CUTOFF WALL CONSTRUCTION TECHNIQUES By Louay M. Owaidat Great - - PowerPoint PPT Presentation

cutoff wall construction techniques
SMART_READER_LITE
LIVE PREVIEW

CUTOFF WALL CONSTRUCTION TECHNIQUES By Louay M. Owaidat Great - - PowerPoint PPT Presentation

CUTOFF WALL CONSTRUCTION TECHNIQUES By Louay M. Owaidat Great Lakes Environmental & Infrastructure, LLC Levee State-of-the-Practice Symposium April 22, 2016 BACKGROUND Over 6,000 miles of levees in Sacramento During Floods If


slide-1
SLIDE 1

CUTOFF WALL CONSTRUCTION TECHNIQUES

By Louay M. Owaidat

Great Lakes Environmental & Infrastructure, LLC Levee State-of-the-Practice Symposium

April 22, 2016

slide-2
SLIDE 2

 Over 6,000 miles of levees in Sacramento  During Floods – If serious seepage develops, then boils may develop

and failure may occur

 Since 1990, the Corps, DWR SAFCA and other local agencies have

launched a levee strengthening program

BACKGROUND

slide-3
SLIDE 3

 1990 Test Section / 4 Methods  Sacramento Urban Area Program  Marysville / Yuba City Projects (Including Three Rivers Levee

Improvement Authority and Sutter Butte Flood Control Agency)

 American River Common Features  Natomas Levee Improvement Program  Marysville Ring Levee  West Sacramento  Pocket  Delta

SACRAMENTO AREA SLURRY WALL HISTORY – 1990 To Present

slide-4
SLIDE 4

REASON FOR THE LEVEE REPAIRS

slide-5
SLIDE 5

TO PREVENT THIS: LEVEE FAILURE

slide-6
SLIDE 6

TO PREVENT THIS: LEVEE FAILURE

slide-7
SLIDE 7

TO PREVENT THIS: LEVEE FAILURE

slide-8
SLIDE 8

TO PREVENT THIS: LEVEE FAILURE

slide-9
SLIDE 9

Cutoff Wall Construction Technologies

 Trench Re-mixing and Cutting Deep Wall Method (TRD)  Cutter Soil Mix Method (CSM)  Deep Soil Mix Method (DSM/DMM)  Conventional Excavation Method (CEM)  Long Stick Excavator  Clamshell Excavation Method

OVERVIEW

slide-10
SLIDE 10

Cutoff Wall Types and Quality Control

 Soil-Bentonite (SB)  Soil-Cement-Bentonite (SCB)  Cement-Bentonite (CB)  Self Hardening  Alternative Methods  Slag Cement-Bentonite  Soil-Attapulgite  Cement-Attapulgite  Other

OVERVIEW (CONTINUED)

slide-11
SLIDE 11

 Slurry trench excavation involving excavation utilizing conventional and

specialized long stick excavators

 Capable of excavation up to 95 feet  Deeper excavations performed utilizing clamshell buckets (over 95 feet)  Excavation performed under an engineered fluid (bentonite slurry) for

trench support

 Requires separate ex-situ backfilling mixing operation performed using

track dozers and small excavators

 Backfill is placed at lead-in trench or tremie placed and progressively

displaces trench slurry

CONVENTIONAL EXCAVATION OVERVIEW

slide-12
SLIDE 12

CONVENTIONAL EXCAVATION EQUIPMENT

slide-13
SLIDE 13

TYPES OF CUTOFF WALLS

 Cement-Bentonite  Others

 Soil-Bentonite  Soil-Cement-Bentonite

slide-14
SLIDE 14

 Constructed utilizing all cutoff wall construction technologies  Permeability of 1 x 10-6 cm/sec or less  Soil can be remixed (if clean and suitable) and used in

backfill material

 Approximately 20% spoil disposal required  No structural strength  Requires capping to support loading above the trench

SOIL-BENTONITE (SB)

slide-15
SLIDE 15

 Constructed utilizing all cutoff wall construction technologies  Permeability of 1 x 10-6 cm/sec or less  Soil can be remixed (if clean and suitable) and used in

backfill material

 Approximately 20% spoil disposal required  Provides minimal strength (30 – 300 psi)  Capping required for curing and protection of cutoff wall

SOIL-CEMENT-BENTONITE (SCB)

slide-16
SLIDE 16

 Constructed utilizing conventional excavation technology  Permeability of 1 x 10-6 cm/sec or less  Self hardening slurry; requires no separate backfilling

