Nuclear Decommissioning Citizens Advisory Panel (NDCAP) September - - PowerPoint PPT Presentation

nuclear decommissioning
SMART_READER_LITE
LIVE PREVIEW

Nuclear Decommissioning Citizens Advisory Panel (NDCAP) September - - PowerPoint PPT Presentation

Nuclear Decommissioning Citizens Advisory Panel (NDCAP) September 27, 2018 Introductions Corey Daniels Decommissioning Director Entergy Nuclear Vermont Yankee 1 Decommissioning Project Status 2 VY Decommissioning Update Dry Fuel


slide-1
SLIDE 1

Nuclear Decommissioning Citizens Advisory Panel (NDCAP)

September 27, 2018

slide-2
SLIDE 2

Introductions

1

Corey Daniels Decommissioning Director Entergy Nuclear Vermont Yankee

slide-3
SLIDE 3

Decommissioning Project Status

2

slide-4
SLIDE 4

1

VY Decommissioning Update

  • Dry Fuel Storage Project

– Dry Fuel Loading

  • The Dry Fuel Storage Loading campaign was completed on August 1st with

a total of 58 casks stored on the ISFSI pads.

  • The project was ahead of the original schedule and on budget.
  • ISFSI Protected Area Activated

– The new ISFSI Protected Area (PA) is staffed and was declared

  • perational on August 23rd.

– All NRC approvals have been received by the site and changes to the Physical Security Plan implemented.

  • NRC Inspection Activities

– The next planned NRC inspections are scheduled for the week of October 1st.

3

slide-5
SLIDE 5

1

VY Decommissioning Update (Cont’d)

4

ISFSI

slide-6
SLIDE 6

1

VY Decommissioning Update (Cont’d)

5

Completed Security Barrier & Final Cask Placed on ISFSI Pad

slide-7
SLIDE 7

1

VY Decommissioning Update (Cont’d)

  • Water Management Update

– A total of 825,000 gallons have been shipped to date.

  • Next shipment is scheduled for 10/2/18

– Water Disposition Program

  • Reduction of groundwater entering the turbine building.
  • Current rate of ~400 - 600 GPD.

– Groundwater is being safely shipped to EnergySolutions licensed disposal site in Tennessee.

  • Employee Information

– Employee out-processing is currently scheduled for October 31st as we transition to the ISFSI Organization.

6

slide-8
SLIDE 8

Proposed VY Sale and Accelerated Decommissioning

7

slide-9
SLIDE 9

1

Public Utility Commission Proceeding Update

  • Recent Completed Milestones

– VPUC issued a Procedural Order postponing its decision until after the NRC issues a ruling – July 6 – Joint Petitioners provided a copy of the status report submitted to the NRC Commissioners – August 13 – All other filings are before the VPUC

  • Upcoming Key Milestones

– VPUC Decision on CPG - TBD

8

slide-10
SLIDE 10

Nuclear Decommissioning Trust Update

9

slide-11
SLIDE 11

1

NRC License Transfer Application Update

  • License Transfer Application (LTA) filed with NRC – Feb. 9, 2017
  • Entergy and NorthStar filed a joint status report with the NRC

Commissioners on August 13, 2018 per their Memorandum and Order dated April 12, 2018

  • Completion of NRC review and decision on LTA expected later

this year.

10

slide-12
SLIDE 12

1

Nuclear Decommissioning Trust Update

  • The ENVY Nuclear Decommissioning Trust (NDT) balance was

$527.9 Million on August 31, 2018

  • The NDT balance was $581.5 Million on December 31, 2017

– Summary of NDT Performance in 2018:

  • Beginning Balance (1/1/18) - $581.5M
  • $32.6M in Qualified Withdrawals
  • $22M in Positive Market Adjustments
  • $43M in Fund Expenses
  • The Site Restoration Trust balance was $33.5 Million
  • n August 31, 2018.

– Entergy has funded a total of $25M; $8.5M fund growth.

11

slide-13
SLIDE 13

www.vydecommissioning.com