DOE FEDERAL PROJECT DIRECTOR’S PERSPECTIVE ON THE HIGH LUMINOSITY LHC ACCELERATOR UPGRADE PROJECT READY FOR CD-1/CD-3a Jerry Kao Federal Project Director August 8, 2017
1
DOE FEDERAL PROJECT DIRECTORS PERSPECTIVE ON THE HIGH LUMINOSITY - - PowerPoint PPT Presentation
DOE FEDERAL PROJECT DIRECTORS PERSPECTIVE ON THE HIGH LUMINOSITY LHC ACCELERATOR UPGRADE PROJECT READY FOR CD-1/CD-3a Jerry Kao Federal Project Director August 8, 2017 1 Presentation Topics Introduction HL-LHC Organization
1
2
3
4
Project Management
G. Apollinari
Q1/Q3 Cryoassemblies Fabrication
G. Ambrosio
Office
High Energy Physics
James Siegrist, Associate Director Simona Rolli, DOEProgram Manager
Fermi Research Alliance, LLC M&O Contractor
Nigel Lockyer, Director S. Belomestnykh, Chief Technical Officer
US HL-LHC Accelerator Upgrade Project (HL-LHC AUP)
G. Apollinari, Project Manager R. Carcagno, Deputy Project Manager
Office
Project Assessment
Stephen Meador, Director
RFD Dressed Crab Cavities Fabrication
L. Ristori
Project Support
J. Blowers, QA Manager C. Trimby, Budget Officer T. Powers, Procurement Liaison R. Marcum, Lead Project Control S. Scott, Project Control (R. Carcagno), Risk Liaison
Rev. 23rd May.
DOE Fermi Site Office
Michael Weis, Site Manager Chih-Ming(Jerry) Kao, DOE Federal Project Director
ES&H Manager
A. Pavnika Integrated Project Team
CERN HL-LHC Project Office
L. Rossi, Project Leader O. Bruning, Deputy Project Leader DOE Fermilab Personnel CERN Personnel
Office
Science
J. Steve Binkley (A), Project Management Executive
5
Parameters Threshold Performance Objective Performance
Inner Triplet Focusing Quadrupoles (Q1 and Q3) a) 5 Q1-Cryoassemblies and 4 Q3- Cryoassemblies are accepted by CERN after testing at HL-LHC nominal temperature and ultimate gradient for the magnets, and functionality for the Cryoassembly. The Cryoassemblies will be assembled from Cold Masses built by HL-LHC AUP and Cryostat kits provided by CERN. b) Procurement of components for 1 additional Q3 Cold Mass 1 additional Q3-Cryoassembly is accepted by CERN after testing at HL- LHC nominal temperature and ultimate gradient for the magnets, and functionality for the
be assembled from Cold Masses built by HL-LHC AUP and Cryostat kits provided by CERN SRF Crab Cavities a) 8 Radio Frequency Dipoles (RFDs) Dressed cavities for the HL-LHC Crab Cavity System are accepted by CERN after being tested at HL-LHC nominal temperature, nominal frequency, and ultimate cavity voltage. Dressed cavities include HOM couplers, pick- ups, He Vessel and magnetic shields. b) Procurement of components for 2 additional RFD Dressed Cavities 2 additional Radio Frequency Dipoles (RFDs) Dressed cavities for the HL-LHC Crab Cavity System are accepted by CERN after being tested at HL-LHC nominal temperature, nominal frequency, and ultimate cavity
couplers, pick-ups, He Vessel and magnetic shields.
6
Labor Hrs Direct M&S Dollars Burdened Dollars Est Uncertainty Contingency (EUC) EUC % Burdened $ + EUC 302.1 Project Management 122,210 $ 582,500 $ 27,534,386 $ 2,753,439 10% $ 30,287,824 302.1 Project Management 122,210 $ 582,500 $ 27,534,386 $ 2,753,439 10% $ 30,287,824 302.2 Q1/Q3 Cryo-assembly Fabrication 468,434 $ 44,217,428 $ 129,356,546 $ 29,842,650 23% $ 159,199,197 302.2.01 Cryo-assembly Design, Integration, and Coordination 134,783 $ 842,206 $ 29,669,244 $ 6,841,218 23% $ 36,510,462 302.2.02 Strand Procurement and Testing 16,546 $ 17,120,689 $ 21,114,995 $ 2,526,106 12% $ 23,641,101 302.2.03 Cable Fabrication 23,773 $ 800,044 $ 4,605,670 $ 1,064,660 23% $ 5,670,331 302.2.04 Coil Parts, Materials, and Tooling Procurement 9,564 $ 4,507,054 $ 6,801,485 $ 1,359,974 20% $ 8,161,459 302.2.05 Coil Fabrication at FNAL 66,978 $ 220,500 $ 6,772,162 $ 1,388,623 21% $ 8,160,785 302.2.06 Coil Fabrication at BNL 70,442 $ 1,081,320 $ 12,709,802 $ 3,200,028 25% $ 15,909,830 302.2.07 Structure Fabrication and Magnets Assembly 52,138 $ 14,076,343 $ 26,075,187 $ 7,630,055 29% $ 33,705,242 302.2.08 Magnets Vertical Test 34,289 $ 2,831,424 $ 9,928,963 $ 1,744,917 18% $ 11,673,880 302.2.09 Cold Mass Assemblies Fabrication 17,562 $ 1,114,633 $ 4,095,444 $ 1,345,783 33% $ 5,441,226 302.2.10 Cryo-assemblies Fabrication and Shipment 17,780 $ 438,874 $ 2,553,305 $ 1,127,610 44% $ 3,680,915 302.2.11 Cryo-assemblies Horizontal Test 24,579 $ 1,184,343 $ 5,030,290 $ 1,613,676 32% $ 6,643,966 302.3 RFD Dressed Crab Cavities Fabrication 46,837 $ 6,142,858 $ 16,573,214 $ 5,596,094 34% $ 22,169,307 302.3.01 RFD Cavities Design, Integration, and Coordination 27,936 $ 367,500 $ 6,202,183 $ 2,033,204 33% $ 8,235,387 302.3.02 RFD Cavities Fabrication and Testing 18,901 $ 5,775,358 $ 10,371,031 $ 3,562,890 34% $ 13,933,920 Total Burdened + EUC 637,481 $ 50,942,786 $ 173,464,146 $ 38,192,182 22% $ 211,656,328 Risk Contingency (90% CL) 9% $ 15,888,604
Total Project Cost (TPC)
31%
$ 227,544,938
7
8
9
Acquisition Strategy 470 N/A Completed To be Approved
93 N/A Completed To be Approved Risk Management Plan 339 N/A Approved N/A Requirements Magnets 36 Approved Accepted N/A Cold Mass 64 V0.5 Accepted N/A Cryostat Assembly 246 Initiated N/A RFD Cavities 294 Approved Accepted N/A CDR Magnets 140 N/A Approved N/A RFD Cavities 164 N/A Approved N/A
303 N/A Approved N/A Integrated Safety Management Plan 201 N/A Approved N/A Preliminary Quality Assurance Prog. 80 N/A Approved N/A NEPA Determinations 101 (FNAL) 515 (LBNL) 530 (BNL) N/A Achieved N/A
10
11