Phase I Site Plan Master Site Plan New Gymnasium Building Renovated Multi-Purpose Project Schedule
CREIGHTON SCHOOL DISTRICT Phase I Site Plan Master Site Plan New - - PowerPoint PPT Presentation
CREIGHTON SCHOOL DISTRICT Phase I Site Plan Master Site Plan New Gymnasium Building Renovated Multi-Purpose Project Schedule BILTMORE PREPARATORY ACADEMY Outdoor Lab __ Maker Space New Existing Ballfield Existing Campus New Parking &
Phase I Site Plan Master Site Plan New Gymnasium Building Renovated Multi-Purpose Project Schedule
Outdoor Lab __ Maker Space
New Gymnasium Existing Ballfield Existing Campus New Parking & Separated Drop-Off Lane
fire lane
85
Drop off
courts
Biltmore Preparatory Academy Initial Phase I Site Layout
New Multi-Use Pathway to Campbell
Outdoor Lab __ Maker Space
New Gymnasium Covered Walkway Remodeled Fab Lab Middle School Neighborhood Existing Campus
courts
Outdoor Lab __ Maker Space
Phase I Gymnasium New Ballfield New 2-Story PreK-8 Campus New Parking & Extended Drop-Off Lane
fire lane
100+ 85
Drop off
courts
New Soccer
Biltmore Preparatory Academy Master Plan Site Layout
New Multi-Use Pathway to Campbell
New Student Drop_Off Entry
retention
patio
85 40
courts Gymnasium Fab Lab Middle School Fire lane Media Center Existing Fields Drop Off Area Existing Play
Creighton School District
Biltmore Prep Academy Design Development
GYMNASIUM
Creighton School District
Creighton School Design Development
BILTMORE SCHOOL
Creighton School District
Biltmore Prep Academy Design Development
Gymnasium
Renovated Multi_Purpose
Classroom Maker Space Storage Classroom Classroom Classroom Storage Expandable Restrooms Mudroom Learning Lab Learning Lab Social Porch W a l k w a y Outdoor Lab Windows Windows Resource Hub FR To Gymnasium To Courts To Exist. Campus
Outdoor Lab __ Maker Space Building Section
Supply Storage Suspended Baffles New Clerestory Windows Portable Furniture Overhead Power Reels Learning Lab
Creighton School District
Biltmore Prep Academy Design Development
BILTMORE SCHOOL
Creighton School District
Biltmore Prep Academy Design Development
BILTMORE SCHOOL
Creighton School District
Biltmore Prep Academy Design Development
BILTMORE SCHOOL
Outdoor Lab __ Maker Space Building Section
Covered Walkway Learning Lab Resource Hub Learning Lab Social Porch Clerestory Windows
Creighton School District
Biltmore Prep Academy Design Development
BILTMORE SCHOOL
Resource Hub
Middle School __ Covered Social Porch Resource Hub
Resource Hub
Social Porch
Middle School __ Covered Social Porch
Screen wall (Perforated Metal Deck) Wrap around existing Portable Classrooms
➢ Start Construction Fall 2018 ➢ Complete Construction Aug 2019 ➢ Demo Parking Lot June 2019 ➢ Begin Remodel May 2019 Biltmore Prep Academy