DTE SolarCurrents Pilot Programs April 8, 2013 PA 295 of 2008 has - - PowerPoint PPT Presentation

DTE SolarCurrents Pilot Programs April 8, 2013 PA 295 of 2008 has led Detroit Edison to develop the following RPS Portfolio Plan Solar At least 50% will be 3 rd Landfill Gas 22 MW 11 MW party-owned Biomass Majority expected to be


slide-1
SLIDE 1

DTE SolarCurrents Pilot Programs April 8, 2013

slide-2
SLIDE 2

PA 295 of 2008 has led Detroit Edison to develop the following RPS Portfolio Plan

  • At least 50% will be 3rd

party-owned

  • Majority expected to be

wind energy

  • Limited availability of

landfill gas, biomass, hydro in Michigan

  • Pilot programs for Solar

2

~ 1,000 MW New Renewable Capacity

Wind ~ 900 MW Biomass ~ 40 MW Solar 22 MW Landfill Gas 11 MW

slide-3
SLIDE 3

Phase 1 (Fully Subscribed)

  • 5 MW in total nameplate capacity, $25 Million

Budget

  • Customers can install solar systems up to 20 kW,

following Net Metering and interconnect guidelines

  • 581 projects commissioned as of 4/3/13, 75/25 %

split between residential and non-residential based

  • n a number of projects
  • Projects located in all 13 counties of DTE Energy’s

electric service territory Phase 2 (Open)

  • 2 MW in total nameplate capacity, $2 Million

budget

  • Projects selected through application process

through 3/1/2015

  • Incentives are lower than Phase 1 offering

Customer-Owned Solar Pilot Program

3

slide-4
SLIDE 4
  • 15 MW in total nameplate capacity
  • $112 Million budget over 5 years
  • Partner with customers to site

projects on large rooftops or ground-mounted

  • DTE Energy facilities
  • Project Sizes: 250-500 kW
  • Using standard site easement

agreements

DTE-Owned Solar Pilot Program

4

slide-5
SLIDE 5

Committed Projects

5

Site Size (kW) Mounting COD Status 1 DECo Project #1 (Scio Township) 60 Ground 11/16/2010 Complete 2 Ford Michigan Assembly (Wayne) 502 Ground 1/25/2011 Complete 3 Monroe County Community College 513 Ground 2/22/2011 Complete 4 Blue Cross Blue Shield (Detroit) 220 Roof 8/5/2011 Complete 5 GM Chevy Volt Plant (Hamtramck) 516 Ground 9/30/2011 Complete 6 DECo project #2‐ TDC (Westland) 391 Ground 9/16/2011 Complete 7 Mercy High School (Farmington Hills) 394 Roof 12/28/2012 Complete 9 Warren Consolidated Schools CPC (Sterling Heights) 197 Roof 3/22/2012 Complete 8 DECo Project #3 ‐HQ (Detroit) 80 Canopy 11/15/2012 Complete 10 GM Orion Assembly (Orion Township) 350 Ground 11/27/2012 Complete 11 Huron Clinton Metro Parks (White Lake) 495 Ground 11/20/2012 Complete 12 IHM The Mother House (Monroe) 516 Ground 12/4/2012 Complete 13 Wil‐Le Farms (Bad Axe) 486 Ground 12/19/2012 Complete 14 U of M ‐ North Campus Research Complex (NCRC) 425 Ground 12/27/2012 Construction 15 U of M ‐ Information, Science and Technology (IST) 230 Ground

  • Est. 7/2013

Design 16 Riopelle Farms (Harbor Beach) 500 Ground

  • Est. 9/2013

Design 17 Hartland Schools (Hartland) 440 Ground

  • Est. 9/2014

Design 18

  • St. Clair RESA (Marysville)

502 Ground

  • Est. 9/2015

Design 19 Leipprandt Orchards (Pigeon) 500 Ground TBD Feasibility 20 Lyon Township Project 750 Ground TBD Feasibility 8067 Total kW

slide-6
SLIDE 6

Educational Kiosks are provided to Host Customers and are typically located in schools

6