DOE Review of LARP – Feb 17-18, 2014
DOE Critical Decision Process
Ruben Carcagno February 17, 2014
1
DOE Critical Decision Process Ruben Carcagno February 17, 2014 1 - - PowerPoint PPT Presentation
DOE Critical Decision Process Ruben Carcagno February 17, 2014 1 DOE Review of LARP Feb 17-18, 2014 Outline Standard DOE/SC Critical Decision Process Tailoring for LARP CD Consolidation LARP actions needed prior to CD process
DOE Review of LARP – Feb 17-18, 2014
1
DOE Review of LARP – Feb 17-18, 2014
2
DOE Review of LARP – Feb 17-18, 2014
3
DOE Review of LARP – Feb 17-18, 2014
Critical Decisions Request PED Funds Definition Initiation Execution Closeout Operating* Funds Operating Funds PED Funds Construction & PED Funds
*
Request Construction Funds
2013 2014 2015 2016 2018 2017
Receive/spend Construction Funds Receive/Spend PED Funds
Project and Budget Process—Standard Scenario
2019
Conceptual Design Preliminary Design Final Design Construction CY
CD-1 Approve Alternative Selection and Cost Range CD-4 Approve Start of Operations or Project Completion CD-3 Approve Start
Construction
CD-2 Approve Performance Baseline (PB) CD-0 Approve Mission Need
4
DOE Review of LARP – Feb 17-18, 2014
approval date
5
DOE Review of LARP – Feb 17-18, 2014
the project’s defined scope by a particular date at a specific cost.
receives the funds for construction.
– During this time, PED funds can be used for long-lead procurement (LLP). LPP approval is designated as CD-3A, which may happen in advance of CD-2 approval.
6
DOE Review of LARP – Feb 17-18, 2014
7
DOE Review of LARP – Feb 17-18, 2014
requirements for documentation, reviews, and approval authority
8
Documented in DOE/SC Project Decision Matrix:
http://science.energy.gov/~/media/opa/pdf/processes-and-procedures/Project_Decision_Matrix_11_2010_p.pdf
DOE Review of LARP – Feb 17-18, 2014
Equipment (MIE)
– This designation is only used by the Office of Science for large capital equipment projects – It is designed to be more flexible than Line Item Construction (LIC) projects
– Equipment will be used for > 3 years – Equipment cost (TEC) > $2M or Total Project Cost (TPC) > $5M – Prototypes NOT included, unless will be incorporated into the final experiment
– For MIE projects “Fabrication” is used rather than “Construction”
9
DOE Review of LARP – Feb 17-18, 2014
– Engineering and design of final instrument – Fabrication of capital equipment
– Conceptual Design Report – R&D, prototyping and testing – Installation and commissioning/pre-operations before CD-4
10
DOE Review of LARP – Feb 17-18, 2014
11
DOE Review of LARP – Feb 17-18, 2014
12
DOE Review of LARP – Feb 17-18, 2014
– WBS Dictionary – Work Package
– Planning Package
later stage and converted to a Work Package
– Defines L1, L2, and L3 managers and their areas of responsibility
– WBS and OBS Intersection
– Minimum WBS level where cost and schedule performance is compared to baseline
– Expected to be L2 Managers, after adequate training (e.g., 2-day EVMS training) – Responsible for Control Account Plan, performance of the Control Account, and managing resources – Monthly reporting – Variance Analysis
13
DOE Review of LARP – Feb 17-18, 2014
– Milestones, Key Events, Technical Performance Measures
– Time-phased budget plan against which performance is measured
– Document, track, and communicate changes to the PMB
and reporting monthly
– System must be in place, effective, tracking project progress, and reporting into DOE PARS II prior to CD-2 approval – Agree on project thresholds and triggers (green/yellow/red) for cost and schedule variance
explanation and corrective actions.
14
DOE Review of LARP – Feb 17-18, 2014
and senior management approval
Variance Analysis Thresholds for Control Accounts Green Thresholds – Cost and Schedule Performance falling outside of yellow or red thresholds Yellow Thresholds
Cost Variance Schedule Variance Type Threshold limit Dollars Current Period
≥ ± 5% to < ± 10% and ≥ $50K
Cumulative
≥ ± 5% to < ± 10% and ≥ $100K
Hours Current Period
≥ ± 5% to < ± 10% and ≥ 350 hrs
Cumulative
≥ ± 5% to < ± 10% and ≥ 700 hrs
Red Thresholds
Cost Variance Schedule Variance Type Threshold limit Dollars Current Period ≥ ± 10% and ≥ $100K Cumulative ≥ ± 10% and ≥ $200K Hours Current Period ≥ ± 10% and ≥ 700 hrs Cumulative ≥ ± 10% and ≥ 1400 hrs
Note: This applies to SV% (Schedule Variance in %) or CV% (Cost Variance in %) and the SV or CV in $ or hours.
15
DOE Review of LARP – Feb 17-18, 2014
BCWS Updated ETC ACWP ORACLE ™ e-Business Suite - Project Costing Module
Cost Processor Deltek Cobra
(BCWP Calculated In Cost Processor)
Physical % Complete CPRs Review and Analyze CPRs Prepare VAR Issue Monthly Report w/narrative Review/Approve VAR
Scheduling Tool
Base-Line Data
Performance Data
Monthly
Actual Cost
ORACLE ™ e-Business Suite - Procurement Module
Material Received Accruals
CV/SV Trigger Thresholds
Yes
Manual Accruals
No
Manual Accruals PARS II
External Organizations
16
DOE Review of LARP – Feb 17-18, 2014
Director (when appointed by DOE). Examples (from Project Decision Matrix):
– Mission Need Statement
– Acquisition Strategy
– Project Execution Plan (PEP)
– Project Management Plan (PMP)
– Preliminary Design Report
– Performance Baseline (PB)
Parameters (KPPs)
17
DOE Review of LARP – Feb 17-18, 2014
becomes a DOE 413.3B Project, the LARP PMO goal will be to remain in the DOE Project Dashboard “Green” category
18
DOE Review of LARP – Feb 17-18, 2014
in Q3FY18
– ~ $6.3M in Pre-MIE funding (preliminary)
– ~ $3.7M in Pre-MIE funding (preliminary)
expected January 2019
– Pre-MIE funding needs being identified
19
DOE Review of LARP – Feb 17-18, 2014
– Starts Q4FY16
– Starts Q1FY18
– Starts Q3FY18
– 13% at contract award – 27% 6 months ARO – First delivery 12 months ARO – 1000 kg of wire every two months
20
$1,885 $4,372 $5,494 $2,747 $0 $0 $0 $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 FY-16 FY-17 FY-18 FY-19 FY-20 FY-21
CD-0/1/2 CD-3 MIE Funds ($8.25M) Pre-MIE Funds ($6.3M)
DOE Review of LARP – Feb 17-18, 2014
21
Magnet Fabrication Tooling FY17
Winding and Curing tooling (mandrel) $710 Coil handling/storage $990 Portable CMM Machine $219 Reaction and Impregnation tooling $1,607 Cold mass assembly tooling $178 TOTAL $3,704
DOE Review of LARP – Feb 17-18, 2014
– For example, equivalent level of readiness for CD-0 in FY15, CD-1 in FY16, and CD-2 in FY17
22