Crane Cove Park Building 49 Contract No. 2814

April 9, 2019

1

slide-2
SLIDE 2
slide-3
SLIDE 3

AGENDA

  • 1. General Information – Andre Antonio
  • 2. Project Overview – Erica Petersen
  • 3. CMD – Finbarr Jewell
  • 4. OLSE– Anna Liu
  • 5. OEWD – Joyce Wong
  • 6. Environmental – Soko Made
  • 7. Bid Documents – Andre Antonio
  • 8. Questions
slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7
slide-8
SLIDE 8
  • See Section 00 21 13 – 1.14 Submission and Opening of Bids
  • Two separately sealed envelopes
  • Envelope #1
  • TITLE: Bid for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)
  • Envelope #2
  • TITLE: Bidder’s Qualifications for Crane Cove Park – Building 49 (Port of SF

Contract No. 2814)

slide-9
SLIDE 9

Envelope #1 Bid for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)

slide-10
SLIDE 10

Envelope #2 Bidder’s Qualifications for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)

slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

AREA OF WORK LOCATION MAP Presented by: Erica Petersen erica.petersen@sfport.com

CRANE COVE PARK BUILDING 49

slide-14
SLIDE 14

Crane Cove P Crane Cove Park – rk – 2814 Building 49 2814 Building 49

  • Cold shell rehabilitation with

restrooms

  • New roof
  • Structural Steel work
  • Foundation with Piles

and Concrete Grade Beams

  • Restrooms
  • Fire Protection
  • Asphalt paving
  • Building is approx. 7,700 sf
  • Engineer’s Estimate is $3.8

million

Project Overview

slide-15
SLIDE 15
  • Project Coordination (Section 01 31 13)
  • Crane Cove Park is an active construction site occupied by other Port Contractors per Section

01 31 13.

  • 2812 Park Improvements and 19th St Parking Lot – Gordon N. Ball
  • Need to coordinate regularly and final electrical connection for Park (see next

slide)

  • 2813 19th St Roadway Improvements (future contract, not bordering this project)
  • Nearby Projects:
  • SFMTA Mission Bay Loop on Illinois St
  • SFPUC Bay Corridor Transmission and Distribution Project (BCTD)
  • Renovation of Historic Core Buildings 101 and 104 along 20th Street by Orton

Construction.

  • Risk Management Plan - Native Soil contains contaminants, see reference in Section 00 31 00,

which includes an asbestos dust mitigation plan (See 01 11 00).

  • Hazmat Abatement already performed, but if your work disturbs a painted surface, need to

perform spot lead abatement.

  • Utility connections under Illinois St.
slide-16
SLIDE 16
slide-17
SLIDE 17
  • Bid Submission

April 30, 2019 at 10:30AM

  • Bid Opening

May 14, 2019 at 10:30AM

  • Award of Contract

June 11, 2019

  • NTP, Construction Start

July 2019

  • Construction Duration

300 Consecutive Calendar Days after NTP

  • Substantial Completion

May 2020

  • Final Completion

July 2020

slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21

Example on Sheet A-01-01, Architectural Floor Plan:

slide-22
SLIDE 22

Presented By: Finbarr Jewell finbarr.jewell@sfgov.org

  • Local Business Enterprise (LBE)

Subcontracting Goal = 23.0% 11.6% MBE 2.6% WBE 8.8% OBE

  • Good Faith Efforts Exception, LBE = 31.0%
  • Refer to Section 00 22 11 for details.
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26

Presented by: Anna Liu anna.liu@sfgov.org

slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29
slide-30
SLIDE 30

Presented by: Joyce Wong joyce.s.wong@sfgov.org

  • Required per San Francisco Administrative Code Section 6.22(g) and Chapter 82
  • See Section 00 73 30 for details
  • Applies to both Prime Contractor and ALL Subcontractors
  • Local Hire Requirement 30% by trade
  • At least 50% of Apprentice project work hours within each trade shall be

performed by local residents.

slide-31
SLIDE 31

Presented by: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements

  • See Section 01 74 50 for details
  • Minimum Diversion Rate of 75% Required
  • Source‐separated C&D debris material must be taken to a facility that reuses

and/or recycles that material

  • MIXED C&D debris material must be taken to a REGISTERED FACILITY by a

REGISTERED TRANSPORTER

  • Diversion Reporting – Use Form C for initial, monthly, and final reports
  • Weight Tags are required for monthly reporting
  • Contractor MUST include materials from ALL Subcontractors in reports
  • City Representative is responsible for reviewing, signing, and approving all

reports submitted by the Contractor.

slide-32
SLIDE 32

QBD  Addendum

1 4/5/19

slide-33
SLIDE 33

Ensuing Site Visit at Crane Cove Park (701 Illinois St.) Hard Hat, Vests, & Boots Required (Addendum 01)

slide-34
SLIDE 34

Questions?