Competition in Connections Review Presentation to the ECSG Roger - - PowerPoint PPT Presentation

competition in connections review
SMART_READER_LITE
LIVE PREVIEW

Competition in Connections Review Presentation to the ECSG Roger - - PowerPoint PPT Presentation

Competition in Connections Review Presentation to the ECSG Roger Morgan, Senior Manager Connections Policy 5 July 2006 Overview of slides summary of responses to May 06 consultation letter - voluntary standards, overhead line works,


slide-1
SLIDE 1

5 July 2006

Competition in Connections Review

Presentation to the ECSG – Roger Morgan, Senior Manager Connections Policy

slide-2
SLIDE 2

5 July 2006

Overview of slides

summary of responses to May 06 consultation letter - voluntary standards, overhead line works, IDNOs, DNO affiliates, unmetered SLA potential scope of August consultation document – formal

  • bligations / increased regulation, regulation of affiliates,

connections application process next steps

slide-3
SLIDE 3

5 July 2006

Summary of responses - voluntary standards

  • f service

13 respondents (including one DNO) support formalising standards – voluntary approach is not delivering required level of performance little science behind the formulation of the standards – review can address this standards are effective if adhered to – introduce RIGS to ensure a consistent approach

slide-4
SLIDE 4

5 July 2006

Contestable overhead line works

  • four DNOs support the grouping of some overhead line works
  • ne DNO suggests that the contestable/non-contestable split should

not be altered – already contestable at LV and HV

  • ne ICP / DNO suggests that this is a minor issue that may detract from

the more fundamental concerns that need addressing through the Review

slide-5
SLIDE 5

5 July 2006

IDNOs (1)

majority of DNOs suggest that a number of DNO/IDNO interface issues need resolving:

  • need for a forum to debate interface issues
  • effects of networks on resilience of upstream networks
  • increased volumes of connections applications for DNOs

since the introduction of IDNOs

slide-6
SLIDE 6

5 July 2006

IDNOs (2)

  • premature to review IDNO framework - let arrangements bed in
  • IDNOs suggest that the following DNO/IDNO interface issues need to

be resolved:

  • exit point capacity charges
  • boundary metering and boundary metering charges
  • managing system security and multiple points of connections
  • dual access to isolation equipment
  • voltage drop issues
slide-7
SLIDE 7

5 July 2006

DNO affiliates

  • mixed views from DNOs - some support inclusion within the Review, some
  • ppose on the basis that adequate measures are in place - (SLC 4C)
  • some DNOs and ICPs suggest that the SP Manweb commitments should apply

to all DNOs with affiliates

  • IDNO concerns: affiliates benefit in terms of access to info and sharing of

resources, affiliates distort true competition

  • Ofgem should focus on compliance with existing legislation to address

behavioural concerns

  • energywatch: supports affiliates as long as they do not create barriers to entry /

formal obligations should be put in place

slide-8
SLIDE 8

5 July 2006

Unmetered service level agreement (1)

DNO views:

  • support concurrent obligations on both parties to make the

SLA work

  • explore whether a voluntary or statutory scheme is

required

  • definitional issues surrounding the SLA need to be resolved

and robust reporting arrangements are required

slide-9
SLIDE 9

5 July 2006

Unmetered service level agreement (2)

Local Authority views:

  • the SLA trial has encouraged DNOs to take street lighting

more seriously

  • two options (a) a national SLA with GSOPs or (b) a national

SLA with locally agreed standards of service

slide-10
SLIDE 10

5 July 2006

Potential scope of August consultation document (1)

  • Introduce formal obligations / increased regulation?
  • voluntary or formal standards
  • closer regulation of non-contestable activities – POC
  • introduce an improved and more effective dispute resolution process
  • Connections application process:
  • amend timescales for the provision of formal offers
  • extent of changes required to streamline the connections application

process

slide-11
SLIDE 11

5 July 2006

Potential scope of August document (2)

Affiliates:

  • establish procedures and reporting requirements governing

the service an affiliate and non affiliate receive – SP Manweb commitments?

  • structural changes to separate monopoly from contestable

activities?

slide-12
SLIDE 12

5 July 2006

Potential scope of August document (3)

  • IDNOs
  • should we review the IDNO regulatory framework?
  • Unmetered connections services
  • continue with voluntary approach with performance targets –

formalise licence conditions/GSOPs?

  • consider extent of further measures and policies to increase

competition – is more work required in this respect?

slide-13
SLIDE 13

5 July 2006

Next Steps

publish detailed consultation in August 06 further workshops – focus on specific areas likely to include:

  • reviewing and setting new standards: industry input and

guidance required

  • formal obligations: what is the most appropriate route
slide-14
SLIDE 14

5 July 2006

Promoting choice and value for all gas and electricity customers