ec c overview and scrutiny panel
play

EC&C Overview and Scrutiny Panel Coral Reef Update September - PowerPoint PPT Presentation

EC&C Overview and Scrutiny Panel Coral Reef Update September 2016 Project Update Contract signed & sealed 4 th July Pre-start meeting 7 th June BFC Brymor Van Egdom Atkins Site mobilisation started 16 th May


  1. EC&C Overview and Scrutiny Panel Coral Reef Update September 2016

  2. Project Update Contract signed & sealed 4 th July • Pre-start meeting 7 th June • – BFC – Brymor – Van Egdom – Atkins Site mobilisation started 16 th May • • Contract is on time and within budget • Budget pressure reduced by circa £226k (secondments) • Cost avoidance of £25k through reduced redundancies Scheduled completion date 18 th August 2017 •

  3. Current Construction Work • Complete drainage diversion works to rear of site • Demolition of the Splash Pool enclosure and walls Commence 1 st Fix Mechanical & Electrical to new reception area • • Begin excavation for new flume tower basement 1 st Fix plumbing to toilet areas • • Commence replacement ceiling to Coconut Grove

  4. Coconut Grove

  5. Splash Pool

  6. Flume Tower & Flumes

  7. Flume Tower

  8. Main Pool Scaffold

  9. Main Pool Roof

  10. Next Phase • Start removal of main pool roof • Construct ground floor of flume tower • Flume manufacturing • Commence reception area and entrance ceilings • Changing Village ceiling work • Construct foundations for new splash pool area

  11. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend