Empire Stores Update Community Advisory Council Nov 26, 2013 Empire Stores design/construction update Design o Schematic design phase (~25%) o SHPO approval o LPC courtesy review in Dec Construction o Stabilization to begin early 2014 o


slide-1
SLIDE 1

Empire Stores Update

Community Advisory Council Nov 26, 2013

slide-2
SLIDE 2
  • Design
  • Schematic design phase (~25%)
  • SHPO approval
  • LPC courtesy review in Dec
  • Construction
  • Stabilization to begin early 2014
  • Structural work in mid‐2014
  • Completion in Q3 2015

Empire Stores design/construction update

2

slide-3
SLIDE 3
  • Jul 2012 – Solicitation for feedback from CAC on RFP document
  • Aug 2012 – RFP feedback provided by CAC
  • Sep 2012 – BBP issues Empire Stores RFP
  • Dec 2012 – RFP responses due
  • Mar 2013 – Design presentation given to CAC
  • Mar 2013 – Design workshop with CAC Design Committee
  • Apr 2013 – Design feedback provided by CAC
  • Jun 2013 – DUMBO community meeting; presentation of responses
  • Sep 2013 – BBP Board awards contract to Midtown Equities
  • Sep 2013 – Design presentation of Midtown proposal to CAC
  • Nov 2013 – DUMBO community meeting; presentation of Midtown proposal
  • Nov 2013 – Design presentation (25% design) to CAC Design Committee
  • Nov 2013 – Design presentation to CB2 Land Use Committee
  • Dec 2013 – Design presentation to CB2 Full Committee
  • Dec 2013 – Design presentation to Landmarks Preservation Committee
  • Early 2014 – Design presentation (75% design) to CAC Design Committee

Community involvement in Empire Stores process

3

Prior to issuing RFP RFP issued Selection process Post‐selection design review

slide-4
SLIDE 4

Size of retail plan Reduced by more than 50% Size of roof addition Reduced by 15% Size of event space Reduced by 60% Location of event space Relocated away from residential Amount of rooftop retail Reduced by 60% Location of rooftop retail Relocated away from residential Roof material Changed from solar panels to green roof Size of loading docks Reduced from 4 to 3 bays Size of public roof garden Size increased by 40%

Design has evolved to address community concerns

Community feedback received Changes to development plans

4

slide-5
SLIDE 5

Empire Stores – first design revision

5

Original Midtown submission First design revision

slide-6
SLIDE 6

Empire Stores – second design revision (current)

6

slide-7
SLIDE 7

Current design in neighborhood context