Double Tee Section Qualitative Assessment of your Floor before you - - PowerPoint PPT Presentation
Double Tee Section Qualitative Assessment of your Floor before you - - PowerPoint PPT Presentation
Double Tee Section Qualitative Assessment of your Floor before you Start Step 1 - Qualitative Review Before you start your detailed capacity calculations Carry out a qualitative review of the floor and potential damage areas
Qualitative Assessment of your Floor before you Start
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
This example is for a Hollowcore floor building – but the same principles apply for all precast floors including Double Tees, Rib and Infill, and Flat Slab assessments.
Step 1 - Qualitative Review
- Before you start your detailed
capacity calculations
- Carry out a qualitative review of the
floor and potential damage areas
- btained from your building analysis
- Check the drawings and details for
what information you need to get from the site investigation Step 2 - Visit the building
- Review the parameters and details
- n site.
- Site measure and audit against
drawings
- Is there some additional invasive
investigation needed
- The better the information the more
accurate the result Step 3 Detailed Check
- Now start your detailed calculations
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Design Drawings and Details
Double Tee Example – Ductile Frame Example Parameters
- Ductile frame building with 350 deep
2400 module Double Tee floors
- Beam span
= 10,500 mm
- Beam depth
= 800 mm
- Column width = 800 mm
- Floor unit seated 285 mm above the
beam centreline
- D12-300 starter bars
- Elastic drift
= 0.6%
- Detailed example calculations provided
in the Appendix
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
le = 3600mm D12-300 600 lap D12-300 600 lap
500W x 600D 500W x 800D 500W x 800D
10500mm (typ.)
U R
350 Double Tee 75mm topping 665 mesh 75mm seating
Double Tee Example – Required checks
Scenarios to check:
- A. Unit adjacent corner columns
- Check using unrestrained hinge (U)
- B. Unit adjacent elongating beam, away
from corners
- Check using restrained hinge (R)
- C. Internal units away from elongating
beam
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Note: Highlighted Units – the topping delaminates so is a special case A or B to consider
Double Tee Example – Required checks
Checks for each scenario:
- 1. Loss of support
– Spalling – Elongation
- 2. Birds Mouth Failure
– Review connection load transfer mechanism and probable failure modes of connection due to drift. – Strut and Tie check of flexural capacity and failure modes – Details on the assessment of the failure modes of flange hung double tees units is provided in Hare et al. (2009)
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Loss of Support Example
Double Tee Floor Example – Loss of Support Review
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Floor Example – Loss of Support Review
- Tee Unit adjacent corner column
- Initial seating
= 75 mm
- Construction tolerance = 20 mm
- Initial spalling
= 10 mm
- Bearing (calc = 8mm)
= 10 mm
- Therefore remaining seating to
permit elongation, rotation + further spalling: 75 – 20 – 10 – 10 = 35 mm
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Construction tolerance (portion of) Initial spalling (example) Drift related spalling (example) Elongation + Rotation
Double Tee Unit SUPPORT BEAM
Double Tee Floor Example – Loss of Support Review
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Calculation of Elongation Plastic beam rotation θp = θp
col * L / (L - hcol - Lp)
= (1.39-0.6)*10500/(10500-800-335) = 0.89% Beam elongation del = 2.6 * θp/2 * (d - d’) ≤ 0.036hb = 2.6*0.0089/2*(800-65) (U) = 8.5 mm => 9 mm ≥ 0.005hb (R) = 4.2 mm => 4 mm
(For reversing plastic hinges) (Restrained taken as ½ of reversing) (Lp = 0.5*d/2)
Double Tee Example – 1. Loss of support review
Calculation of Beam Rotation Similar to the hollowcore design example the support rotation is the maximum {S del + dr1 or dr2 + del unit} qbeam = 1.39% dr1 = ((hb/2)-hl)*θbeam = (800/2-(115))*0.0139 = 4.2 mm dr2 = hlθbeam =115*0.0139 =1.4 mm
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Floor Example – Loss of Support Review
How is the spalling calculated ?
