DUNE Project Status Eric James DUNE PMG Meeting March 21, 2017 - - PowerPoint PPT Presentation
DUNE Project Status Eric James DUNE PMG Meeting March 21, 2017 - - PowerPoint PPT Presentation
DUNE Project Status Eric James DUNE PMG Meeting March 21, 2017 Outline ES&H Update QA Update Schedule & Budget Status PM Update Far Detector Report ProtoDUNE-SP Report Design & Construction reports by
Outline
- ES&H Update
- QA Update
- Schedule & Budget Status
- PM Update
- Far Detector Report
- ProtoDUNE-SP Report
- Design & Construction – reports by subsystem
- Onsite - installation & instrumentation
- ProtoDUNE-DP Report
- Upcoming Events
2
ES&H
- Supporting the DUNE Production Readiness Review (PRR) process
- Review procedures, hazard analysis, & SDS documentation
- Verify compliance with institutions ES&H program including
that the ES&H representative is engaged in the process
- Kevin Fahey will address specific reviews
- Review Detector installation hazard analysis documentation being
submitted to CERN EH&S organization
- Participated in 35 ton cryogenic safety committee review at PC4
- Assist evaluation process of US & EU fire safety codes and
standards for cabling and materials within the existing FNAL equivalency review process including definition of deliverables
- Met with Martha Michels FNAL Chief Safety Officer
- Met with Jim Niehoff & Mike Bonkalski from the ES&H Section
3
Quality Assurance
- Working to continue finalizing dates of the ProtoDUNE
subsystem PRRs
- Continue to work with LSU on the Field Cage End Wall
documentation in preparation
- Indiana University Photon Detector Bars PRR was performed
- n 3/15/2017
- The report for the CPA PRR review at ANL was issued on
3/6/2017. Response was received on 3/9/2017 and is being reviewed.
- The next confirmed PRR is the Cold Electronics – Mechanical
at Brookhaven National Lab on 3/27/2017
4
DUNE Stop Light Report for February 2017
- FD actuals exceeded budget due to cost transfer of Cold
Electronics COLDATA (FNAL labor) from incorrect ProtoDUNE task number
- ProtoDUNE design & construction SV and CV represent delays
in APA fabrication, CE procurement
DUNE Feb Status
February 28, 2017 Currency in: $K
- rk Package.WBS (2), Work Package.WBS (3), Work Package.WBS Budget
Earned Actuals SV ($) SV (%) CV ($) CV (%) 131.02 DUNE 1,312 934 863 (378)
- 29%
71 8% 131.02.01 Project Office - DUNE 135 135 102 0% 32 24% 131.02.02 Far Detector 1,177 799 761 (378)
- 32%
38 5% 131.02.02.20 Far Detector - Detectors 1-4 68 110 222 41 61% (112) -102% 131.02.02.30 ProtoDUNE Design and Construction 1,045 620 458 (424)
- 41%
162 26% 131.02.02.40 ProtoDUNE Onsite 64 69 81 5 8% (12)
- 17%
131.02.03 Near Detector 0% 0% Total 1,312 934 863 (378)
- 29%
71 8% Current Period
DUNE Stop Light Report – Cumulative as of February 28, 2017
DUNE Feb Status
February 28, 2017 Currency in: $K
- rk Package.WBS (2), Work Package.WBS (3), Work Package.WBS
Budget Earned Actuals SV ($) SV (%) CV ($) CV (%) SPI CPI 131.02 DUNE 16,377 15,660 16,536 (717)
- 4%
(877)
- 6%
0.96 0.95 131.02.01 Project Office - DUNE 2,231 2,231 2,315 0% (85)
- 4%
1.00 0.96 131.02.02 Far Detector 14,146 13,429 14,221 (717)
- 5%
(792)
- 6%
0.95 0.94 131.02.02.20 Far Detector - Detectors 1-4 2,472 2,284 2,502 (188)
- 8%
(217)
- 10%
0.92 0.91 131.02.02.30 ProtoDUNE Design and Construction 10,696 10,270 10,764 (427)
- 4%
(494)
- 5%
0.96 0.95 131.02.02.40 ProtoDUNE Onsite 978 875 956 (103)
- 11%
(81)
- 9%
0.89 0.92 131.02.03 Near Detector 0% (0)
- 0.00
Total 16,377 15,660 16,536 (717)
