Dielectric Strength Test Status B. Freemire IIT HPRF/Vacuum - - PowerPoint PPT Presentation

dielectric strength test status
SMART_READER_LITE
LIVE PREVIEW

Dielectric Strength Test Status B. Freemire IIT HPRF/Vacuum - - PowerPoint PPT Presentation

Dielectric Strength Test Status B. Freemire IIT HPRF/Vacuum Meeting September 9, 2015 Dielectric Strength Test Goal Determine the dielectric strength of each of the four purity (96, 98.5, 99.5 & 99.8%) samples of alumina Ramp up


slide-1
SLIDE 1

Dielectric Strength Test Status

  • B. Freemire

IIT HPRF/Vacuum Meeting September 9, 2015

slide-2
SLIDE 2

9/9/15

  • B. Freemire - HPRF/Vacuum Meeting

2

Dielectric Strength Test Goal

  • Determine the dielectric strength of each of the four purity (96, 98.5, 99.5 & 99.8%)

samples of alumina

Ramp up E-field slowly

  • May require some conditioning, as per past experience

Induce breakdown in the cavity and then back off in E-field until sparking stops

  • Use nitrogen to ease the safety requirements and compare measurements

with past results

  • Run at Station 2 to minimize conflict with MICE or MC programs

Repeat at different gas pressures

slide-3
SLIDE 3

9/9/15

  • B. Freemire - HPRF/Vacuum Meeting

3

Operational Pressure Range

  • Using existing spacers:

Pressure range for donuts:

  • 99.5%: 31.2 – 87.4 atm
  • 98.5%: 48.4 – 98 atm (safety)
  • 96%: 62.6 – 98 atm (safety)

Pressure points:

  • 99.8%: 35, 50, 75, 85
  • 99.5%: 35, 50, 75, 85
  • 98.5%: 50, 75, 85, 98
  • *96%: 65, 75, 85, 98
slide-4
SLIDE 4

9/9/15

  • B. Freemire - HPRF/Vacuum Meeting

4

Run Plan

1) Pressurize the cavity with 50 atm N2 2) Tune klystron at low power 3) Ramp up E-field in 1.0 MV/m steps 4) Wait 5-8 minutes at each step 1) Record 2 RF pulses 2) If no sparks observed, move on 3) If few sparks observed, wait longer 4) If many sparks observed, decrease E-field 5) ~2 hours to reach 14 MV/m 5) Once E-field limit reached, collect 5,000 pulses 1) Record every 500 pulses 2) ~2.75 hours at 0.5 Hz 6) Repeat at three other pressures, then return to 50 atm

slide-5
SLIDE 5

9/9/15

  • B. Freemire - HPRF/Vacuum Meeting

5

Timeframe

  • I would like to complete 2 gas pressures per day
  • 5 pressures / 2 per day = 2.5 days required per donut
  • 2.5 days per donut x 4 donuts = 10 days of data taking
  • 1 day setup per donut x 3 donuts = 3 days setup
  • 10 days data + 3 days setup = 13 days
  • Wait time and # of RF pulses may be affected by heating of cavity

Four thermocouples installed on HPRF cavity

  • Pressure window, coupler waveguide, end plate, cavity equator

Monitor pressure gauges during running

ACNET parameters:

  • Pressure – E:C8GLP1 & E:C8GLP2
  • Temperature – E:C2TC45-48
slide-6
SLIDE 6

9/9/15

  • B. Freemire - HPRF/Vacuum Meeting

6

Accomplished

  • Pressure test passed as of September 1st

Awaiting safety paperwork to be processed

  • Operational pressure relief valve installed
  • Full bottle of N2 ready

Purchase order for dry air completed

  • RF calibration complete

1 MV/m on axis = 1.75 MV/m on donut = 4.052 kW

Magnetic probe: -32.0 dB, electric probe: -34.4 dB

Q0 = 8,875

  • Cavity connected to waveguide and waveguide pressurized
  • Thermocouples reinstalled
  • (Most) Signal cables connected
slide-7
SLIDE 7

9/9/15

  • B. Freemire - HPRF/Vacuum Meeting

7

To Be Done

  • Check for leaks in new pressure relief valve
  • Connect optical fibers to cavity and PMT box
  • Connect signal cables to PMTs
  • Power PMTs
  • RF switch moved to position for Station 2
  • Verify DAQ configuration
  • Order new gaskets

Awaiting new drawings from Terry when he returns on Monday

Thicker radial diamond structure