- Initial Spalling
= 10 mm + Additional spalling at limiting drift of 1.39%
- Unit (27 -10)
= 17 mm
- Ledge
= 5 mm
- Total spalling
= 32 mm
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
L.O.S = 1.39%
5mm 27mm 10mm
Figure C5E.26 Spalling depths to be considered for Flange hung and web supported double tees
COVER TO FIRST BAR 25mm + 10mm COVER TO FIRST BAR XX mm + 10mm
Double Tee Floor Example – Loss of Support Review
Through iteration 35mm of seating is exceeded at a total inter-storey drift of 1.4% components of loss
- Unit Spalling
= 17 mm
- Ledge Spalling
= 5 mm
- Beam elongation
= 9 mm
- Beam rotation
= 4 mm 35 mm
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
L.O.S = 1.4%
Initial seating = 75mm Construction Tolerance = 20mm Bearing = 10 mm Initial Spalling = 10 mm
Double Tee Floor Example – Loss of Support Review
Through iteration 45mm of seating is exceeded at a total inter-storey drift of 1.7% components of loss
- Unit Spalling
= 17 mm
- Ledge Spalling
= 21 mm
- Beam elongation
= 11 mm
- Beam rotation
= 5 mm 45 mm
With suitable site investigation 20mm tolerance may be able to be reduced to actual site tolerance e.g. for the above example with a site measured 10mm variance on seating (75mm +/- 10mm)
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
L.O.S = 1.7%
Initial seating = 75mm Construction Tolerance = 20mm Bearing = 10 mm Initial Spalling = 10 mm
Extra investigation – tolerance reduced
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Floor Example – Loss of Support Review
Now repeat the L.O.S for rest of the floor
- The L.O.S support calculation is
easily put into a spreadsheet and
- nce set up with the project
specific geometry and spalling parameters can be repeated for the rest of the floor and levels relatively quickly
Double Tee Floor Example – Loss of Support Review
Results for L.O.S for Building Summary Results repeated for the other units gives; Case A Adjacent Unrestrained Hinge
- L.O.S = 1.4% drift
Case B Adjacent Restrained Hinge
- L.O.S = 1.5% drift
Case C Internal Unit
- L.O.S. = 1.7% drift
These are the limiting drifts for the loss of support due to spalling or elongation Now you need to investigate the Birdsmouth Support detail and possible failures to see if these are critical for limiting drift
*Note: Highlighted Units – the topping delaminates so is a special case A or B
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
A*
Double Tee Example – Loss of Support NBS Rating
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
How to use Limiting Drift for Rating of %NBS
ULS design drifts are factored by 2.0 in the Yellow Book to get drift demand [Note: this is different to NZBC = dULS x 1/SP x 1.5] Building Drift Demand dULS x 2 = 3.2% Limiting Drift Calculated = 1.4%
Correct Rating Method
Limiting Drift / Building Drift Demand 1.4 / 3.2 = 44% NBS
Incorrect Rating Method
Seating Provided / Seating Required 75 / 132 = 57% NBS The NBS rating is based on a limiting drift to loss of support i.e. the methodology assesses the amount of drift required before loss of precast support – this is a bi-linear function and gives a different answer than simply comparing against the total seating that would be required for design.
Figure: Total required seating at calculated demand building drift using C5E Methodology
Total required seating at calculated building drift demand 3.2% Summary Elongation and Rotation 37.8 mm Unit Spalling 35.0 mm Ledge Spalling 29.5 mm Shrinkage 0.0 mm Construction Tolerance 20.0 mm Bearing Length 10.0 mm Total 132.3 mm TOTAL SEATING REQUIRED 132 mm AS PER C5 GUIDELINES Seating Provided 75 mm
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Effect of L.O.S Due to Spalling and Elongation
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
No Spalling and After Spalling
Birdsmouth / Loop Bar Review
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
350x2400 Double Tee Example
- Span = 10000mm
Unit Width = 2400mm
- Topping = 75mm
f’c = 20MPa => f’cp = 30 MPa
- Double Tee
f’c unit = 45MPa
- “Pigtail” Loop Bar Detail – 3 R12 Bars / fy = 275 MPa => fyp = 324MPa
Loading Gravity [G unit = 2.5 KPa] + [Topping = 1.8 KPa] + [SDL = 0.5KPa] = 4.8KPa Live Load = Q= 3.0 KPa , YE = 0.3 Total G + YE Q + Eu = 5.7 KPa Load per Unit = 5.7*2.4*10 = 136 kN Load per web / Pigtail = 136/4 = 34 kN
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Loop Bar Hanger damage being investigated post Christchurch EQ
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Possible Failure Modes There are a number of possible failure modes / crack patterns that can occur at the birdsmouth connection. The failure in fig C5E 29 is a combination of – a, b, c, d, e & f. and the designer needs to be satisfied that they have investigated all likely modes in the failure analysis. Note: For the double tee supported in the elongation zone (immediately adjacent column) topping delamination is likely to
- ccur and the check is for the
precast portion (t-ttopping) only in fig C5E.29
C5E 29 Example demonstrated
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Tension Shift
e’ mm tension shift
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Elongation Demand: Solve for d to find limiting drift M* = P (d + e + e’) + mPt < MBM.capacity Friction Static (typical ranges)
mf= 1.0 - 1.2 concrete to concrete mf= 0.8 - 1.0 on soft mortar mf= 0.8 - 1.0 on steel mf= 0.6 - 1.0 on bearing strip Note: Be careful some published values of m are lower bound or dependable values i.e. they have a f.o.s or reduction factor for design built in and may be un-conservative for calculation
- f demand.
