DOE IPR
LHC CMS Upgrade Project
Alan Harris Federal Project Director
DOE IPR LHC CMS Upgrade Project Alan Harris Federal Project - - PowerPoint PPT Presentation
DOE IPR LHC CMS Upgrade Project Alan Harris Federal Project Director Outline Purpose and Scope WBS Completion Definition (KPPs) Schedule Cost and Funding ES&H Project Status Conclusions 2
Alan Harris Federal Project Director
2
upgrades
the Barrel and Endcap with silicon photomultipliers, readout electronics to increase bandwidth, off-detector electronics for higher bandwidth and improved trigger information
modules of 100 mm x 150 mm pixels, organized into 6 half-disks, housed in 2 half-cylinders
Trigger
3
4
WBS# WBS NAME 401
Large Hadron Collider (LHC) Compact Muon Solenoid (CMS) Detector Upgrade Project
401.01
Project Management
401.01.01
Project Milestones and Interfaces
401.01.02
Project Management and Administration
401.01.03
Project Controls and Finance
401.01.04
Project Office Support
401.02
Hadron Calorimeter (HCAL)
401.02.01
HCAL Milestones and Interfaces
401.02.02
HCAL Management
401.02.03
HF Frontend
401.02.04
HB/HE Frontend
401.02.05
HCAL Backend
401.03
Forward Pixel Detector (FPIX)
401.03.01
FPIX Milestones and Interfaces
401.03.02
FPIX Management
401.03.03
FPIX Components
401.03.04
FPIX Assembly and Testing
401.03.05
FPIX Pilot System
401.04
Trigger
401.04.01
Trigger Milestones and Interfaces
401.04.02
Trigger Management
401.04.03
Muon Trigger
401.04.04
Calorimeter Trigger
Threshold KPP- defined to de-couple from CERN LHC Shutdown schedule
Objective KPP- Complete installation only if Shutdown schedule allows
Detector
5
6
and trigger emulation using test data patterns
from current system
emulation using test data patterns
7
8
Level 2 milestones have a 6 month float from the corresponding technical milestones
9
As of August 2015
Fiscal Year 2013 2014 2015 2016 2017 2018 2019 2020 Total OPC - Design 1.50 6.75 3.75 12.00 TEC - MIE 3.75 9.50 8.00 21.25 Total DOE 1.50 6.75 7.50 9.50 8.00 33.25 NSF (June 15-June 14)* 0.45 3.50 4.50 1.20 2.00 0.30 11.95 Total 1.95 10.25 12.00 10.70 10.00 0.30 0.00 0.00 45.20 * Year 1 prespending from Jan 1
10
11
– Goal of installation during the 2015-1016 technical stop
– KPP just to build and deliver FPIX equipment – FPIX is not on critical path and has 1.3 years of float
12
13