- 4%
(877)
- 6%
0.96 0.95 Cumulative to Date
Last month: SPI = 0.98, CPI = 0.94
DUNE Budget, Earned, Actuals – February 28, 2017
- 5,000,000
10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 Budget Earned Actuals
Far Detector/ProtoDUNE Actuals, Budget, EV at Level 4
- 500,000
1,000,000 1,500,000 2,000,000 2,500,000 3,000,000 3,500,000 4,000,000 Actuals Budget Earned
Project Management Highlights
- DOE IPR 28 Feb – 2 Mar at Fermilab; First full review of the project
since July 2015 (Next slide summarizes DUNE recommendations)
- Preparing for LBNC review at Fermilab, 23-25 Mar
- itrack no longer used for DUNE recommendations; docdb #2750
- Three 2016 reviews generated 99 recommendations with 18
different responsible parties spread among 20 entities (working groups, task forces, project teams); 16 recommendations remain
- pen (83 closed)
- Received charge last week; 9 subgroups address various topics
- CERN SPSC review, 4-5 April; responded to committee questions
- Schedule review, obligations review (CR impact)
- Working with FESS to identify shipping timeline (& cost estimate) for
delivering first APA from UWM to CERN by early June
- DUNE mgmt. and DOE FSO toured DAB Cold Electronics set-up, Lab 7
Photon Detector bar production facility, and PC4 35ton HV test, 23 Feb
9
Project Management Highlights DUNE Review Recommendations, DOE IPR, 28 Feb-2 Mar
10
Define minimal, quantifiable requirements that ProtoDUNE must achieve so that DUNE will have successful LBNC, CD-2, and CD-3b reviews. Define a date for each of these sets of requirements to be achieved. Due Date: May 1, 2017. James, with Thomson Use project management tools to manage the schedule, costs, and possible scope reductions so as to achieve the ProtoDUNE requirements. The planning should extend beyond integration. Due Date: June 1, 2017. Macier Develop a plan and budget with clearly defined objectives for operating ProtoDUNE at CERN. Due Date: August 1, 2017. James Assemble a task force to address photon detection in preparation for CD-2. Due Date: May 1, 2017. James Establish and document, with the DUNE Collaboration, the detector performance requirements necessary to achieve the physics goals for CP violation, proton decay, and astrophysical neutrinos of the DUNE project for the TDR. James Perform a comprehensive review of your bottom-up cost estimate (including CORE costs) prior to the next OPA review. Macier DOE should work with LBNF/DUNE and international partners to better define CD2 requirements for non-DOE contributions. Carolan
Project Management Highlights
- ProtoDUNE-SP Production Readiness Reviews (PRRs) in process
- Review team includes QA manager, ES&H managers, Project Engineers,
Project Managers, and other technical expertise as needed
- 22 February, CPA @ Argonne
- 15 March, PD at Indiana University
- 28 March, CE Mechanical at BNL
- 7 April, PD at CSU
- 10 April, PD at FNAL
- 13 April, APA at UW-PSL
- 30 April, CE Electronics at BNL
11
Far Detector
- Data Transmission tests with 35m long cable were performed using
the ProtoDUNE signal cable type and bit errors were observed even when the FPGA cable compensations was at maximum.
- Looking for ways to modify the APA frame in order to allow the cables
from the lower APA to be routed through the frame.
- An alternate would be to use the larger gauge Gore cables but these
are very expensive and difficult to handle.
- Defining DUNE installation stay-clear spaces will require additional
engineering support.
