slide-1
SLIDE 1

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 1

Edie’s Mulch Site Master Plan

Public Meeting #1

City of Ladue, Missouri 05.14.2019

slide-2
SLIDE 2

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 2

Team Introduction

  • Jay Wohlschlaeger - Partner
  • Liza Farr - Planner
  • Allyssa Gray - Designer
  • Anne Lamitola - Director of Public Works
  • Beautifjcation, Open Space, and Tree

Advisory (BOSTA) Committee

slide-3
SLIDE 3

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 3

Project Funding

  • Confjrm a vision for future development of the park.
  • Assist the City in future grant applications for park construction.
  • Implementation timeline and funding are to be determined.

The City of Ladue has received a planning grant from the Municipal Park Grant Commission (MPGC). This grant will assist with the cost

  • f creating the Master Plan for a future park on the Edie’s Mulch Site.

The MPGC is also a potential funding source for implementation, with a maximum grant amount of $370,000.

slide-4
SLIDE 4

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 4

¯

Project Goals

The focus of this project is to create a Edie’s Mulch Site Master Plan that addresses the following key priorities for the City of Ladue:

  • Improve the park site with low-maintenance passive recreational

amenities

  • Coordinate with partners that are active on or near the park site
  • Connect the park site with Clayton Road business district
  • Enable access to views of Deer Creek
  • Enhance vegetation through native plantings and removal of invasives
  • Maintain Public Works operations at the site
slide-5
SLIDE 5

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 5

¯

Project Process

  • May 14, 2019: Open House #1
  • Project Kick-ofg
  • Community Input and Discussion
  • May - Mid June:
  • Meetings with Key Stakeholders
  • Refjne Concepts Based on Community Input
  • Produce Imagery, Cost Estimates, Implementation Strategies in Draft Report
  • June 24, 2019: Open House #2
  • Final Concept Plan & Connectivity Diagram
  • Overview of Input (Meeting #1 and Survey)
  • Overview of Stakeholder Discussions
  • Cost Review
  • Priorities Discussion
  • Mid-June - Mid-July:
  • Incorporate Community Feedback
  • Finalize Master Plan Document
  • Mid-July - Late July:
  • Finalize Document with City
  • Submit Final Master Plan Document

SWT Design and the City of Ladue will work together to produce a Master Plan responsive to community input:

slide-6
SLIDE 6

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 6

Deer Creek

Edie’s Mulch Site Clayton Road Business District Rodes Park

City Context

Interstate 64/40 C l a y t

  • n

R

  • a

d L a d u e R

  • a

d

  • S. Lindbergh Boulevard

Litzsinger Road S . M c K n i g h t R

  • a

d Warson Road

Schools

Tilles Park

slide-7
SLIDE 7

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 7

Design Concept

Operations Parking S F

  • r

t y D r . win Springs Lane Horse Trail Pedestrian Trail Pole Barn Meadow Reclaimed Land Shelter Overlook D e e r C r e e k I n t e r s t a t e 6 4 / 4 Cell Tower Planted Stormwater Swale

slide-8
SLIDE 8

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 8

340’ 2 , 4 1 5 ’ Interstate 64/40 S F

  • r

t y D r .

Flood Hazard Area (1% Annual Chance) Flood Area (0.2% Annual Chance)

TOTAL PROPERTY AREA: 12.3 acres

Deer Creek

3 acres of paved yard

Existing Conditions

slide-9
SLIDE 9

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 9

Interstate 64/40 S Forty Dr.

MSD Easement MSD Sanitary Sewer Easement Ameren Easement MoDOT Easement

TOTAL PROPERTY AREA: 12.3 acres

Deer Creek

Existing Conditions

Planned MSD Improvement Easement - Permanent Planned MSD Improvement Easement - Temporary Construction

slide-10
SLIDE 10

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 10

Program and Site Identity

Existing Conditions

Constraints

  • City of Ladue Public Works operations:
  • Controlled access
  • Truck turning radii
  • Noise
  • Machinery storage
  • Cell phone tower
  • Private property lines cross Deer Creek
  • Site stormwater management and

testing

  • Flood zones
  • Ameren, MSD, and MODOT easements
  • Construction Timeline Deer Creek

Sanitary Sewer Project (2019-2023)

Assets

  • Underutilized natural space
  • Deer Creek aesthetics and habitat
  • Potential partners
  • Existing concrete pad for parking
slide-11
SLIDE 11

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 11

Program and Site Identity

Opportunities

  • Nature-focused, passive trail park
  • Asphalt trail loop
  • Separate entrance from Public Works operations
  • Moments to pause:
  • Shelter at trailhead
  • Benches along trail
  • Overlook to view Deer Creek
  • Parallel equestrian trail
  • Connect to informal trails
  • Planting barrier from Public Works operations
  • Potential partnerships
  • Future opportunity to connect to Clayton Road

Business District

  • Future opportunity to stormwater basins
slide-12
SLIDE 12

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 12

Design Concept

Operations Parking S F

  • r

t y D r . win Springs Lane Horse Trail Pedestrian Trail Pole Barn Meadow Reclaimed Land Shelter Overlook D e e r C r e e k I n t e r s t a t e 6 4 / 4 Cell Tower Planted Stormwater Swale

slide-13
SLIDE 13

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 13

Trail Concept Images

Horse Trail Pedestrian Trail

Asphalt Trail through Woods Benches along Grants Trail Horse Trail

slide-14
SLIDE 14

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 14

Small Picnic Shelter Large Picnic Shelter

Shelter and Overlook Concept Images

Shelter Overlook

Creek Overlook

slide-15
SLIDE 15

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 15

Pole barn Vegetated stormwater swale

Additional Elements Concept Images

Meadow

Pole Barn Meadow Vegetated Stormwater Swale

slide-16
SLIDE 16

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 16

Beyond the Boundary

Private Property Owners D e e r C r e e k C l u b Easements: MSD, Ameren, MODOT Racquet Club Clayton Road Business District Site Existing Informal Trails

Connections, Partners, & Stakeholders

  • Clayton Road Business District - Intersection

improvement at Clayton / 1-64/40

  • Neighboring residential property owners
  • Nearby Destinations: Deer Creek Club, Rac-

quet Club, Litzsinger Ecology Center

  • Long-Term Partners: Great Rivers Greenway,

Deer Creek Watershed Alliance

L i t z s i n g e r E c

  • l
  • g

y C e n t e r

slide-17
SLIDE 17

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 17

Beyond the Boundary

Edie’s Mulch Site

Long-Term Partners:

Great Rivers Greenway

  • Connect to regional greenway

system Deer Creek Watershed Alliance

  • Coordinate creek improvements
  • Work with volunteers
slide-18
SLIDE 18

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 18

PLEASE VISIT THE OPEN HOUSE MAPS!

slide-19
SLIDE 19

EDIE’S MULCH SITE MASTER PLAN

City of Ladue, Missouri

May 14, 2019 19

Project Schedule / Next Steps

OPEN HOUSE #2

JUNE 24TH

FINAL MASTER PLAN DOCUMENT

WEEK OF JULY 29TH

STAKEHOLDER INTERVIEWS

MONTH OF JULY