1
Distributed Energy Resources: Maintaining Reliability & Integrating New Technology
Solar Stakeholder Collaborative for New Jersey
October 4, 2016 – Morning Session
Distributed Energy Resources: Maintaining Reliability & - - PowerPoint PPT Presentation
Distributed Energy Resources: Maintaining Reliability & Integrating New Technology Solar Stakeholder Collaborative for New Jersey October 4, 2016 Morning Session 1 Welcome to Pepco Holdings Distributed Energy Resources (DER)
1
October 4, 2016 – Morning Session
2
3
4
5
April 7, 2016
6
7
Application Received GPC verifies information & enters in WMIS 10* kW or Less DERP&A Reviews Above 10* kW DERP&A, Distribution, and Protection review Approval to Install issued
Interconnection Metrics Completion Commitment (Business Days) Pepco - DC Pepco - MD DPL - MD DPL - DE ACE Acknowledgement
10 5 5 5 3
Authorization to Install
15 15 15 15 10
Authorization to Operate 1,2
20 20 20 20 20
[1] Also referred to as “Permission to Operate” [2] PHI completes its interconnection-related construction prior to issuing “Authorization to Operate” in accordance with jurisdictional requirements
and timelines
Expedited Technical Review Process for Successful Applications
* System size qualifying for expedited review will be raised from 10 kW to 25 kW beginning September, 2016.
8
9
February 1, 2016
Small Application Review Pre-screen Screen Advanced Study
10
– Arrays that exceed 75% will receive a secondary voltage rise analysis
11
February 1, 2016
12
February 1, 2016
13
February 1, 2016
14
February 1, 2016
15
February 1, 2016
16
February 1, 2016
17
proposed system output does not cause the network protector to operate, the following control scheme is required:
inverters that can receive a control signal and curtail output to maintain the target level of import or export on each phase
access to view the electrical parameters and operation of the system
goes beyond a Company defined set point
second Company determined set point and will send another alert to PHI
the utility
February 1, 2016
18
less than 1/3
includes overall reach of the protecting devices.
19
20
February 1, 2016
21
22
23
Minimum Daytime Load (MDL) Max Load Point Low Load Point Max PV Point Max PV/Load Ratio Max Difference Point
24
Power Research) PV output service
Analysis
25
CPR provides irradiance based generation modelling for PV systems System output is applied to DEW component and used in Power Flow calculations Minimum input requirements:
26
27
from the GIS system.
database which now has over 26,000 systems.
28
29
30
31
February 1, 2016
32
33
Principal Engineer National Renewable Energy Laboratory
35
PG&E SCE SDG&E SMUD NSP Com Ed Detroit Edison Nashville Electric PSCO PNM APS Tri County Electric Coop Austin Power SPS NSTAR National Grid Con Ed O&R Central Hudson LIPA PEPCO
36
37
Install PV PTO
38
39
line section
is inverter‐based, aggregated DG capacity is <5% of peak load & <50 kW
maximum short circuit current is <10%
protective device to exceed 87.5% of short circuit interrupting capability
primary distribution line (wye/Delta)
Aggregated DG capacity <20kW
transformer rating of 240 V service
capacity <10 MW for stability‐limited area
interconnection
40
41
42
43
44
45
46
Michael.coddington@nrel.gov
47
April 7, 2016
48
a load
generation
treatment
supplied from the grid or only from renewable generation?
February 1, 2016
49
February 1, 2016
50
PV system, then the maximum power flow fluctuation would be the import to export range of the inverter. For example, a 10 kW inverter system that can import or export 10 kW will be evaluated for the scenario where the power flow may fluctuate by 20 kW.
then the aggregate impact of the power flow fluctuation of the battery and generation will be evaluated.
frequency regulation (FR), then the aggregate will be studied as acting
to regional transmission operator (RTO) FR signals.
evaluated as a load.
51
52
April 7, 2016
53
used in the design of new and modified portions of the distribution system. These criteria govern how:
– Load carrying capacity of system facilities are determined and utilized – Required service voltage levels are maintained
54
54
55
In addition to ongoing improvements, PHI has also implemented several enhancements which specifically address the Company’s Merger Commitment which states PHI must: “…include an analysis of the long term effects/benefits of the addition of behind-the- meter distributed generation attached to the distribution system within its service territory, including any impacts on reliability and efficiency. PHI will also work with PJM to evaluate any impacts that the growth in these resources may have on the stability of the distribution system.
process, including (where necessary) the generation profile of the resource relative to load/demand so that no detrimental impacts are introduced to the system or other customers.
generation on distribution automation (DA)
impact DA schemes, the company will make reasonable investments to mitigate the impact.
Reliability Efficiency
distributed energy resources in the planning process when the aggregate amount of PV on a circuit exceeded 1 MVA.
peak demand using a 22% capacity factor.
levels of DER and any corresponding impacts they may have on future load growth and
construction recommendations.
