EC&C Overview and Scrutiny Panel Coral Reef Update September - - PowerPoint PPT Presentation

ec c overview and scrutiny panel
SMART_READER_LITE
LIVE PREVIEW

EC&C Overview and Scrutiny Panel Coral Reef Update September - - PowerPoint PPT Presentation

EC&C Overview and Scrutiny Panel Coral Reef Update September 2016 Project Update Contract signed & sealed 4 th July Pre-start meeting 7 th June BFC Brymor Van Egdom Atkins Site mobilisation started 16 th May


slide-1
SLIDE 1

EC&C Overview and Scrutiny Panel

Coral Reef Update September 2016

slide-2
SLIDE 2

Project Update

  • Contract signed & sealed 4th July
  • Pre-start meeting 7th June

– BFC – Brymor – Van Egdom – Atkins

  • Site mobilisation started 16th May
  • Contract is on time and within budget
  • Budget pressure reduced by circa £226k (secondments)
  • Cost avoidance of £25k through reduced redundancies
  • Scheduled completion date 18th August 2017
slide-3
SLIDE 3

Current Construction Work

  • Complete drainage diversion works to rear of site
  • Demolition of the Splash Pool enclosure and walls
  • Commence 1st Fix Mechanical & Electrical to new reception area
  • Begin excavation for new flume tower basement
  • 1st Fix plumbing to toilet areas
  • Commence replacement ceiling to Coconut Grove
slide-4
SLIDE 4

Coconut Grove

slide-5
SLIDE 5

Splash Pool

slide-6
SLIDE 6

Flume Tower & Flumes

slide-7
SLIDE 7

Flume Tower

slide-8
SLIDE 8

Main Pool Scaffold

slide-9
SLIDE 9

Main Pool Roof

slide-10
SLIDE 10

Next Phase

  • Start removal of main pool roof
  • Construct ground floor of flume tower
  • Flume manufacturing
  • Commence reception area and entrance ceilings
  • Changing Village ceiling work
  • Construct foundations for new splash pool area
slide-11
SLIDE 11

Questions?