Decommissioning of MAX-lab Magnus Hrling 9 th International Workshop - - PowerPoint PPT Presentation

decommissioning of max lab
SMART_READER_LITE
LIVE PREVIEW

Decommissioning of MAX-lab Magnus Hrling 9 th International Workshop - - PowerPoint PPT Presentation

Decommissioning of MAX-lab Magnus Hrling 9 th International Workshop on Radiation Safety at Synchrotron Radiation Sources April 19-21, 2017 Taiwan Photon Source, Hsinchu, Taiwan Outline Facility Description Objective & Conditions


slide-1
SLIDE 1

Decommissioning of MAX-lab

Magnus Hörling

9th International Workshop on Radiation Safety at Synchrotron Radiation Sources April 19-21, 2017 Taiwan Photon Source, Hsinchu, Taiwan

slide-2
SLIDE 2

Outline

  • Facility Description
  • Objective & Conditions
  • Regulations
  • Approach
  • Phase 1 - Radiological Characterization
  • Phase 2 - Dismantling & Radiological

Clearance

  • Outcome & Costs

Decommissioning of MAX-lab / Outline

slide-3
SLIDE 3

Facility Description

slide-4
SLIDE 4

Facility Description (1/4)

  • Former Swedish national laboratory

for accelerator development, synchrotron light and nuclear physics research

  • The history of MAX-lab dates back to

the early 80’s

  • About 1000 users per year

Decommissioning of MAX-lab / Facility Description

slide-5
SLIDE 5

Facility Description (2/4)

Injector

  • Microtron

95 MeV 1984-2002

  • Linac

200/400 MeV 2001-2015 MAX I

  • Ø 32 m

200/550 MeV 1986-2015 MAX II

  • Ø 90 m

1500 MeV 1996-2015 MAX III

  • Ø 36 m

700 MeV 2007-2015 Nuclear physics

  • Prolonged runs at 10 Hz using MAX I as a pulse-stretcher
  • Significant losses in the injector and MAX I

Decommissioning of MAX-lab / Facility Description

slide-6
SLIDE 6

Facility description (3/4)

Decommissioning of MAX-lab / Facility Description

MAX II MAX III MAX I Injector Nuclear physics

slide-7
SLIDE 7

Facility Description (4/4)

Decommissioning of MAX-lab / Facility Description

slide-8
SLIDE 8

Objective & Conditions

slide-9
SLIDE 9

Objective & Conditions (1/2)

Objective:

  • Building to be emptied and returned to

the landlord

  • Building to be “cleared for free use” –

i.e. no longer subject to the terms and requirements of the Radiation Protection Act Physical conditions:

  • Local decay storage not an option
  • No dedicated or suited space for decay

storage on the MAX IV property

  • Alternate solutions for decay storage

were briefly considered, but decided not to be an option

  • → 3rd objective: Disposal of activated

material

Decommissioning of MAX-lab / Objective & Conditions

slide-10
SLIDE 10

Objective & Conditions (2/2)

Time constraints:

  • Facility to remain in operation until mid

December 2015

  • Dismantling to start immediately after

shutdown

  • Goal for (physical) completion set by

the management to the summer of 2016 Budget:

  • Total budget: 1500 k€
  • Estimated radiological cost: 650 k€

Decommissioning of MAX-lab / Objective & Conditions

slide-11
SLIDE 11

Regulations

slide-12
SLIDE 12

Regulations

The Swedish requirements for radiological clearance procedures are given by the regulatory code SSMFS 2011:2.

  • Nuclide specific clearance levels (Bq/g
  • r kBq/m2)
  • Generally harmonized to levels in

related EC RP publications

  • Before any clearance, a control

program has to be notified to the authority

  • Decisions on the clearance of

buildings are taken by the authority

  • n application by the licensee

Decommissioning of MAX-lab / Regulations

slide-13
SLIDE 13

Approach

slide-14
SLIDE 14

Approach

Given the time frame, personnel resources, legal requirements and lack of space the implementation of a comprehensive measuring and clearance program within the organization was not considered feasible. The decision was made to hire a contractor specialized in the field of radiological decommissioning and radioactive waste management. The radiological decommissioning was divided into two phases.