- A 3.6m high Ross cage alternate is being considered where the 4m tall
field cage crates would be mounted to the work platform connected to the cage roof. This could be more efficient than transporting the 200 FC units as slung loads.
- An LBNF/DUNE Far Site CAD integration workshop was held in March
to discuss integration and modeling tools.
12
SPPD Design & Construction – Subsystem Reports
APA
- Winding of APA#1 frame (U plane in
process); wire tensioning requirements
- UK Frame #1 tube machining underway;
wire winding machine commissioning Photon Detector
- Dry run with dipped bar apparatus at
Lab 6 last week
- Resolving SiPM board and integration issues
Cold Electronics
- Testing underway of FE ASICs from vendor
- Prototype flange mechanical assembly & boxes have been ordered
CPA/FC/HV
- CPA production material received
- Strength testing of Field Cage FRP threaded rods/nuts performed
13
SPPD On-Site – EHN1
- About 1/2 of the membrane insulation
inside the SP cryostat structure is completed
- Clean Room material procurement in
progress
- Cold Test Box design completed,
material procurement to start
- Grounding and electrical layout
progressing (safety document nearly completed)
- Procedures for integrated APA tests in
Cold Box and test data read-out under development
14
SPPD On-Site - Instrumentation
- Beam Instrumentation
- Progress reported on Tracking Fiber detectors (also possibly used
for ToF), on Cherenkov counters and pLAPPD (test in LArIAT test beam started). Under study BI DAQ and data storage (CERN)
- Cryo-Instrumentation
- Vertical T-Gradient Monitors: two VTG Monitors are agreed to be
installed, based on different designs developed at UHawaii and IFIC-Valencia.
- Progress with internal Web Cam Monitors based on development
from HV test installation in 35t.
- External Instrumentation
- Muon tagging paddles mechanical tests underway. Design of frame
for (4) paddles - “CRT module” - in progress, holding structure for frames (new or existing rails) under discussion. Shipment to CERN
- f Paddles from D-Chooz experiment delayed (April).
15
SPPD On-Site – DAQ & Data Reconstruction & Analysis
- DAQ Vertical Test Stand - for APA test in Cold Box - advanced
- Calibration tasks, Detector Performance Measurements and first
Physics Measurements: path almost defined
- (new) MC production not started yet (input beam fluxes under
- ptimization)
- great progress with EM and hadron shower reconstruction by CNN
based new algorithms for EM component identification, combined with efficient (traditional) algorithms (TrajCluster+PMA, Pandora, ..) for hadron track reconstruction and primary vertex identification
16
Dual-Phase - Technical Progress
- On 3 March, a layer of frost was observed on the
bottom south east corner of the cryostat on an area of approximately 50x50 cm2.
- At the time, the tank was in the slow cool down phase
(few kelvin per hour) with a minimum measured gas temperature of 176K at the sensor located near the bottom of the drift cage. No liquid argon was introduced.
- Infrared pictures on 4 March indicate a cold spot of
down to -40C on the outer structure at this specific corner.
- Leak-testing of warmed cryostat by CERN and GTT
has not identified any leaks in this area; the delay on detector commissioning is still being assessed but will likely be on the order of several weeks.
- ProtoDUNE-DP design review scheduled for 24-25 April
17
Upcoming Events
- LBNC Review, March 23-25, 2017 at FNAL
- ProtoDUNE-SP Production Readiness Reviews, ongoing at production
sites
- DUNE Near Detector Workshop, 27-29 March 2017 at FNAL
- SPSC Review, 4-5 April, 2017 at CERN
- ProtoDUNE-SP Installation Workshop, 19-21 April 2017 at CERN
- ProtoDUNE-DP Design Review, 24-25 April 2017 at CERN
- ProtoDUNE-SP Cryo instrumentation Review, 26 April at CERN
- ProtoDUNE-SP Beam instrumentation Review, 27 April at CERN
- DUNE Collaboration meeting, 16-19 May at FNAL
18