EDUCATION CENTER REUSE
Schematic Design
SCHOOL BOARD INFORMATION ITEM FEBRUARY 7, 2019
EDUCATION CENTER REUSE Schematic Design SCHOOL BOARD INFORMATION - - PowerPoint PPT Presentation
EDUCATION CENTER REUSE Schematic Design SCHOOL BOARD INFORMATION ITEM FEBRUARY 7, 2019 Agenda Overview Site Design Building Design Project Funding and Total Project Cost Estimate Recommendations SCHOOL BOARD
SCHOOL BOARD INFORMATION ITEM FEBRUARY 7, 2019
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 2
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 3
initially, and later to adapt to possible future instructional and grade level changes
Students
APS project website: https://www.apsva.us/education-center-reuse/
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 4
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 5
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 6
W-L HIGH SCHOOL
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 7 QUINCY STREET NEW ED CENTER MAIN ENTRANCE
PLAZA IMPROVEMENTS TERRACE IMPROVEMENTS MMTA- RECOMMENDED OFF-SITE IMPROVEMENTS (OPTION A) NEW “DO NOT ENTER” SIGNS NEW GROUND CONNECTION RAMP (SLOPE 1:12) AND FLUSH PAVING AT GENERALS’ WAY. GRADE DROPS 6.5’ BETWEEN ROAD CROSSING AND MAIN ENTRANCE NEW MULTI-USE COURT DIMENSIONS PAINTED ON EXISTING ASPHALT NEW BICYCLE PARKING, 30 BIKE CAPACITY POSSIBLE COVERED BICYCLE PARKING IN EXISTING GARAGE, ~40 BIKE CAPACITY 76 PARKING SPACES SITE PLAN INCORPORATES ALL RECOMMENDATIONS FROM THE MMTA
Exhibit A
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 8 MULTI-USE COURT ON RE-GRADED, CROWNED PLAYING SURFACE NEW ED CENTER MAIN ENTRANCE
PERVIOUS AREA IMPROVES STORMWATER MANAGEMENT AND FIRE TRUCK ACCESS
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 9
Spaces are to perform at the highest levels for the following:
all daylight and views are the same.
related to the perception of time of day
brain sense this.
possible for good color rendering
daylight and views, should be minimized
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 10
Exhibit B Legend Classrooms / Collaboration Commons / Support Instructional Support Administration Building Support
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 11
improving energy performance, and required upgrades to support an educational environment (including operable windows).
Exhibit C
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 12
a different frit density. This diagram is not an illustration of the actual visual condition; it is a quantitative documentation of the variations of the frit density. Exhibit D
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 13
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 14
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 15
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 16
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 17
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 18
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 19
Exhibit E
Project Funding (Millions)1 Major Construction Bonds $ 36.25 Other (Operating)2 $ 0.75 Total $ 37.00
Notes:
Includes APS portion of Jointly Funded Items.
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 20
information, final total project cost estimates are prepared at the end of each project phase by both the Architect / Engineering team (A/E) and Construction Manager at-Risk (CMR).
very busy and that material costs for some trades continue to experience above average increases.
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 21
Exhibit F
Base Scope - Estimated Cost (Millions) A/E CMR Construction Costs $ 28.13 $ 27.59 Owner (Soft) Costs1 $ 8.80 $ 8.80 Total $ 36.93 $ 36.39
Note:
services fees, utility/permitting fees, furniture, equipment, and project contingencies.
Alternates - Estimated Cost (Millions) A/E CMR Enhanced Site Improvements $ 0.62 $ 0.62 Bridge Connection between Buildings $1.64 to $4.77 $2.96 to $5.66 Canopy Connection between Buildings $ 1.35 $ 1.08
Alternate recommended to continue to pursue in the design development phase. Alternates recommended to no longer pursue in the design development phase.
Alternates - Estimated Cost (Millions) A/E CMR Replace 4th Floor Windows $ 0.31 $ 0.37
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 22
preliminary review of existing conditions and conceptual design study.
the project including:
to W-L High School
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 23
design becomes more detailed and more information about the project is known.
conjunction with engineering systems (HVAC, plumbing, electrical, etc.).
unexpected cost increases, including options for building materials.
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 24
described in Exhibits A through D;
recommendations on alternates as described in Exhibits E and F;
including preparation of the Use Permit application;
identifying APS/ACG jointly funded items; and
using every effort to complete the project for less than the maximum available funding.
SCHOOL BOARD INFORMATION ITEM, FEBRUAARY 07, 2019 – 25