econ asics
play

ECON ASICs Gregory Deptuch, Zoltan Gecse, Jim Hirschauer, Sandeep - PowerPoint PPT Presentation

ECON ASICs Gregory Deptuch, Zoltan Gecse, Jim Hirschauer, Sandeep Miryala, Paul Rubinov ASICs PMG 10 May 2019 Reminders Two Endcap Concentrator (ECON) ASICs on independent data paths: ECON-TRG : select and compress interesting data for


  1. ECON ASICs Gregory Deptuch, Zoltan Gecse, Jim Hirschauer, Sandeep Miryala, Paul Rubinov ASICs PMG 10 May 2019

  2. Reminders • Two Endcap Concentrator (ECON) ASICs on independent data paths: • ECON-TRG : select and compress interesting data for transmission off detector at 40 MHz. • ECON-DAQ : perform zero suppression and concentrate for events passing L1 trigger at 750 kHz. • Baseline architecture : • ECON-T : 36x 1.28 Gbps inputs + 3x 10.24 Gbps inputs • ECON-D : 36x 1.28 Gbps inputs + 7x 1.28 Gbps inputs • Baseline schedule : • ECON prototype 1 : • verify essentially all ECON pieces except internal algorithms including high speed I/O, power distribution, PCB/package interface, etc. • ECON prototype 2 : • incorporate trigger algorithm for ECON-T • incorporate zero suppression logic and smart buffer for ECON-D • Need to submit by June 2020 to be ready for full system test • ECON production : full production of both ECON-T and and ECON-D 2

  3. Recent developments • CD-1 Director's Review • Comment : We are worried that, as currently envisioned, the first prototype of the ECON concentrator ASIC will take much longer to design than anticipated and will still have a significant risk of failure. We believe it would be safer to first design a prototype with 36 1.28 Gbps inputs and 7 1.28 Gbps outputs. This is the configuration required for ECON-D, and this configuration could also be used for ECON-T, albeit at the cost of a more complex printed circuit board design requiring more LpGBTs. • Recommendation : Consider the approach described above for the ECON ASICs to reduce schedule and performance risks. 
 • Optimization of motherboard / system design: • CMS has been become more concerned about high multiplicity of motherboard variants. • System design options that reduce motherboard variety impact optimal ECON design. • ECON schedule: • Despite excellent progress, latest forecast shows ECON P1 submission moving from Aug ➔ Dec 2019. Evolving ECON plan* must address all of these developments. * all plans are necessarily evolving plans 3

  4. ECON internal mini-review on May 14 Goals: • Finalize ECON architecture choices. • Present status and plans for ECON design in more technical detail than possible during usual HGCAL meetings. ECON presenters • Gregory, Sandeep, Ralph Wickwire, Mike Hammer (ANL), Ante Kristic (Split), Paul Rubinov, Hirschauer Reviewers: • Magnus Hansen (CMS electronics coordinator), Paolo Moreira and Szymon Kulis (lpGBT designers) • HGCAL people : Paul Aspell, Sandro, etc. 4

  5. Optimization of motherboard / system design • Modules (yellow/green on right) in each 60° sector of each layer are connected and readout by motherboards (gray on right). • M odules hold HGCROCs • M otherboards hold ECONs, optical transmitter(s), etc. • With 51 layers of varying module arrangement and varying required bandwidth, the tendency towards a high multiplicity of motherboard variants is evident . • Minimization of this multiplicity is one contribution to multi-dimensional optimization 5

  6. System design : illustration of two approaches Total: # DAQ/TRG 12/12 12/12 6/12 elinks 30/36 Maximal concentration D T L V 36x1G in motherboard (3/1)x10G out engine 12/12 12/12 6/12 Staged compression L L D D D T T T V +serialization L L 12x1G in 12x1G out engine many varieties of few varieties of simple passive few varieties of complex transmitter connection boards complex ECON boards boards 6

  7. Advantages / Disadvantages of two approaches Maximal Staged concentration compression+serialization 36x1G in 12x1G in (3/1)x10G out 12x1G out • Simpler 2-chip engine • More naturally allows isolation of complexity into • ECON board • more flexible load balancing • Transmitter board • t ransmitter redundancy Advantages • N aturally accommodates FPGA ECON emulator board • ~20% lower power for system early prototyping • Less ECON design time • More unified ECON-D / ECON-T architectures • Lower risk of ECON prototype problems • Simpler / less expensive ECON package • decentralization lowers single point failure risk • Longer ECON design time • More dense 4-chip engine • Higher risk of ECON • Less flexible load balancing Disadvantages prototype problems • Single point failure 7

  8. ECON development schedules for two approaches CMS need-by dates for System Test and Final chip • Compare schedules for 12in-12out and 36in-(3/1)out ST ST FC ST FC • Conclusion 12in-12out plan allows for delivery ~6 months sooner than 36in-(3/1)out 8

  9. Message for ECON May 14 review • In the past weeks, Fermilab ECON designers and system designers have considered the diverse aspects of ECON and HGCAL system design optimization including: • System / PCB complexity (and associated schedule risks, technical risks, and cost) • ASIC and package complexity (and associated schedule risks, technical risks, and cost) • power requirements • link counts (which drives cost) • readout redundancy and flexibility • ease of system prototyping • Taken all together, we conclude that the 12in-12out ECON design with the associated modular system design offers more advantages than an 36in-(3/1)out ECON design, so we propose to pursue the 12in-12out design. 9

  10. To do for May 14 and May 20 P2UG • JH : finalize link count comparison • JH : update power estimates • JH & GD : provide CMS with intermediate ECON design milestones for Sep 2019 and Jan 2020 • All : finalize talks (drafts have already been reviewed) 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend