crane cove park building 49 contract no 2814
play

Crane Cove Park Building 49 Contract No. 2814 April 9, 2019 1 - PowerPoint PPT Presentation

Crane Cove Park Building 49 Contract No. 2814 April 9, 2019 1 AGENDA 1. General Information Andre Antonio 2. Project Overview Erica Petersen 3. CMD Finbarr Jewell 4. OLSE Anna Liu 5. OEWD Joyce Wong 6. Environmental


  1. Crane Cove Park Building 49 Contract No. 2814 April 9, 2019 1

  2. AGENDA 1. General Information – Andre Antonio 2. Project Overview – Erica Petersen 3. CMD – Finbarr Jewell 4. OLSE– Anna Liu 5. OEWD – Joyce Wong 6. Environmental – Soko Made 7. Bid Documents – Andre Antonio 8. Questions

  3. • See Section 00 21 13 – 1.14 Submission and Opening of Bids • Two separately sealed envelopes • Envelope #1 • TITLE: Bid for Crane Cove Park – Building 49 (Port of SF Contract No. 2814) • Envelope #2 • TITLE: Bidder’s Qualifications for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)

  4. Envelope #1 Bid for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)

  5. Envelope #2 Bidder’s Qualifications for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)

  6. Presented by: Erica Petersen erica.petersen@sfport.com CRANE COVE PARK BUILDING 49 AREA OF WORK LOCATION MAP

  7. Project Overview Crane Cove Park – Crane Cove P rk – 2814 Building 49 2814 Building 49 • Cold shell rehabilitation with restrooms • New roof • Structural Steel work • Foundation with Piles and Concrete Grade Beams • Restrooms • Fire Protection • Asphalt paving • Building is approx. 7,700 sf • Engineer’s Estimate is $3.8 million

  8. • Project Coordination (Section 01 31 13) Crane Cove Park is an active construction site occupied by other Port Contractors per Section o 01 31 13. 2812 Park Improvements and 19 th St Parking Lot – Gordon N. Ball o Need to coordinate regularly and final electrical connection for Park (see next o slide) 2813 19 th St Roadway Improvements (future contract, not bordering this project) o Nearby Projects: o SFMTA Mission Bay Loop on Illinois St o SFPUC Bay Corridor Transmission and Distribution Project (BCTD) o Renovation of Historic Core Buildings 101 and 104 along 20th Street by Orton o Construction. • Risk Management Plan - Native Soil contains contaminants, see reference in Section 00 31 00, which includes an asbestos dust mitigation plan (See 01 11 00). • Hazmat Abatement already performed , but if your work disturbs a painted surface, need to perform spot lead abatement. • Utility connections under Illinois St.

  9. • Bid Submission April 30, 2019 at 10:30AM • Bid Opening May 14, 2019 at 10:30AM • Award of Contract June 11, 2019 • NTP, Construction Start July 2019 • Construction Duration 300 Consecutive Calendar Days after NTP • Substantial Completion May 2020 • Final Completion July 2020

  10. Example on Sheet A-01-01, Architectural Floor Plan:

  11. Presented By: Finbarr Jewell finbarr.jewell@sfgov.org Local Business Enterprise (LBE) • Subcontracting Goal = 23.0% 11.6% MBE 2.6% WBE 8.8% OBE Good Faith Efforts Exception, LBE = 31.0% • Refer to Section 00 22 11 for details. •

  12. Presented by: Anna Liu anna.liu@sfgov.org

  13. Presented by: Joyce Wong joyce.s.wong@sfgov.org Required per San Francisco Administrative Code Section 6.22(g) and Chapter 82 • See Section 00 73 30 for details • Applies to both Prime Contractor and ALL Subcontractors • Local Hire Requirement 30% by trade • At least 50% of Apprentice project work hours within each trade shall be • performed by local residents.

  14. Presented by: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements • See Section 01 74 50 for details • Minimum Diversion Rate of 75% Required • Source ‐ separated C&D debris material must be taken to a facility that reuses and/or recycles that material • MIXED C&D debris material must be taken to a REGISTERED FACILITY by a REGISTERED TRANSPORTER • Diversion Reporting – Use Form C for initial, monthly, and final reports • Weight Tags are required for monthly reporting • Contractor MUST include materials from ALL Subcontractors in reports • City Representative is responsible for reviewing, signing, and approving all reports submitted by the Contractor.

  15. 4/5/19 QBD  Addendum 1

  16. Ensuing Site Visit at Crane Cove Park (701 Illinois St.) Hard Hat, Vests, & Boots Required (Addendum 01)

  17. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend