DTE SolarCurrents Pilot Programs April 8, 2013 PA 295 of 2008 has led Detroit Edison to develop the following RPS Portfolio Plan Solar At least 50% will be 3 rd Landfill Gas 22 MW 11 MW party-owned Biomass Majority expected to be
PA 295 of 2008 has led Detroit Edison to develop the following RPS Portfolio Plan
- At least 50% will be 3rd
party-owned
- Majority expected to be
wind energy
- Limited availability of
landfill gas, biomass, hydro in Michigan
- Pilot programs for Solar
2
~ 1,000 MW New Renewable Capacity
Wind ~ 900 MW Biomass ~ 40 MW Solar 22 MW Landfill Gas 11 MW
Phase 1 (Fully Subscribed)
- 5 MW in total nameplate capacity, $25 Million
Budget
- Customers can install solar systems up to 20 kW,
following Net Metering and interconnect guidelines
- 581 projects commissioned as of 4/3/13, 75/25 %
split between residential and non-residential based
- n a number of projects
- Projects located in all 13 counties of DTE Energy’s
electric service territory Phase 2 (Open)
- 2 MW in total nameplate capacity, $2 Million
budget
- Projects selected through application process
through 3/1/2015
- Incentives are lower than Phase 1 offering
Customer-Owned Solar Pilot Program
3
- 15 MW in total nameplate capacity
- $112 Million budget over 5 years
- Partner with customers to site
projects on large rooftops or ground-mounted
- DTE Energy facilities
- Project Sizes: 250-500 kW
- Using standard site easement
agreements
DTE-Owned Solar Pilot Program
4
Committed Projects
5
Site Size (kW) Mounting COD Status 1 DECo Project #1 (Scio Township) 60 Ground 11/16/2010 Complete 2 Ford Michigan Assembly (Wayne) 502 Ground 1/25/2011 Complete 3 Monroe County Community College 513 Ground 2/22/2011 Complete 4 Blue Cross Blue Shield (Detroit) 220 Roof 8/5/2011 Complete 5 GM Chevy Volt Plant (Hamtramck) 516 Ground 9/30/2011 Complete 6 DECo project #2‐ TDC (Westland) 391 Ground 9/16/2011 Complete 7 Mercy High School (Farmington Hills) 394 Roof 12/28/2012 Complete 9 Warren Consolidated Schools CPC (Sterling Heights) 197 Roof 3/22/2012 Complete 8 DECo Project #3 ‐HQ (Detroit) 80 Canopy 11/15/2012 Complete 10 GM Orion Assembly (Orion Township) 350 Ground 11/27/2012 Complete 11 Huron Clinton Metro Parks (White Lake) 495 Ground 11/20/2012 Complete 12 IHM The Mother House (Monroe) 516 Ground 12/4/2012 Complete 13 Wil‐Le Farms (Bad Axe) 486 Ground 12/19/2012 Complete 14 U of M ‐ North Campus Research Complex (NCRC) 425 Ground 12/27/2012 Construction 15 U of M ‐ Information, Science and Technology (IST) 230 Ground
- Est. 7/2013
Design 16 Riopelle Farms (Harbor Beach) 500 Ground
- Est. 9/2013
Design 17 Hartland Schools (Hartland) 440 Ground
- Est. 9/2014
Design 18
- St. Clair RESA (Marysville)
502 Ground
- Est. 9/2015
Design 19 Leipprandt Orchards (Pigeon) 500 Ground TBD Feasibility 20 Lyon Township Project 750 Ground TBD Feasibility 8067 Total kW
Educational Kiosks are provided to Host Customers and are typically located in schools
6