DFARS Case 2017-D019 Performance-Based Payments and Progress - - PowerPoint PPT Presentation

dfars case 2017 d019 performance based payments and
SMART_READER_LITE
LIVE PREVIEW

DFARS Case 2017-D019 Performance-Based Payments and Progress - - PowerPoint PPT Presentation

DFARS Case 2017-D019 Performance-Based Payments and Progress Payments Wesley Hallman Senior Vice-President of Policy WHallman@NDIA.org, (703)2472595 Public Meeting September 14, 2018 1 9/10/2018 DFARS Case 2017-D019 INDUSTRY


slide-1
SLIDE 1

DFARS Case 2017-D019 Performance-Based Payments and Progress Payments

Wesley Hallman

Senior Vice-President of Policy WHallman@NDIA.org, (703)–247–2595

Public Meeting September 14, 2018

9/10/2018 1

slide-2
SLIDE 2

INDUSTRY CONCERNS

DFARS Case 2017-D019

9/10/2018 2

slide-3
SLIDE 3

Overview & Recommendation

  • This Rule…

– Discourages industry investment in innovation – Is duplicative and unnecessarily increases bureaucracy and oversight – Disrupts cashflow and drives prices higher – Distorts competition – Punishes contractors who accept high risk and challenging performance requirements – Contradicts congressional intent

  • We Recommend…

– That DoD rescind this proposed rule in its current form – Or extend the comment period and provide another public meeting with industry to discuss further

9/10/2018 3

slide-4
SLIDE 4

Decreases Investment in Innovation

  • Increasing working capital requirements for

production and slowing the recovery of capital via contract financing payments will reduce the capital available for:

– Innovation (Company-funded R&D + IRAD) – Affordability (Capital improvements)

  • This contradicts DoD’s emphasis on

innovation and capability

9/10/2018 4

slide-5
SLIDE 5

Increased Bureaucracy & Oversight

  • Currently, DoD has the ability to establish

performance requirements, metrics and incentives for each contractor

  • Implementation of this rule at the enterprise

level will complicate reporting and planning for both the contractor and government

  • This rule would create a duplicative

requirement and would add another layer of bureaucracy in an already cumbersome process

9/10/2018 5

slide-6
SLIDE 6

Disrupts Cashflow and Increases Prices

  • Cash flow disruptions at the Prime level will

flow down to all tiers of the supply chain

– Reducing lower-tier companies’ desire to do business with DoD – Negatively impacting contractors’ ability to meet basic payment requirements including payroll

  • Prices will increase as industry seeks greater

margins to offset loss of government provided financing

– Weighted Guidelines (WGL) calculations specifically allow for greater margins where industry has assumed greater financing risks

9/10/2018 6

slide-7
SLIDE 7

Distorts Competition

  • This rule allows the government to pick

“winners and losers” by subjective application

  • f the payment rate criteria
  • Contractors preserving (or enhancing) contract

financing payment rates will have a competitive advantage built in during the bidding process

– These companies/BUs can then bid lower prices and win more business

  • Historically, the government has avoided

allowing access to contract financing to become competitive advantage

– This is why interest on commercial financing is an unallowable cost

9/10/2018 7

slide-8
SLIDE 8

Punishes Contractors

  • Contractors that accept high risk and

challenging performance requirements are unfairly punished

  • Performance on all contracts will be

punished – even the highest performing – due to the challenges and risks in others

9/10/2018 8

slide-9
SLIDE 9

Contradicts Congressional Intent

  • Section 831 of the FY17 NDAA sought to align

DoD practices on performance-based payments with the FAR and remove barriers for their increased use

– (e.g. unique accounting systems/ties to cost incurred)

  • Section 831 did NOT address progress

payments based on cost

  • This proposed rule would:

– Erect new barriers for the use of PBPs and progress payments – Bring DoD further out of alignment with FAR based practices – Irrationally discriminate based on end item

  • (Selectively applying the rule to progress payments to aircraft, satellites,

vehicles, but not shipbuilding or Navy MRO work, etc.)

9/10/2018 9

slide-10
SLIDE 10

Recommendations

  • DoD should rescind this proposed rule
  • If not, extend the comment period and

provide another opportunity for industry to publicly comment

9/10/2018 10

slide-11
SLIDE 11

Thank You

9/10/2018 11

Direct questions to: Wesley Hallman, Whallman@NDIA.org