Disconnections processes – update to ECSG
Dan Cantle, Senior Consultant 25th May 2011
Disconnections processes update to ECSG Dan Cantle, Senior - - PowerPoint PPT Presentation
Disconnections processes update to ECSG Dan Cantle, Senior Consultant 25 th May 2011 Progress to Date Following discussions with industry stakeholders, issue raised to MRA regarding processing of disconnections Special MRA
Dan Cantle, Senior Consultant 25th May 2011
MRA regarding processing of disconnections
understand key drivers
– Processes for large scale disconnections – Technical solutions to improve data flow – Potential changes for ‘single site’ disconnections
Resolution Expert Group (IREG)
– Issued for Impact Assessment early June – MRA Development Board scheduled to vote on solutions 30th June – Implementation likely for November 2011 or February 2012
– A new Working Practice for large scale disconnections – A standardised data flow format for passing data between Distributors and Suppliers – Changes to data items to better fit industry and business processes
– Expansion of the Working Practice to include single sites – Adopting an Agreed Procedure to enforce the working practice (following ‘trial period’ – Further changes to data items to improve flow of information in processes
disconnections
less need to contact multiple parties
information to initiate the process
– Addresses of the properties; – Date from which the Developer will have responsibility for the site; – Point of contact for the Developer – Point of contact for site access if different to above
– MPANs and Meter Serial Number(s), if known; – Planned demolition date; – Earliest dates for both meter removal and disconnection
– Where all information provided, Distribution Business will normally quote within 20 Working Days – Suppliers sent Disconnection notices within 5 Working Days of price being agreed with developer – Suppliers will have 25 Working Days to remove meters – If no meters on site, disconnection as quick as 5 Working Days.
– Incomplete or incorrect data provided to Distribution Business – Suppliers seeking to recover asset costs from developer – this will NOT delay disconnection of the supply. – Distribution Business requiring permissions – wayleaves, traffic orders etc. – Lack of site access at agreed times
disconnections, e.g.
– Address information (plot to postal etc.) – Multi-utility connection and disconnection
information expected shortly
raise changes as appropriate
issues and developing industry solutions
Dan Cantle
Gemserv Limited 10 Fenchurch Street London, EC3M 3BE Tel: +44 (0)20 7090 1020 daniel.cantle@gemserv.com www.gemserv.com