Field Cage Mockup Status Mike Wilking Stony Brook University DUNE - - PowerPoint PPT Presentation

field cage mockup status
SMART_READER_LITE
LIVE PREVIEW

Field Cage Mockup Status Mike Wilking Stony Brook University DUNE - - PowerPoint PPT Presentation

Field Cage Mockup Status Mike Wilking Stony Brook University DUNE Engineering Meeting April 27, 2016 1 Field Cage Design Original Work on the mockup began Design last month We are currently assembling the original field cage


slide-1
SLIDE 1

Field Cage Mockup Status

Mike Wilking Stony Brook University DUNE Engineering Meeting April 27, 2016

1

slide-2
SLIDE 2

Field Cage Design

  • Work on the mockup began

last month

  • We are currently assembling

the original field cage design

  • Cross bracing I-beams were

not included

  • For this first mockup, we are

not planning extensive tests

  • f manipulation, mechanical

stability, cold testing, etc.

  • For now, we are developing

assembly procedures, QC of prefabricated parts, production of in-house machined component, etc.

Original Design New Design

2

slide-3
SLIDE 3

Profiles

  • Currently using prefabricated stainless steel profiles
  • The pieces we received were pinched closed at the ends
  • Cut to length using a (somewhat dull) bandsaw (~1 hour for 50 profiles)
  • Ends we deburred with a grinding wheel, filing, and sanding (~6 hours for 50 profiles)
  • Goal was to remove loose pieces; endcaps can handle minor imperfections
  • Decision on stainless steel vs extruded aluminum in May?
  • If aluminum, will post-processing be necessary, or will these come cut to length?
  • There are concerns about scratching the profiles surfaces during assembly
  • Stainless steel was quite resilient; aluminum may be more delicate
  • In the new design, the profiles extend further from the I-beams
  • Some concern about mechanical deformation depending on the final material

3

slide-4
SLIDE 4

I-beams

  • Profiles holes were cut via waterjet
  • In a few places, the I-beam coating began to peel, exposing the rough fiberglass

surface below

  • All of the cut holes and I-beam ends had a similar rough surface
  • Filing/sanding may be an option (with a solvent to minimize dust)
  • Screw holes did not always line up properly due to

slight twists in the I-beams and rounding in the I-beam fabrication

  • Some amount of filing will likely be necessary
  • Can tiny fiberglass shards, emitted in the LAr, cause any

problems? Bad for the pumps?

  • Could consider coating the exposed surfaces. Epoxy?
  • The rough surface of the profile holes can potentially scratch profiles
  • We may want to consider a coating for these holes
  • This problem may be a larger issue for aluminum profiles

4

slide-5
SLIDE 5

Component Machining

  • Profiles are secured to the I-beam using slipnuts
  • Several versions have been machined at Stony Brook with different

screw sizes, thicknesses, etc.

  • Can we continue with 304 Stn. Stl. even with aluminum profiles?
  • We currently have a small number of endcaps
  • We are looking into machining some more
  • The mechanism to attach endcaps to profiles

has not yet been finalized

5

slide-6
SLIDE 6

Assembly Status

  • Initial assembly of I-beams and profiles is complete
  • We should soon receive additional nuts, M4 ↔ M6

screws, etc. in a few different material types (stn stl, nylon, G10?)

  • Different material options are under consideration
  • Ground planes from CERN should arrive this week

6

slide-7
SLIDE 7

Next Steps

  • The amount we can learn from further work with the old

design is limited

  • We hope to move to the new, 2 I-beam, design in the

next few weeks

  • A design for the temporary manipulation frame for the

2 I-beam design is ready

  • We plan to begin fabricating this soon
  • This will allow us to begin manipulating an assembled

module using the overhead crane (lifting, tilting, etc.)

  • Preparations are underway for the clean tent (gray room)

and cold test setup

  • This isn’t necessary for the first few mockups that will

be sent to Ash River

7