  • perations; suitable in areas with limited equipment access;

depth limitations

 100% trench spoil disposal required  Provides minimal strength (30 – 300 psi)  Capping required for curing and protection of cutoff wall

CEMENT-BENTONITE (CB)

slide-17
SLIDE 17

SLURRY CUTOFF WALLS

DEFINITION: SUBSURFACE WALLS THAT ACT AS BARRIERS TO LATERAL FLOW OF GROUNDWATER AND WATERBORNE CONTAMINANTS

slide-18
SLIDE 18

SLURRY TRENCHING TECHNIQUE

slide-19
SLIDE 19

SLURRY TRENCHING TECHNIQUE

slide-20
SLIDE 20

SLURRY TRENCHING TECHNIQUE

slide-21
SLIDE 21

SLURRY TRENCHING TECHNIQUE

slide-22
SLIDE 22

SLURRY TRENCHING TECHNIQUE

slide-23
SLIDE 23

SLURRY TRENCHING TECHNIQUE

slide-24
SLIDE 24

SLURRY TRENCHING TECHNIQUE

slide-25
SLIDE 25

HYDRAULIC BARRIERS SLURRY CUTOFF WALLS

slide-26
SLIDE 26
  • Soil-Bentonite
  • Soil-Cement-

Bentonite

  • Cement Bentonite
  • Composite walls
  • Plastic Concrete

HYDRAULIC BARRIERS SLURRY CUTOFF WALLS

slide-27
SLIDE 27

CASE STUDY

Cement/Slag Cement Bentonite Cutoff Wall

slide-28
SLIDE 28

American River Common Features Project Sites L8 and R8

slide-29
SLIDE 29

BATCH PLANT / STAGING AREA

slide-30
SLIDE 30

BATCH PLANT / STAGING AREA

slide-31
SLIDE 31

 28 DAY HYDRAULIC CONDUCTIVITY OF 1X10-6 cm/s  28 DAY UNCONFINED COMPRESSIVE STRENGTH OF

50 – 300 PSI

 LEVEE RESTORATION - AFTER15 PSI WAS ACHIEVED  10 DIFFERENT MIX DESIGNS WERE EVALUATED

CB SLURRY MIX DESIGN

slide-32
SLIDE 32

SLURRY BATCHING OPERATION

BENTONITE SLURRY SLAG CEMENT PORTLAND CEMENT POLYMAX CB MIXING TANK

slide-33
SLIDE 33

SITE L8 – BATCHING OPERATION

slide-34
SLIDE 34

CEMENT BENTONITE CUTOFF WALL PANEL CONSTRUCTION

slide-35
SLIDE 35
slide-36
SLIDE 36
slide-37
SLIDE 37
slide-38
SLIDE 38
slide-39
SLIDE 39

 OVER 5,500 MAN HOURS WITH ZERO LOSS TIME

ACCIDENTS

 CB WALL EXCEEDED SPECIFICATION REQUIREMENTS  PROJECT COMPLETED ON TIME  PROJECT COMPLETED UNDER BUDGET

CONCLUSION

slide-40
SLIDE 40

 US ARMY CORPS OF ENGINEERS – SACRAMENTO

DISTRICT

 HDR  SACRAMENTO AREA FLOOD CONTROL AGENCY

(SAFCA)

 DEPARTMENT OF WATER RESOURCES (DWR)  ASCE – SACRAMENTO SECTION

ACKNOWLEDGEMENTS

slide-41
SLIDE 41

 The trench remixing and deep wall (TRD) method is a

process for excavation and in situ mixing.

 The TRD method has been widely employed in Japan  Utilizes a large revolving chain and cutter bar, which is

lowered down to design depth of the cutoff wall and then moved in horizontal direction

 TRD equipment simultaneously excavates and mixes in situ

soils and added slurry resulting in a continuous soil mixed wall.

TRD OVERVIEW

slide-42
SLIDE 42

 TRD wall installation can consist of two steps

 Pre-trenching using bentonite slurry to stabilize the trench  Wall production by adding cement grout to the soil-bentonite mixture

in the pre-trenched zone.

