ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT Joe Griffith - - PowerPoint PPT Presentation

electric generation and transmission on the railbelt
SMART_READER_LITE
LIVE PREVIEW

ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT Joe Griffith - - PowerPoint PPT Presentation

ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT Joe Griffith General Manager, MEA Chief Executive Officer, ARCTEC Anchorage Mayor s Energy Task Force November 6, 2013 1 RAILBELT MAKEUP Electrical utilities are all cooperatives or


slide-1
SLIDE 1

ELECTRIC GENERATION AND TRANSMISSION ON THE RAILBELT

Anchorage Mayor’s Energy Task Force November 6, 2013

1

Joe Griffith General Manager, MEA Chief Executive Officer, ARCTEC

slide-2
SLIDE 2

RAILBELT MAKEUP

2

  • Electrical utilities are all cooperatives or municipalities
  • Anchorage Municipal Light & Power
  • Seward Electric System
  • Chugach Electric Association
  • Golden Valley Electric Association
  • Homer Electric Association
  • Matanuska Electric Association
slide-3
SLIDE 3

RAILBELT TRANSMISSION SYSTEM

  • Connects utilities
  • Facilitates economic dispatch
  • Transfers power
  • Shares Reserves

3

slide-4
SLIDE 4

4

RAILBELT ELECTRICAL GENERATION

1 – Eklutna Generation Station (EGS) 2 – Bradley Lake 3 – Soldotna 4 – Nikiski 5 – Fire Island 6 – SPP 7 – ML&P Plants 2 & 2A 8 – Beluga 9 – Mount Spurr Geothermal Project 10 – Watana 11 – Eva Creek 12 – Healy 2 (HCC) 13 – Battery Energy Storage System (BESS) 14 – Zehnder 15 – North Pole

slide-5
SLIDE 5

GENERATION

5

  • All utilities have or will soon have their own generation capability
  • New generation cost is approximately $1 billion
  • Utility balance sheets are stressed
  • No additional debt-assuming capability
slide-6
SLIDE 6

RAILBELT GENERATION SUITE

6

  • Chugach – Beluga, South Anchorage, IGT, Cooper Lake hydro, Eklutna hydro
  • AML&P – Plant 1, 2, & 2A (soon to be built), Eklutna hydro
  • GVEA – North Pole, Eva Creek Wind, Healy 1 & 2, Aurora (IPP), BESS, Zehnder
  • MEA – Eklutna Generation Station, Eklutna hydro, + 2 small IPPs
  • HEA – Nikiski combined cycle, Soldotna, Bernice Lake
  • SES – Seward plant

Note: All above participate in Bradley Lake hydro (state-owned IPP)- 124 mW capacity

slide-7
SLIDE 7

SITUATION

7

  • New generation system changes playing field due to transmission constraints
  • Limits Bradley Lake power deliveries when needed most.
  • Railbelt economy demands reasonably-priced power (as does the rest of Alaska)
slide-8
SLIDE 8

AEA TRANSMISSION STUDY

8

  • Southern section upgrades proposed:
  • Quartz creek to University (AC)
  • Additional conductor from Quartz Creek to Daves Creek
  • 230 kV upgrade from Daves Creek to University s/s
  • DC tie line from Bernice Lake to Beluga
  • 2nd 115kV line from Bradley Junction to Soldotna
  • Anchorage battery
  • Northern Upgrades
  • 230 kV Lake Lorraine to Douglas upgrade
  • Douglas to Healy upgrade
slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

Slater Consulting August 2013

11

slide-12
SLIDE 12

AEA TRANSMISSION STUDY – CASES MODELED

12

  • Scenario 1:

All transmission upgrades

  • Scenario 2:

Southern transmission upgrades

  • Scenario 3:

Northern transmission upgrades

  • Scenario 4:

No transmission upgrades

slide-13
SLIDE 13

AEA TRANSMISSION STUDY – NO TRANSMISSION UPGRADES

13

  • The system operates as a 5 separate utilities
  • Each provides its own reserves
  • The interface limit for Kenai North is 75 MW
  • The transfer limit from Stevens (Talkeetna) to Cantwell is 75 MW
  • North Pole CC is “must-run” Oct through Mar
  • Bradley Spin is only 10 MW
  • Commitment/Dispatch hurdles exist between all utilities
  • Opportunity cost of over $100 million per year
slide-14
SLIDE 14

ARCTEC 2014 REQUESTS

14

  • Unconstrain Bradley Lake
  • Silvertip Creek to Hope Substation 115 kV transmission line 4,500,000
  • Powerline Pass to Indian 115 kV transmission line

5,000,000

  • Eklutna hydro transmission upgrade

4,000,000

  • Battle Creek Diversion into Bradley Lake

$24,000,000

  • 50/50 Shared cost between State of Alaska and utilities.

TOTAL REQUEST: $37,500,000

slide-15
SLIDE 15

INDEPENDENT POWER PRODUCERS (IPPs)

15

Assert they can solve the problem

  • Federal law: Public Utility Regulatory Policies Act (PURPA)
  • Avoided cost principle for Combined Heat and Power (CHP) utilities
  • Must meet or beat avoided cost (2 types)
  • Firm and non-firm
  • Alaska RCA regulations mimic federal PURPA
  • Rate of return: co-ops 3-5% / IPPs need 10%+
  • IPPs have filed with the RCA to disuage regulations
  • IPPs pushing for Alaska statute changes to force utilities to accept their power at the

expense of ratepayers

slide-16
SLIDE 16

SHORT-TERM ENERGY DELIVERY MITIGATIONS

16

  • Decongest the transmission system to facilitate optimum use of Bradley Lake energy and

capacity

  • Maintain Cook Inlet gas market
  • Foster more exploration in Cook Inlet
  • Import LNG and/or propane
slide-17
SLIDE 17

AEA TRANSMISSION STUDY – VALUE OF PROPOSED UPGRADES

17

  • $140,000,000 per year
slide-18
SLIDE 18

CONCLUSION

  • Without a program to rectify transmission shortcoming asap
  • Cost of electricity will continue to rise
  • Possible savings will be forfeited
  • Alaska will not achieve its alternative energy goal
  • Railbelt will be captive to Cook Inlet natural gas pricing and supply issues

18

slide-19
SLIDE 19

DISCUSSION / QUESTIONS

19

slide-20
SLIDE 20

AEA TRANSMISSION STUDY – ALL TRANSMISSION UPGRADES CASE

20

Base Case

  • The system operates as a single pool with a single system reserve requirement
  • The interface limit for Kenai North is 125 MW
  • Anchorage battery is 25 MW
  • Bradley spin is 27 MW
slide-21
SLIDE 21

AEA TRANSMISSION STUDY – SOUTHERN TRANSMISSION CASES

21

Case S1: Remove AC upgrades from Quartz Creek to University

  • The system operates as a single pool with a single system reserve requirement
  • The interface limit for Kenai North is 100 MW
  • Anchorage battery is 25 MW
  • Bradley spin is 27 MW

Case S2: Remove DC tie

  • The system operates as a single pool with a single system reserve requirement
  • The interface limit for Kenai North is 75 MW
  • Anchorage battery is 75 MW
  • Bradley spin is 27 MW
slide-22
SLIDE 22

AEA TRANSMISSION STUDY – SOUTHERN TRANSMISSION CASES

22

Case S3: Do both S1 and S2

  • The system effectively operates as 2 pools
  • Railbelt minus HEA
  • Shared reserves
  • HEA
  • HEA provides its own reserves
  • The interface limit for Kenai North is 75 MW
  • Bradley spin is 27 MW
  • Commitment/Dispatch hurdles exist between all other companies and HEA
slide-23
SLIDE 23

AEA TRANSMISSION STUDY – SOUTHERN TRANSMISSION CASES

23

Case S4: Case S3 + remove 2nd line from Bradley to Soldotna

  • The system effectively operates as 2 pools
  • Railbelt minus HEA
  • Shared reserves
  • HEA
  • HEA provides its own reserves
  • The interface limit for Kenai North is 75 MW
  • Bradley spin is 10 MW
  • Commitment/Dispatch hurdles exist between all other companies and HEA