75mm seating 15mm gap 10mm min seating
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Scenario Review
a) Flexure
a) Yes - check required
b) Topping delamination
a) at loop bar – Yes likely - check b) In unit – Yes - possible as the R6 spirals are unlikely to be sufficient
c) Shear Failure
a) Yes - check required
d) Diagonal tension failure
a) Yes - check required
e) Bond failure
a) At Leg – <600mm anchorage for plain R12 bar in tension – to short to develop b) At bottom hangar bar – ? may be OK
f) Separation of Flange from Web
a) 4 sets of R6 Stirups at 50mm crs at end of unit so failure is likely suppressed but should check
Qualitative Review of Detailing
C5E 29 Example demonstrated
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Qualitative Review of Detailing
30O 65 90 75 50
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Elongation Demand: Solve for d => to find limiting drift Iteration 1 => try max d = (75/2-10) = 27.5mm Design Actions for Review P* = 34 kN (G + Qe + E) P*m = 27 kN (assuming m=0.8) M* = P (d + e + e’) + mPt = 34*[(75/2-10)+(75/2+15)+65]mm + 0.8*34*125mm = 8.3kNm (at max d of 27.5mm) Iteration 2 => try min d = 0mm M* = 7.4 kNm (at d of 0mm) i.e. At initiation of movement / crack 75 P
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
But why can’t I just use simple flexural theory?
Solve for limiting d - take first trial as max = 27mm fMn = fAsfy (d-a/2) f = 0.85 = 11.0 kNm M* = P (d + e + e’) + mPt = 8.3kNm < 11.0 kNm => OK T*N = P / Cos qh = 34 /Cos 60o = 68kN < 110 kN => OK This check may be simple but is un-conservative and does not consider the actual failure modes of the connection. The birds mouth is a disturbed region and you must use an appropriate method i.e. Strut and Tie to assess the failure modes. Further details on the assessment of the failure modes is in Hare et al. (2009)
75mm seating 15mm gap 10mm min seating 65 mm tension shift => e’
q =60o qh =60o
30O 65 90 75 50
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Review the Flexural Mechanism
Horizontal Reinforcing Tie To develop Tjd of 11kNm the tension steel yeilds => for 3 R12 T* = C = Asfy = 110 kN Compression Strut Check Strut / Node Force = 110/Cos30 = 127 kN Node width = 200mm x 20mm (Pigtail bar width) Node Capacity fFn = f*bn*f’c = 0.75*0.80*200*20*30 = 72kN < 127kN =>Capacity Ratio = 0.56 Strut Capacity fFs = f*bs*f’c = 0.75*1.0*200*20*30 = 90kN => Ratio = 0.70 Therefore node failure and concrete crushing may occur at loop bar node before you can fully develop tension steel capacity required for flexure theory.
P T = ASfy C C Concrete Tension
30O 65 90 75 50
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Note: Caution Needed - Concrete Tension Capacity - NZBC
Unreinforced Tie Check Not permitted by B1 / VM1 - NZS3101 Cl 2.3.2.3 Equations for Concrete Tension – Use with Caution! Tension capacity in slab (NZS3101 5.2.4) gives ft = 0.38 l [f’c]1/2 = f x 2.08 MPa (for 30MPa) Cold joint interface - for tension across slab/unit interface (ACI) = 0.25 [f’c]1/2 = f x 1.36 MPa
P T C Concrete Tension
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Review the Flexural Mechanism
Review slab in tension Tension tie required = 127*Sin30 = 63.5kN Assume 50mm at node x 200mm wide Tie capacity = f * f’t*At = 15.6 kN << 63.5kN Ratio = 0.25 ……. Iterating gives a max capacity = 22kN / 0.35 Slab Interface capacity = 10.2 kN << 63.5 kN Ratio = 0.16……. Iterating gives a max capacity = 23kN / 0.36 By iteration you can find S&T mechanisms which may give better results than this initial review
- example. A key consideration is the capacity of the tie is limited by the geometry of the joint
including the pigtail compression node width + amount of spread of strut of 1:2.5 max. Further details on the assessment of the double tee failure modes is in Hare et al. (2009)
Slab Interface
Simplified S&T Model
Reinforcing for Pigtail Tension tie Other failure mode?
Double Tee Example – Birdsmouth / Loop Bar
Review the results for failure mode a) Flexure for this example
- Flexural Capacity derived by S&T < 40% of that provided by simple Flexure theory fMi= Tjd
=>this is quite sensitive to geometry of loop bar and joint.