56
The planning process is composed of short-term and long-term plans. 1. Biennial plans for each feeder in the utility service territory are developed
engineering analyses to identify any near-term (i.e., over next three years) violations of the planning criteria
– Actions to mitigate any violations are developed and issued as construction recommendations and result in capital and/or O&M projects
2. A ten-year plan for the entire service territory is developed every year
extension of the short-term load forecasts to encompass a ten-year horizon, and higher-level engineering analyses to identify potential violations of the planning criteria (typically over the ten-year horizon to identify large construction projects that require more than two-years lead time)
– Actions to mitigate any violations are developed and result in potential capital projects, in addition to those identified in the short-term plan
Annually these plans are reviewed to evaluate actual and projected loads and to make adjustments that could be impacted by changes in commercial construction programs, energy efficiency, DER growth or other new technologies such as electric vehicles (EVs).
57
– Actual loadings are obtained through PHI’s EMS or through field measurements – Loadings are analyzed to develop a base history reflective of peak loadings during extreme (90/10) weather conditions for use in forecasting future facility loadings
58
PJM Coincident Historical Peak (7/21/2011) Hour ACE Non-Coincident Substation Peaks Peak Hour 17:00 Sea Isle 17:00
Tabernacle
15:00 Dacosta 16:00 Churchtown 15:00
59
Resource Type Description Pepco DC Pepco MD DPL MD DPL DE ACE Programs which PHI has direct control over EnergyWise Rewards Demand Response Energy Wise cycles customer-level A/C or heat pumps under three cycling options during "peak saving days" to decrease the demand for electricity.
Conservation Voltage Reduction Energy Efficiency Voltage set-points can be lowered within ANSI limits to increase energy/demand savings with no change in customer behavior required.
Programs which PHI administers Peak Energy Savings Credit Demand Response PESC is a form of dynamic pricing where consumers can save money via a rebate for reducing consumption on peak demand days.
*
Energy Management Tools Energy Efficiency EMT allows customers to better understand their energy consumption patterns and provides opportunities to save energy and decrease monthly costs.
Other Programs / Resources Behind-the- meter Distributed Generation Generation The impact of BTM generation depends upon both the type of generation and production profile and the attributes of the circuit to which it is interconnected.
PJM Demand Response Demand Response Programs administered by Energy Service Curtailment providers which have an impact at the system/load zone level and is not directly controlled by PHI.
Residential EE&C Energy Efficiency Residential EE&C includes a suite of programs including lighting, appliances, home check-up, ENERGY STAR, new construction, HVAC, and low income.
Commercial & Industrial EE&C Energy Efficiency Commercial and industrial programs include: multi-family, multi-dwelling, small business, prescriptive/existing buildings, new construction, retrocommissioning, CHP/
*PESC was piloted in DC, but there is currently no dynamic pricing program
60
circuit (MVA)
(MVA)
modifying resources on the corresponding circuit
requires accounting for circuit specific attributes as well as the characteristics
direct control over some programs (e.g. DLC, CVR), these may not be available to be called upon in all peaking
EMT) depend on customer behavior.
System/Circuit Attributes
DER Resource Characteristics
Triggers and Control
61
61
62
12:00 AM 1:00 AM 2:00 AM 3:00 AM 4:00 AM 5:00 AM 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:00 PM NJ0987 0% 0% 0% 0% 0% 0% 1% 13% 30% 47% 61% 69% 76% 76% 70% 62% 48% 32% 15% 1% 0% 0% 0% 0%
0% 10% 20% 30% 40% 50% 60% 70% 80% CAPACITY FACTOR OF PV HOUR OF DAY AND CORRESPONDING CAPACITY FACTORS
Average Hourly Summer (Jun – Aug) PV Capacity Factors for 2015
In order to accurately account for the impact of Distributed PV in planning, PHI requires:
Note: Actual hourly production capacity will rarely achieve 100% of nameplate rating due to factors which include cloud cover, panel efficiency loss due to temperature, panel tilt and orientation, and shading NJ0987 Peak Demand Hour
63
ACE Feeders Feeder Historical Peak (MVA) Feeder Peak Hour Nameplate PV (kW) PV Capacity Factor for Feeder Peak Hour PV Impact on Peak (kW) NJ0994 15.0 12:00 1838.5 76% 1397.3 NJ0987 16.8 17:00 2024.9 32% 648.0 NJ1983 13.6 17:00 3503.0 32% 1121.0 NJ2094 17.0 11:00 287.3 69% 198.2 NJ0428 8.3 20:00 3965.8 0% 0.0
No impact Significant impact
Note: This is an extrapolation based upon the production curve presented in the previous slide. For planning purposes PHI can model each feeder individually to account for the impacts of PV.
64
65