 TRD equipment, in general, requires a very high

maintenance cost due to the need for frequent repair of cutter

TRD OVERVIEW (CONTINUED)

slide-43
SLIDE 43

TRD METHOD

slide-44
SLIDE 44

TRD EQUIPMENT

slide-45
SLIDE 45

 Cutter soil mixing (CSM) provides for the construction of

retaining and cut-off walls by mixing soil in-situ with a cement/bentonite grout

 The CSM wall consists of adjacent primary and secondary

panels

 The CSM wall is constructed using equipment derived from

diaphragm wall cutter technology

 Consists of cutting and mixing drums mounted on compact

hydraulic motors

 The positioning and verticality of the wall is achieved using

a kelly bar

CSM OVERVIEW

slide-46
SLIDE 46

CSM METHOD

slide-47
SLIDE 47

CSM EQUIPMENT

slide-48
SLIDE 48

 Deep Soil Mix Method (DSM/DMM) has been utilized in

United States since 1986

 Process involves in-situ mixing utilizing multiple augers

(3 to 6)

 Depth capabilities in excess of 200 feet  Applications include excavation support, under seepage

cutoff, liquefaction mitigation and other ground improvement

DSM/DMM OVERVIEW

slide-49
SLIDE 49

DSM/DMM METHOD

slide-50
SLIDE 50

DSM/DMM METHOD

slide-51
SLIDE 51

DSM/DMM METHOD

slide-52
SLIDE 52

DSM/DMM METHOD

slide-53
SLIDE 53

DSM/DMM EQUIPMENT

slide-54
SLIDE 54

CASE HISTORY

CALPERS Headquarters Expansion 3rd and Q Streets Sacramento, CA

slide-55
SLIDE 55

 12 miles of slurry walls (3.6 million sf)  Maximum depth to 80 feet  Permeability Requirements: 5 x 10-7 cm/sec  Strength Requirement: 30 psi  Residential and commercial areas

SACRAMENTO, CA

slide-56
SLIDE 56

CALPERS HEADQUARTERS SITE PLAN

NUMBER AND DIMENSIONS DEPENDENT ON SPOILS MANAGEMENT

Q STREET R STREET 3RD STREET

5TH STREET

N

Min 50' - 0" (Typ)

EXISTING ALLEY 4TH STREET

A A

50' MIN. C L

CUTOFF WALL

2% MAX 1/20

SECTION A - A WORKING PLATFORM (TYP)

1 1

9'

40' 50' 20'

SOIL-CEMENT WALL SOIL-CEMENT WALL

BATCH PLANT #2

N

BATCH PLANT #1

WORKING PLATFORM

SPOILS COLLECTION AREA (TYP.)

40' Min 9' - 0"(Typ)

CUTOFF WALL INSTALLATION STARTING POINT PRE-DRILLING STARTING POINT

MATERIAL DELIVERIES ACCESS ROUTE

slide-57
SLIDE 57

CASE HISTORY

slide-58
SLIDE 58

CASE HISTORY

slide-59
SLIDE 59

CASE HISTORY

slide-60
SLIDE 60

CASE HISTORY

slide-61
SLIDE 61

CDSM BATCH PLANT

slide-62
SLIDE 62

SLURRY PREPARATION

slide-63
SLIDE 63

SLURRY PREPARATION

slide-64
SLIDE 64

DSM CORE SAMPLES

slide-65
SLIDE 65

TEST SPECIMENS PREPARED FROM CORE SAMPLES

slide-66
SLIDE 66

CDSM PANEL

slide-67
SLIDE 67
slide-68
SLIDE 68

SINGLE PASS TRENCHING METHOD

slide-69
SLIDE 69

SINGLE PASS TRENCHING METHOD

slide-70
SLIDE 70

SHEET PILE WALLS

slide-71
SLIDE 71

Focused Applications: Temporary Excavation Support/Seepage Control

For Environmental Applications

Permanent Seepage Barrier For Environmental

Applications

Used In Conjunction With Other Systems:

 Jet Grouted Bottom Seal  Rock Grout Curtains  Funnel And Gate Treatment Systems

SHEET PILE WALLS

slide-72
SLIDE 72

 Conventional Hot and Cold rolled sections with interlock

sealants

 WaterlooTM Barrier  HDPE and Vinyl Sheets

SHEET PILE WALLS SYSTEMS

slide-73
SLIDE 73

BELLE WV

slide-74
SLIDE 74

DISCUSSION POINTS

slide-75
SLIDE 75

 Design Intent  Applicable Construction Method/Site Condition  Risk Analysis/Cost  Uniform Specifications  Lessons Learned  Experience/Qualifications  Permits  Water  Community Involvement

DISCUSSION POINTS