Decommissioning of MAX-lab / Approach

slide-15
SLIDE 15

Phase 1 – Radiological Characterization

slide-16
SLIDE 16

Phase 1 - Radiological Characterization (1/5)

The characterization - performed during the first half of 2015 - included:

  • Summary of operating history
  • Risk categorization of rooms and

material

  • Inventory and marking, database –

~800 objects/sections/surfaces

  • Pulse and dose rate measurements
  • Sampling of concrete and metal
  • Determination of nuclide vectors

Decommissioning of MAX-lab / Phase 1 – Radiological Characterization

slide-17
SLIDE 17

Phase 1 - Radiological Characterization (2/5)

Risk categorization of rooms and material:

  • Initially based on operating history

and facility knowledge

  • Protected (and normal) areas deemed

Extremely Low Risk (~6700 m2)

  • Conservative approach for controlled

areas (~1500 m2)

Decommissioning of MAX-lab / Phase 1 – Radiological Characterization

slide-18
SLIDE 18

Phase 1 - Radiological Characterization (3/5)

Risk categorization of rooms and material:

  • Pulse rate measurements used

primarily to confirm initial categorization

  • Results allowed for modifications of

the categorization (less conservative) – mainly exclusion of stands in MAX II and MAX III and recategorization of less critical room surfaces

Decommissioning of MAX-lab / Phase 1 – Radiological Characterization

slide-19
SLIDE 19

Phase 1 - Radiological Characterization (4/5)

General categorization of controlled areas and material inside. Injector, MAX I and Nuclear Physics BL:

  • Vacuum system, magnets etc
  • Other equipment, incl. stands
  • Room surfaces

MAX II and MAX III:

  • Vacuum system
  • Magnets, incl. IDs etc
  • Stands and peripheral equipment
  • Room surfaces

Decommissioning of MAX-lab / Phase 1 – Radiological Characterization

Above Clearance Level Risk Low Risk Extremely Low Risk

slide-20
SLIDE 20

Phase 1 - Radiological Characterization (5/5)

Determination of nuclide vectors

  • Sampling of concrete, wall filling

material and activated metal

  • Large uncertainties
  • Concrete samples showed induced

activity, but only up to ~ 60% of the clearance level

  • For all concrete samples, the naturally
  • ccurring radionuclides (mainly 40K

and 232Th) still dominated the activity content

Decommissioning of MAX-lab / Phase 1 – Radiological Characterization

Steel Co-60 1,0E+00 Sc-46 1,6E-01 Cr-51 1,6E+01 Mn-54 3,4E+01 Co-56 2,4E+00 Co-57 4,8E+01 Co-58 2,2E+00 Fe-59 1,8E-02 Y-88 5,0E-02 Zn-65 2,1E-02 Nb-95 2,6E-01 Concrete Co-60 1,0E+00 Na-22 1,1E+00 Sc-46 1,9E-01 Mn-54 4,0E-01 Co-58 1,0E+00 Cs-134 3,8E-01 Cs-137 2,9E-01 Eu-152 2,1E+00 Eu-154 5,2E-01 Eu-155 6,8E-01 Wall Filling Material Co-60 1,0E+00 Mn-54 1,9E+00 Zn-65 8,2E-01 Cs-134 3,7E-01 Eu-152 1,6E+00

Radionuclides measured in samples and average ratios to 60Co

slide-21
SLIDE 21

Phase 2 – Dismantling & Radiological Clearance

slide-22
SLIDE 22

Phase 2 – Dismantling & Radiological Clearance

(1/7)

Dismantling began with categorized material in controlled areas in January 2016.

  • Dismantling
  • Separation & Sorting
  • Packaging
  • Registration (contractor’s data base)
  • Shipping to contractor’s site

A separate contractor, hired for general dismantling and demolition of (the rest

  • f) the facility started work two months

later.

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

slide-23
SLIDE 23

Bulk shielding of the injector, nuclear physics and parts of MAX I:

  • Walls of 2-3 m thickness
  • Made out of gravel including stones of

varying sizes, supported by corrugated metal and beams

  • ~800 m3 of concrete like mass
  • Probably a great idea back in the day…
  • Turned out to be very challenging (and

costly) to remove

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

Phase 2 – Dismantling & Radiological Clearance

(2/7)

slide-24
SLIDE 24

Bulk shielding of the injector, nuclear physics and parts of MAX I:

  • Innermost 40 cm of the wall filling

material were separated for clearance measurments

  • Filled into big-bags and measured
  • When the innermost parts had been

separated and removed, the remaining masses could be dealt with in a less delicate way

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

Phase 2 – Dismantling & Radiological Clearance

(3/7)

slide-25
SLIDE 25

Local clearance of material:

  • Concrete blocks and wall filling

material was not shipped to the contractor – measured for clearance at MAX-lab

  • Dedicated measuring station set up by

the contractor (NaI probes)

  • 60Co content quantified and nuclide

vector applied

  • < 1000 kg material per measurement
  • Formally cleared by MAX-lab (control

program notified to authority)

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

Phase 2 – Dismantling & Radiological Clearance

(4/7)

slide-26
SLIDE 26

Clearance measurements of concrete bulk shielding and room surfaces:

  • Rooms completely emptied
  • HPGe equipment, collimated
  • Low Risk – one measurement per

surface, critically chosen area

  • Risk – measurements in a 1 x 1 m2 grid
  • 5 m2 measured at once when practical

(tm increased accordingly)

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

Phase 2 – Dismantling & Radiological Clearance

(5/7)

slide-27
SLIDE 27

Demolition of bulk shielding:

  • Could start when the data from the

clearance measurements had been analyzed

  • Cast concrete was segmented by

circular cutting and wire sawing

  • None of the bulk shielding concrete

could leave MAX-lab until the decision by the authority on the clearance of the building was received

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

Phase 2 – Dismantling & Radiological Clearance

(6/7)

slide-28
SLIDE 28

Clearance measurements and waste treatment of material shipped to contractor:

  • Nuclide specific measurements (HPGe)
  • f Low Risk and Risk material
  • Material categorized as Above Clearance

Limit is treated as Low Level Waste (LLW) – i.e. melted

  • Low Risk and Risk material found not to

be subject to clearance is also treated as LLW

  • Ingots from melting are measured and

either

– Subject to clearance – Stored for decay, or – Shipped to the national Final Repository (SFR)

Decommissioning of MAX-lab / Phase 2 – Dismantling & Radiological Clearance

Phase 2 – Dismantling & Radiological Clearance

(7/7)

slide-29
SLIDE 29

Outcome & Costs

slide-30
SLIDE 30

Outcome & Costs (1/8)

Local clearance of material:

  • Concrete blocks

230 t

  • Wall filling material

190 t

  • 60Co detected in 22 out of ~500

packages

  • Induced activity content was below

the clearance level for all packages

Decommissioning of MAX-lab / Outcome & Costs

slide-31
SLIDE 31

Outcome & Costs (2/8)

Clearance measurements of concrete bulk shielding and room surfaces:

  • ~400 m2 measured (75% of which in

the injector and MAX I areas)

  • An area constituting the floor of the

injection/extraction straight in MAX I and roof in the injector was found to have induced activity content well above the clearance level (up to x 8)

  • Concrete sampling during the

characterization phase included this area of MAX I – however, the clearance measurements revealed sharp gradients

Decommissioning of MAX-lab / Outcome & Costs

slide-32
SLIDE 32

Outcome & Costs (3/8)

Removal of room surfaces above the clearance level:

  • ~40 m2 of floor (including margin) and

supporting concrete beams had to be removed and reconstructed

Decommissioning of MAX-lab / Outcome & Costs

slide-33
SLIDE 33

Outcome & Costs (4/8)

Clearance of the building:

  • The application for clearance of the

building, along with the project reports, was submitted to the authority in October 2016

  • The decision (positive) was received in

mid December 2016 – one year to the day after shutdown of the facility

  • Removal of the stored concrete could

begin (~1700 t)

Decommissioning of MAX-lab / Outcome & Costs

slide-34
SLIDE 34

Outcome & Costs (5/8)

Decommissioning of MAX-lab / Outcome & Costs

slide-35
SLIDE 35

Outcome & Costs (6/8)

Decommissioning of MAX-lab / Outcome & Costs

slide-36
SLIDE 36

Outcome & Costs (7/8)

Outcome of material shipped to contractor:

(preliminary figures)

  • Low Risk

108 t

  • Risk

45 t

  • Low Level Waste

47 t

  • In total ~70 t to be melted
  • A few of the ingots from the melting will

have to be stored for decay, ≤ 2 years

  • Yet a few will have to be sent to final

repository

Decommissioning of MAX-lab / Outcome & Costs

Measured activity in ~ 50 t , of which 23 t were above the clearance level.

slide-37
SLIDE 37

Outcome & Costs (8/8)

Radiological costs:

(preliminary figures)

  • Total cost Phase 1:

~110 k€ ~650 h

  • Total cost Phase 2:

~1130 k€ ~6600 h

– Dismantling & measurements ~250 k€ ~3600 h – Management & administration ~400 k€ ~3000 h – Measurements (at contractor) ~170 k€ – Material management/treatment ~270 k€ – Other costs (e.g. shipping) ~40 k€

Prices per kg for material shipped to contractor (based on contract):

  • Clearance measurements

– Low Risk 0.40 €/kg, minimum 190 €/package – Risk 1.90 €/kg, minimum 930 €/package

  • Waste treatment

– Melting 3.80 €/kg

Decommissioning of MAX-lab / Outcome & Costs

slide-38
SLIDE 38

Decommissioning of MAX-lab

Decommissioning of MAX-lab / The End

Thank you for your attention!