DOMAIN COMMUNITY REFERENCE GROUP Meeting #18 Wednesday 16 October, - - PowerPoint PPT Presentation

domain community reference group
SMART_READER_LITE
LIVE PREVIEW

DOMAIN COMMUNITY REFERENCE GROUP Meeting #18 Wednesday 16 October, - - PowerPoint PPT Presentation

DOMAIN COMMUNITY REFERENCE GROUP Meeting #18 Wednesday 16 October, Seasons Botanic Gardens 1 ST KILDA ROAD REALIGNMENT UPDATE 2 ST KILDA ROAD REALIGNMENT OVERVIEW 3 TIME-LAPSE SEPTEMBER 1 TO OCTOBER 15 4 5 NORTH VIEW 7AM MONDAY 14


slide-1
SLIDE 1

Meeting #18 Wednesday 16 October, Seasons Botanic Gardens

DOMAIN COMMUNITY REFERENCE GROUP

1

slide-2
SLIDE 2

ST KILDA ROAD REALIGNMENT UPDATE

2

slide-3
SLIDE 3

ST KILDA ROAD REALIGNMENT OVERVIEW

3

slide-4
SLIDE 4

TIME-LAPSE SEPTEMBER 1 TO OCTOBER 15

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

NORTH VIEW 7AM MONDAY 14 OCTOBER

6

slide-7
SLIDE 7

NORTH VIEW 6.45AM WEDNESDAY 16 OCTOBER

7

slide-8
SLIDE 8

SOUTH VIEW 7AM MONDAY 14 OCTOBER

8

slide-9
SLIDE 9

SOUTH VIEW 6.45AM WEDNESDAY 16 OCTOBER

9

slide-10
SLIDE 10

MAP OF CURRENT WORK ZONES

10

slide-11
SLIDE 11

WORKS LOOKAHEAD

11

slide-12
SLIDE 12

ENVIRONMENT UPDATE

12

slide-13
SLIDE 13

NOISE SO FAR – SUNDAY 13 OCTOBER

13

Building Unmitigated predicted noise level dB Night-time measured dB The Domain

<65 64

The Botanica

<65 64

Hallmark Apartments

<65 56

Domain Hill

<65 62

slide-14
SLIDE 14

NOISE SO FAR – MONDAY 14 OCTOBER

14

Building Unmitigated predicted noise level dB Night-time measured dB The Domain

>75 79

The Botanica

>75 79

Hallmark Apartments

>75 73

Domain Hill

>75 75

slide-15
SLIDE 15

NOISE SO FAR – TUESDAY 15 OCTOBER

15

Building Unmitigated predicted noise level dB Night-time measured dB The Domain

>75 70

The Botanica

>75 70

Hallmark Apartments

>75 66

Domain Hill

>75 66

slide-16
SLIDE 16

WORKS UPDATE

16

slide-17
SLIDE 17

ANZAC STATION PROGRAM

17

Melbourne cup site shut down 2-6 November 2019

slide-18
SLIDE 18

CURRENT AND UPCOMING WORKS NORTHERN SECTION

  • Excavation through the voids
  • Base slab construction
  • 24 hour works under the roof

slab

Under the roof slab 18

slide-19
SLIDE 19

19

EXCAVATION

slide-20
SLIDE 20

STRUTTING, LOOKING SOUTH

20

slide-21
SLIDE 21

UPCOMING WORKS BASE SLAB CONSTRUCTION

21

slide-22
SLIDE 22

BASE SLAB CONSTRUCTION

  • Start at southern end and move north in seven sections over two stages
  • Similar methodology as roof slab
  • First stage of base slab construction will require protection of the South Yarra

Main Sewer

  • 24 hour works under the roof slab

22

Illustration of sewer protection works Northern section of the station box layout

slide-23
SLIDE 23

23

UNCOVERING THE SEWERS

slide-24
SLIDE 24

SEWER PROTECTION WORKS

24

slide-25
SLIDE 25

MIDDLE BOX

25

slide-26
SLIDE 26

DIAPHRAGM WALL AND PILING

26

Works in the southern section of the station box

slide-27
SLIDE 27

SITE LAYOUT

27

Artists impression After realignment map Indicative only

slide-28
SLIDE 28

UPCOMING WORKS TUNNEL BORING MACHINE DELIVERY

28

slide-29
SLIDE 29

DELIVERY LOGISTICS

  • Deliveries must be made overnight to

minimise impacts on traffic and trams

  • 40 oversized deliveries starting from

between late November and May

  • Working with Yarra Trams and

VicRoads on best route options as tram wires need to be lifted to allow for some pieces to be delivered.

29

Tunnel boring machine cutterhead delivery western precinct

slide-30
SLIDE 30

CREATIVE PROGRAM UPDATE

30

slide-31
SLIDE 31

METRO TUNNEL CREATIVE PROGRAM ARTWORK

Watercolour herbarium By Caitlin Klooger, 2019

slide-32
SLIDE 32

DOMAIN ROAD POP-UP PARK UPDATE

  • Fabrication of the Domain Road Pop-up

park currently occurring offsite.

  • Structure will be transported in a series of

modules and installed on site.

  • Planting consistent with Royal Botanic

Garden’s ‘Landscape Succession Strategy’.

  • Images provide reference to the look and

feel of planting for the Domain Road Pop- Up Park.

slide-33
SLIDE 33

METRO TUNNEL CREATIVE PROGRAM POP-UP PARK PROGRESS

Domain Road Pop-up Park

  • Installation for later in the year.
  • Built offsite to minimise disruption

with planting to occur onsite. Albert Road Reserve Pop-up Park

  • Ongoing work occurring offsite
  • Installation anticipated for early 2020.
slide-34
SLIDE 34

THANK YOU