electric generation and transmission on the railbelt
play

ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT Joe Griffith - PowerPoint PPT Presentation

ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT Joe Griffith General Manager, MEA Chief Executive Officer, ARCTEC Anchorage Mayor s Energy Task Force November 6, 2013 1 RAILBELT MAKEUP Electrical utilities are all cooperatives or


  1. ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT Joe Griffith General Manager, MEA Chief Executive Officer, ARCTEC Anchorage Mayor ’ s Energy Task Force November 6, 2013 1

  2. RAILBELT MAKEUP Electrical utilities are all cooperatives or municipalities • Anchorage Municipal Light & Power • • Seward Electric System Chugach Electric Association • Golden Valley Electric Association • • Homer Electric Association Matanuska Electric Association • 2

  3. RAILBELT TRANSMISSION SYSTEM Connects utilities • Facilitates economic dispatch • Transfers power • • Shares Reserves 3

  4. RAILBELT ELECTRICAL GENERATION 1 – Eklutna Generation Station (EGS) 2 – Bradley Lake 3 – Soldotna 4 – Nikiski 5 – Fire Island 6 – SPP 7 – ML&P Plants 2 & 2A 8 – Beluga 9 – Mount Spurr Geothermal Project 10 – Watana 11 – Eva Creek 12 – Healy 2 (HCC) 13 – Battery Energy Storage System (BESS) 14 – Zehnder 15 – North Pole 4

  5. GENERATION All utilities have or will soon have their own generation capability • New generation cost is approximately $1 billion • • Utility balance sheets are stressed • No additional debt-assuming capability 5

  6. RAILBELT GENERATION SUITE Chugach – Beluga, South Anchorage, IGT, Cooper Lake hydro, Eklutna hydro • AML&P – Plant 1, 2, & 2A (soon to be built), Eklutna hydro • • GVEA – North Pole, Eva Creek Wind, Healy 1 & 2, Aurora (IPP), BESS, Zehnder MEA – Eklutna Generation Station, Eklutna hydro, + 2 small IPPs • HEA – Nikiski combined cycle, Soldotna, Bernice Lake • • SES – Seward plant Note: All above participate in Bradley Lake hydro (state-owned IPP)- 124 mW capacity 6

  7. SITUATION New generation system changes playing field due to transmission constraints • Limits Bradley Lake power deliveries when needed most. • • Railbelt economy demands reasonably-priced power (as does the rest of Alaska) 7

  8. AEA TRANSMISSION STUDY Southern section upgrades proposed: • Quartz creek to University (AC) • • Additional conductor from Quartz Creek to Daves Creek • 230 kV upgrade from Daves Creek to University s/s DC tie line from Bernice Lake to Beluga • 2 nd 115kV line from Bradley Junction to Soldotna • Anchorage battery • • Northern Upgrades 230 kV Lake Lorraine to Douglas upgrade • • Douglas to Healy upgrade 8

  9. 9

  10. 10

  11. 11 Slater Consulting August 2013

  12. AEA TRANSMISSION STUDY – CASES MODELED • Scenario 1: All transmission upgrades • Scenario 2: Southern transmission upgrades • Scenario 3: Northern transmission upgrades • Scenario 4: No transmission upgrades 12

  13. AEA TRANSMISSION STUDY – NO TRANSMISSION UPGRADES The system operates as a 5 separate utilities • Each provides its own reserves • The interface limit for Kenai North is 75 MW • • The transfer limit from Stevens (Talkeetna) to Cantwell is 75 MW North Pole CC is “must-run” Oct through Mar • • Bradley Spin is only 10 MW Commitment/Dispatch hurdles exist between all utilities • Opportunity cost of over $100 million per year • 13

  14. ARCTEC 2014 REQUESTS Unconstrain Bradley Lake • • Silvertip Creek to Hope Substation 115 kV transmission line 4,500,000 • Powerline Pass to Indian 115 kV transmission line 5,000,000 • Eklutna hydro transmission upgrade 4,000,000 $24,000,000 • Battle Creek Diversion into Bradley Lake 50/50 Shared cost between State of Alaska and utilities. • TOTAL REQUEST: $37,500,000 14

  15. INDEPENDENT POWER PRODUCERS (IPPs) Assert they can solve the problem Federal law: Public Utility Regulatory Policies Act (PURPA) • Avoided cost principle for Combined Heat and Power (CHP) utilities • • Must meet or beat avoided cost (2 types) • Firm and non-firm • Alaska RCA regulations mimic federal PURPA Rate of return: co-ops 3-5% / IPPs need 10%+ • • IPPs have filed with the RCA to disuage regulations IPPs pushing for Alaska statute changes to force utilities to accept their power at the • expense of ratepayers 15

  16. SHORT-TERM ENERGY DELIVERY MITIGATIONS Decongest the transmission system to facilitate optimum use of Bradley Lake energy and • capacity Maintain Cook Inlet gas market • • Foster more exploration in Cook Inlet Import LNG and/or propane • 16

  17. AEA TRANSMISSION STUDY – VALUE OF PROPOSED UPGRADES • $140,000,000 per year 17

  18. CONCLUSION Without a program to rectify transmission shortcoming asap • Cost of electricity will continue to rise • Possible savings will be forfeited • • Alaska will not achieve its alternative energy goal Railbelt will be captive to Cook Inlet natural gas pricing and supply issues • 18

  19. DISCUSSION / QUESTIONS 19

  20. AEA TRANSMISSION STUDY – ALL TRANSMISSION UPGRADES CASE Base Case • The system operates as a single pool with a single system reserve requirement • The interface limit for Kenai North is 125 MW • Anchorage battery is 25 MW Bradley spin is 27 MW • 20

  21. AEA TRANSMISSION STUDY – SOUTHERN TRANSMISSION CASES Case S1: Remove AC upgrades from Quartz Creek to University • The system operates as a single pool with a single system reserve requirement The interface limit for Kenai North is 100 MW • • Anchorage battery is 25 MW Bradley spin is 27 MW • Case S2: Remove DC tie • The system operates as a single pool with a single system reserve requirement The interface limit for Kenai North is 75 MW • Anchorage battery is 75 MW • Bradley spin is 27 MW • 21

  22. AEA TRANSMISSION STUDY – SOUTHERN TRANSMISSION CASES Case S3: Do both S1 and S2 • The system effectively operates as 2 pools • Railbelt minus HEA • Shared reserves • HEA • HEA provides its own reserves • The interface limit for Kenai North is 75 MW Bradley spin is 27 MW • Commitment/Dispatch hurdles exist between all other companies and HEA • 22

  23. AEA TRANSMISSION STUDY – SOUTHERN TRANSMISSION CASES Case S4: Case S3 + remove 2nd line from Bradley to Soldotna • The system effectively operates as 2 pools • Railbelt minus HEA • Shared reserves • HEA • HEA provides its own reserves • The interface limit for Kenai North is 75 MW Bradley spin is 10 MW • Commitment/Dispatch hurdles exist between all other companies and HEA • 23

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend