Board Presentation FEASIBILITY STUDY South Montgomery Community School Corporation March 14, 2016 SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Presentation Outline Review Previous Information Elementary Schools Findings New


slide-1
SLIDE 1

FEASIBILITY STUDY

South Montgomery Community School Corporation

March 14, 2016

Board Presentation

slide-2
SLIDE 2

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Presentation Outline

 Review Previous Information

 Elementary Schools Findings

 New Information

 Southmont Junior High  Southmont High School

 Building  Campus Master Plan

 District Needs

 Cost summary  Schedule  Questions/Answers

slide-3
SLIDE 3

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Walnut Elementary School

Site/Circulation

  • 1. Dual stripe for

handicap parking

  • 2. Improve security

camera coverage

  • 3. Selective playground

equipment replacement / improve accessibility

  • 4. Replace sewage

treatment plant

slide-4
SLIDE 4

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Walnut Elementary School

Building Envelope

  • 1. Replace exterior doors

and windows

  • 2. Replace main1995 roof
  • 3. Create wind screen/
  • verhang at main entry
slide-5
SLIDE 5

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Walnut Elementary School

Building Interior/Systems

  • 1. Expanded secure entry

vestibule

  • 2. Improve office visibility/

function

  • 3. Renovate main restrooms
  • 4. Repurpose music room
  • 5. Combine music/ band
  • 6. Would gain four classrooms

with 6th grade relocation

  • 7. Consider potential for life

skills classroom

slide-6
SLIDE 6

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

All Elementary Schools

Building Interior/Systems

  • 1. Replace HVAC system
  • 2. Selective technology

improvements

  • 3. Finishes improvements
  • 4. Replace chalkboards
slide-7
SLIDE 7

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Ladoga Elementary School

Site/Circulation

  • 1. Improve control/flow at

drop-off/pick-up

  • 2. Improve creek flow at

culvert to eliminate basement flooding

  • 3. Expand sidewalk for bus

loading

  • 4. Selective playground

equipment replacement/ improve accessibility

slide-8
SLIDE 8

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Ladoga Elementary School

Building Envelope

  • 1. Replace exterior doors

and windows

  • 2. Replace 1998 shingle

and 2009 gym roofs

  • 3. Add vestibule to main

entry

slide-9
SLIDE 9

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Ladoga Elementary School

Building Interior/Systems

1. Provide new secure entry vestibule 2. Relocate administrative offices to larger/more functional location 3. Repurpose existing office for small group/other 4. Improve restroom ADA compliance 5. Improve flexibility for team collaboration 6. Selective kitchen equipment replacement 7. Replace seating handrails/stage curtain 8. Would gain one classroom with 6th grade relocation * Generally improve acoustics in all classrooms

slide-10
SLIDE 10

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

New Market Elementary School

Site/Circulation

  • 1. Create new bus loading

lot

  • 2. Change existing bus

loading to parking

  • 3. Selective playground

equipment replacement/ improve accessibility

  • 4. Remove portable unit
slide-11
SLIDE 11

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

New Market Elementary School

Building Envelope

  • 1. Replace 1995 metal

roof and 1999 shingle roof

  • 2. Resolve fascia/leak

problems

slide-12
SLIDE 12

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

New Market Elementary School

Building Interior/Systems

  • 1. Expanded secure

vestibule

  • 2. Expanded secure office

waiting

  • 3. Replace bleachers
  • 4. Add second set of

restrooms

  • 5. Improve serving line

flow/ replace seating

  • 6. Renovate staff lounge
  • 7. Add story areas
  • 8. Would gain three

classrooms with 6th grade relocation

slide-13
SLIDE 13

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Southmont Junior High

Building Interior/Systems

  • 1. Secure corridor near cafeteria
  • 2. Repurpose Corp. Admin. to

accommodate 6th Grade

  • 3. Repurpose lower level storage

for JH wrestling

  • 4. Add time-out room at SE

classroom

slide-14
SLIDE 14

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Southmont High School

Building Interior/Systems

  • 1. Replace door hardware

as needed

  • 2. New digital cameras
  • 3. Replace 1996 HS and

2007 JH gym roofs

  • 4. Remodel CTE, Woods

Lab, Ag./Hort. and Culinary Arts

slide-15
SLIDE 15

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Southmont High School

Campus Master Plan

slide-16
SLIDE 16
slide-17
SLIDE 17

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

District Needs

Administrative Offices

  • 1. New freestanding facility

at JH/HS Campus Transportation Center

  • 1. New facility located at

JH/HS Campus Administrative Offices

  • 1. Provide fiber optic

connections from three elementary schools JH/HS Campus

slide-18
SLIDE 18

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Project Cost

Site/Circ. Safety/Sec. Building Env. Building Int. Building Sys. Total

High School 5,696,500 95,000 487,200 1,410,500 7,689,200 Junior High School 45,000 281,350 326,350 Walnut ES 300,000 102,066 993,396 1,063,995 1,313,369 3,772,826 Ladoga ES 520,956 673,692 860,736 1,292,306 3,697,690 New Market ES 207,500 313,154 1,369,809 1,066,770 2,082,440 5,039,673 Administrative Offices 1,476,000 Transportation Center 3,731,250 District-wide Needs 926,640 Construction Costs 6,554,000 1,076,176 3,524,097 4,683,351 4,688,115 26,659,629 Soft Costs 6,664,907 Total Project Costs $ 33,324,537

slide-19
SLIDE 19

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Schedule/Major Milestones

2016 March 14 Board Meeting April-May Community Meetings June 13 Board Meeting- Final Study Presentation

slide-20
SLIDE 20

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Feasibility Study