacturin g, it is g, it is extremely extremely difficult to difficult to change the change the design. design. At this point it At this point it At this point it At this point it is in the is in the hands of hands of vendor vendor Project Project Management Management to drive this to drive this to FAT to FAT
SLIDE 29
Build Process – cont.
Internal Internal view of view of half half-suit suit interfaced interfaced with lyo on with lyo on this same this same design pre design pre- FAT FAT FAT FAT
SLIDE 30
Lyo Door Interface
Door Design & clearance ties into Half-suit design & position. Davit style Swing bolts Swing bolts Recessed wall flange
SLIDE 31
FAT photo – internal view of inlet & integrated filler
SLIDE 32 Fully Integrated @ FAT
mechanically and electrically integrated @ vendor cleanroom site for full FAT check-
- uts and protocol
- uts and protocol
execution
mounted to the flange
Isolator.
SLIDE 33 FAT Testing
from as simple as surface finish & dimensional dimensional checks
involved DOE type studies: UAF & airflow smoke testing
SLIDE 34 Shipping & Installation Preparations
broken down to the key dimensions for door and room clearances & reassembled reassembled
- n-site
- In this particular
case, the design required all HVAC and components on top of the shell to be removed
SLIDE 35 Outer view in facility
HVAC, valving, & components are covered by stainless steel flashing.
conforms to the angles in the drawing and mock-up needed to accommodate the room constraints and process.
SLIDE 36 Conclusions:
- Design is key, but it takes a good team with specified tasks and
understanding of what alleviates big timing & costs consequences for both the vendor & client
- No matter how off the shelf the Pharma industry tries to push to for process
equipment, there continues to be a growing need for custom design due to a multitude of circumstances.
- Overall....no matter how unique an application, if the correct
steps are put in place to validate feasibility studies from both the clients needs and vendors capabilities, in the end you can and will always find an optimal solution.
SLIDE 37
Thank You
Q&A