Facility Bond Program Update - VHS June 18, 2020 Dr. Matt Doyle, - - PowerPoint PPT Presentation

facility bond program update vhs
SMART_READER_LITE
LIVE PREVIEW

Facility Bond Program Update - VHS June 18, 2020 Dr. Matt Doyle, - - PowerPoint PPT Presentation

Facility Bond Program Update - VHS June 18, 2020 Dr. Matt Doyle, Superintendent Ami Shackelford, Asst. Sup., Business Services John Wathen, Executive Director Agenda Lease Leaseback Construction Delivery Method The Design Process;


slide-1
SLIDE 1

Facility Bond Program Update - VHS

June 18, 2020

  • Dr. Matt Doyle, Superintendent

Ami Shackelford, Asst. Sup., Business Services John Wathen, Executive Director

slide-2
SLIDE 2

Agenda

2

  • Lease Leaseback Construction Delivery Method
  • The Design Process; from Schematic Design to Design

Development, to Construction Documents

  • Project Timeline and the GMP (Guaranteed Maximum Price)
  • Vista High Softball Field Title IX and ROM Cost Estimate Options
  • Vista High New Classroom Buildings - Schematic Overview
  • Vista High Ag Department Project Scope Discussion
slide-3
SLIDE 3

Facilities Funding Sources by Phase

3

Funding Type Original Amount

  • f Funds

Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Measure Funds

$247,000,000 $ 56,320,000 $ 49,400,000 $ 49,400,000 $ 49,400,000 $ 42,480,000

Redevelopment Funds

$20,000,000 $ 4,000,000 $ 4,000,000 $ 4,000,000 $ 4,000,000 $ 4,000,000

State Matching Funds

$18,000,000 $ - $ 9,000,000 $ - $ 9,000,000 $ -

Developer Fees

$5,000,000 $ 1,000,000 $ 1,000,000 $ 1,000,000 $ 1,000,000 $ 1,000,000

General Fund

$2,000,000 $ 400,000 $ 400,000 $ 400,000 $ 400,000 $ 400,000

Total Available Funds $292,000,000 $ 61,400,000 $ 63,800,000 $ 54,800,000 $ 63,800,000 $ 48,200,000

slide-4
SLIDE 4

4

Lease Leaseback (LLB) Construction Delivery Method

slide-5
SLIDE 5

Project Timeline & Lease Leaseback (LLB) Process

5

slide-6
SLIDE 6

6

GUARANTEED MAXIMUM PRICE (GMP) AND THE DESIGN PROCESS

slide-7
SLIDE 7

Construction Delivery Method - Lease Leaseback

  • Lease Leaseback (LLB) Delivery method

○ District selects an architect to design the project ○ Construction firm is solicited and awarded to construct the project ○ District, architect and construction firm work as a team to develop, design and construct the project ○ Once the design phases are complete, the LLB contractor will bid the project and submit a Guaranteed Maximum Price (GMP) to the District for approval

■ Cost is fixed and change orders are exceedingly rare, increases in cost during construction become the responsibility of the contractor, not the District

  • VUSD has a LLB agreement with Erickson Hall Construction

Company at Vista High for construction of new classrooms, ag department improvements, and athletic fields improvements

7

slide-8
SLIDE 8

The Design Process

8

  • Schematic Design (SD) - First phase of design where the architect and

District hold meetings, gather input, and formulate input into plans for review and board approval. Multiple iterations and ideas can be considered to ensure District goals are met

  • Design Development (DD) - Second phase where design team will

engage with consultants and engineers to start programming the features and elements into the project. ○ Changes to the schematic design at this phase may trigger additional design costs to the District

  • Construction Documents (CD) - Third phase of design where

documents are finalized and submitted to DSA. Final input from DSA is incorporated into the construction plans which are then used to obtain final costs from contractors, and establishing the GMP for the project

slide-9
SLIDE 9

9

VHS SOFTBALL FIELD

slide-10
SLIDE 10

Vista High Softball Field Title IX And ROM Estimate Options

10

  • A GMP action item is being presented for consideration to address Title

IX issues at Vista High, this package also includes drainage improvements, new tennis courts, basketball courts, pickleball courts, and small parking lot. The latter elements are beyond the Title IX