- Large increase in design actions due to tension from elongation Pmt => actions almost double
– also quite sensitive to support load and friction coefficient chosen
- Tension Shift – once concrete cracks also accounts for another shift approximately additional
30% - 40% increase
- Offset of support due to elongation has less affect and accounts for about another 10% to 15%
increase in load
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Ideal Flexural Capacity fMi = 11kNm MoR Flange = 5.5kNm S&T Capacity = 4.5 kNm 2.7 kNm 27 mm Limit before L.O.S governs 1.8 kNm 7.1 kNm 8.3 kNm Crack may form due to tension Pmt from elongation 6.1 kNm 4.9 kNm
Birdsmouth / Loop Bar – Demand / Capacity Envelope
kNm mm
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Review - Outcome
Strut and Tie Review of Mechanism (a)
- Review of the flexural mechanism with an initial S&T model gives a lower bound limiting drift
sensitive to cracking with d = <5 mm for the birdsmouth after onset of cracking.
- The S&T review indicated however that the unit it may be able to (just) carry gravity loads after
elongation has finished i.e. (Pm loads from elongation no longer action).
- Could investigate geometry further and sliding capacity – important to understand site
constraints and geometry of loop bar and joint Other Failures – mechanism (b), (c), (d), (e), etc
- Need to now complete the review and check other modes to determine critical mode of failure
has been determined. The floor %NBS in this example (a) Flexure will be difficult to rate as a result of the birdsmouth / loop bar connection having insufficient capacity to accept movement that would result in a crack forming and tension (from elongation) across the birdsmouth connection. A detailed further investigation of the loop bar details should be undertaken to help determine the actual as built capacity.
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Scenario Review
a) Flexure
a) Completed – Probably OK
b) Topping delamination
a) at loop bar – possible - check b) In unit – possible as the R6 spirals are unlikely to be sufficient
c) Shear Failure
a) OK
d) Diagonal tension failure
a) Yes – further check required
e) Bond failure
a) At Leg – <600mm anchorage for plain R12 bar in tension – Ld x 2 = 610mm ~ 570 => OK b) At bottom hangar bar – Ldh OK
f) Separation of Flange from Web
a) 4 sets of R6 Stirups at 50mm crs b) Capacity > 34kN => OK
Qualitative Review of Detailing
C5E 29 Example demonstrated
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Review of Double Tees - Summary
Loss of Support – Elongation
- Likely to govern most situations for most 1980s and early 90s buildings which have typical
seating detailed between 30mm to 50mm.
- Failures observed to date Clarendon / Statistics were loss of support.
Birdsmouth Failure
- Likely to govern all buildings at PHZ where delamination of topping occurs
- Likely to govern newer buildings mid 1990s onwards using the loop bar detail that are provided
with a more generous seating of 75 mm or more.
- Be aware of double tees that have the flange trimmed back locally (more common on steel beam
support) with no distributed flange bearing means redundancy is reduced.
- Be aware of long span double tees – high shear load at the birds mouth is problematic
- It can be difficult to assess the capacity and point of failure of the failure of those modes relying
- n concrete in tension. Need to undertake a rational approach and look at likely scenarios.
- Hare et al 2009 covers this topic very well.
- No direct failures– but lots of in service evidence that birdsmouth cracking mechanisms are
- ccurring even under service loads so may be problematic with the right earthquake conditions.
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
What happens at the Plastic hinge regions and corners ?
Topping Delaminates
tf Section capacity is based solely on the double tee flange depth tf for these areas
Double Tee Example – Birdsmouth / Loop Bar
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Delamination of topping
40
40
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Can not hang the unit from the topping
Concrete Tension at Interface (ACI) = 0.25 [f’c]1/2 = 1.36 MPa Capacity 10,000 x 2,400 x 1.36 MPa = 32,640 kN Double Tee Weight 10,000 x 2,400 x 2.4 kPa = 60 kN F.O.S = > 500 Why did this fail ? Not permitted by B1 / VM1 - NZS3101 Cl 2.3.2.3 Assess Birdsmouth and other failure mechanisms and using concrete tension with caution Re-Cast Project => programmed to look at this loop bar issue in existing buildings in more detail with detailed FEM solid modelling and lab tests
Precast Rib and Infill
Failure of Rib and Timber Infill Floors
- Possible rib entrapment under
positive moments
– Casting of ribs into the beam – Haunching final vertical form Seating
- n mortar
- Weak section forms along rib
- Follow
42
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Assessment of Rib and Timber Infill Floors
- Similar Process to hollowcore
example
- Checking for;
- Spalling and loss of support
due to elongation
- Displacement / drift induced
design actions on the precast member and floor
Flat Slab Floors
Assessment of Flat Slab Floors
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
- Similar Process to hollowcore
example
- Checking for;
- Spalling and loss of support
due to elongation
- Displacement / drift induced