DAQ Design Workshop Dave Newbold, Georgia Karagiorgi 30-Oct-17 - - PowerPoint PPT Presentation
DAQ Design Workshop Dave Newbold, Georgia Karagiorgi 30-Oct-17 - - PowerPoint PPT Presentation
DAQ Design Workshop Dave Newbold, Georgia Karagiorgi 30-Oct-17 Welcome! Especially to those who travelled a long way at short notice Even so, please keep your talks to time! My thanks to our host Georgia, who has organised
Welcome!
- Especially to those who travelled a long way at short notice
- Even so, please keep your talks to time!
- My thanks to our host Georgia, who has organised everything
- Goals of this workshop:
- Identify the physics requirements on the FD (SP + DP) DAQ
- Identify pre-existing technical constraints on the DAQ design
- Learn about existing technical solutions from other experiments
- Narrow down to a few possible architectures as candidates for TP
- Agree a ‘decision matrix’ which will examine the merits of each
- What we need to achieve
- Everything should be on the table here, but by ~Jan need baseline decision
- From now on, work should be on one or more concrete DAQ designs
- Meaning, we also need the tools to undertake that design process
- Our Technical Proposal draft is needed by ~March (to be confirmed today…)
2
(Straw man) Schedule
3
DUNE FD DAQ Design, prototyping, review Baseline design M1: TP M2: Design review M3: TDR Prototype slice construction 6.6m Prototype slice test 6.5m M4: EDR passed M5: Prod review passed FE construction Pre-production 6.6m SURF slice test 3.2m Det #1 Tendering 3.25m Det #1 Procurement 3.3m Det #1 test, ship 1.36 years Det #1 Installation 1.9 years M6: Det #1 rdy for comm Det #2 Tendering 3.3m Det #2 Procurement 3.25m Det #2 test, ship 1.36 years Det #2 Installation 1.9 years M7: Det #2 rdy for comm BE construction Comms procurement 3.3m Comms installation 3.3m Det #1 tendering 3.3m Det #1 procurement 6.45m Det #1 installation 6.6m Det #2 tendering 3.3m Det #2 procurement 6.55m Det #2 installation 6.55m Commissioning Commission det #1 1.09 years Commission det #2 1.09 years External events Beneficial occ. of underground Fill #1 starts Fill #2 starts Start of physics #1 Start of physics #2 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 20
CAVEAT EMPTOR: the details are definitely wrong in many respects
Some Motherhood Thoughts
- We need a flexible, scalable system
- We really don’t know how requirements or detector performance will be
- We need to able to add selection / filtering / event building capacity at any time
- Schedule is tight – need to ‘design for construction’
- Meaning: modular and partionable system, designed for self test
- Meaning: avoid schedule interaction with other FD components
- A single system should serve SP + DP + ???
- Though the interfaces may be quite different at the front end
- Good ideas are great, proven and deployed good ideas are even better
- We will have only ~1 year to demonstrate and document everything for the TDR
- Need to respect resource constraints
- Unless some good news, this is a $10M system for det. #1, #2
- We need to identify and agree off-site bandwidth and datasets
- Reminder: 100Gb/s is 0.5PB/year
4