  • requirements. Construction could commence immediately if approved,

GMP $5,613,697

  • A ROM* estimate has also been provided as an option instead of the

above GMP. This option addresses the Title IX issues and resurfacing of the existing courts. The drainage, new courts and parking lot has been

  • removed. ROM $4,784,016. The ROM option will require nine months

for design and DSA-approval prior to obtaining final GMP cost. Construction could commence Summer 2021. ○ ROM amount does not includes additional $300K of architect and

  • ther soft costs. ROM option would be reduced costs of $529,000

*ROM - Rough Order of Magnitude estimate-only, requires design and future bid solicitations to determine actual costs for construction

slide-11
SLIDE 11

11

VHS GMP Softball Field GMP Schematic Overview Option #1

slide-12
SLIDE 12

12

VHS Softball Field ROM Schematic Overview (Option #2)

Tennis Courts Softball Field

slide-13
SLIDE 13

13

VHS NEW CLASSROOM BUILDINGS

slide-14
SLIDE 14

14

VHS New Classroom Building Schematic Overview

  • Building 200 is a

Three-story building located adjacent to the stadium and across from the gymnasium

  • Building 100 is a

Two-story building located along Bobier at the entrance to the campus

slide-15
SLIDE 15

15

VHS New Classroom Building Schematic Overview

Building 200 facing the campus core. This is a 3-story building with student, staff and gender-neutral restrooms located on the 2nd and 3rd floors, roll up doors on the 1st floor for JROTC and athletics, ten science classrooms, ten general education classrooms, one large flex-suite, and staff workrooms

slide-16
SLIDE 16

16

VHS New Classroom Building Schematic Overview

Building 200 facing the stadium. Ground level here are science classrooms with easy access to outside. The 3rd floor will have 10 general education classrooms and one large flex-suite. A flex-suite is two over-sized rooms connected with a movable partition to allow for large collaboration space

slide-17
SLIDE 17

17

VHS New Classroom Building Schematic Overview

Building 100 facing from Bobier Drive. This is a 2-story building with

student, staff and gender-neutral restrooms located on the 1st and 2nd floors, 18 general education classrooms, one large flex-suite on the 2nd floor, and staff workroom on the 2nd floor

slide-18
SLIDE 18

18

VHS New Classroom Building Schematic Overview

Building 100 facing from campus core. This is a 2-story building with student, staff and gender-neutral restrooms located on the 1st and 2nd floors, 18 general education classrooms, one large flex-suite on the 2nd floor, and staff workroom on the 2nd floor

slide-19
SLIDE 19

New Classroom Buildings Schematic Design

  • Here is the schematic drawings for Vista High Schools’ new

classroom buildings from Alpha Studio Design Group

  • Approval is required of schematic drawings prior to entering into the

Design Development phase when engineers and consultants will be utilized by the design team

  • Once into the Design Development phase if changes are made to the

schematic design of the project it could result in additional costs to the district

  • The current ROM estimate for this schematic drawing is $52,955,988,

and the original ROM was $37,786,880

19

slide-20
SLIDE 20

20

VHS Agricultural Dept (Ag Dept) Facilities Project

slide-21
SLIDE 21

AG Department Scope

  • VHS AG Department scope of work for only ADA and safety improvements

and Alpha Studio Design Group proposal for design services

  • Original expanded scope of work was to be funded in large part through a

CTE grant which was not awarded to VUSD

  • These additional elements have been removed from current scope to reflect
  • nly ADA and Safety issues as an option for the board
  • Initial Scope includes:

○ Removal and replacement of warped and lifting concrete ○ Provide new accessible gate and hardware, ○ Provide new accessible pathways to and into the greenhouses, ○ Provide new ADA parking adjacent to the facility, removal and construction

  • f new hay barn, removal of non-compliant concession stand

○ Installation of sewer separator to prevent animal waste from being discharged directly into the schools’ sewer system

  • Future Project - CTE Education Building

21

slide-22
SLIDE 22

Ag Dept ADA and Safety Improvements Scope

22

slide-23
SLIDE 23

Summary Next Steps

  • Board Approval requested for Vista High School Classroom from

Schematic Design to Design Development on June 18 Board agenda

  • Board Approval for Vista High School Girls Softball Field GMP or

Option #2 (ROM) on June 18 Board agenda

  • Board Consensus on scope for of the AG Department
  • Update for Beaumont and Bobier Projects on the June 25 Board

meeting

23