Crane Cove Park Building 49 Contract No. 2814 April 9, 2019 1 AGENDA 1. General Information Andre Antonio 2. Project Overview Erica Petersen 3. CMD Finbarr Jewell 4. OLSE Anna Liu 5. OEWD Joyce Wong 6. Environmental
SLIDE 2
SLIDE 3
AGENDA
- 1. General Information – Andre Antonio
- 2. Project Overview – Erica Petersen
- 3. CMD – Finbarr Jewell
- 4. OLSE– Anna Liu
- 5. OEWD – Joyce Wong
- 6. Environmental – Soko Made
- 7. Bid Documents – Andre Antonio
- 8. Questions
SLIDE 4
SLIDE 5
SLIDE 6
SLIDE 7
SLIDE 8
- See Section 00 21 13 – 1.14 Submission and Opening of Bids
- Two separately sealed envelopes
- Envelope #1
- TITLE: Bid for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)
- Envelope #2
- TITLE: Bidder’s Qualifications for Crane Cove Park – Building 49 (Port of SF
Contract No. 2814)
SLIDE 9
Envelope #1 Bid for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)
SLIDE 10
Envelope #2 Bidder’s Qualifications for Crane Cove Park – Building 49 (Port of SF Contract No. 2814)
SLIDE 11
SLIDE 12
SLIDE 13
AREA OF WORK LOCATION MAP Presented by: Erica Petersen erica.petersen@sfport.com
CRANE COVE PARK BUILDING 49
SLIDE 14
Crane Cove P Crane Cove Park – rk – 2814 Building 49 2814 Building 49
- Cold shell rehabilitation with
restrooms
- New roof
- Structural Steel work
- Foundation with Piles
and Concrete Grade Beams
- Restrooms
- Fire Protection
- Asphalt paving
- Building is approx. 7,700 sf
- Engineer’s Estimate is $3.8
million
Project Overview
SLIDE 15
- Project Coordination (Section 01 31 13)
- Crane Cove Park is an active construction site occupied by other Port Contractors per Section
01 31 13.
- 2812 Park Improvements and 19th St Parking Lot – Gordon N. Ball
- Need to coordinate regularly and final electrical connection for Park (see next
slide)
- 2813 19th St Roadway Improvements (future contract, not bordering this project)
- Nearby Projects:
- SFMTA Mission Bay Loop on Illinois St
- SFPUC Bay Corridor Transmission and Distribution Project (BCTD)
- Renovation of Historic Core Buildings 101 and 104 along 20th Street by Orton
Construction.
- Risk Management Plan - Native Soil contains contaminants, see reference in Section 00 31 00,
which includes an asbestos dust mitigation plan (See 01 11 00).
- Hazmat Abatement already performed, but if your work disturbs a painted surface, need to
perform spot lead abatement.
- Utility connections under Illinois St.
SLIDE 16
SLIDE 17
- Bid Submission
April 30, 2019 at 10:30AM
- Bid Opening
May 14, 2019 at 10:30AM
- Award of Contract
June 11, 2019
- NTP, Construction Start
July 2019
- Construction Duration
300 Consecutive Calendar Days after NTP
- Substantial Completion
May 2020
- Final Completion
July 2020
SLIDE 18
SLIDE 19
SLIDE 20
SLIDE 21
Example on Sheet A-01-01, Architectural Floor Plan:
SLIDE 22
Presented By: Finbarr Jewell finbarr.jewell@sfgov.org
- Local Business Enterprise (LBE)
Subcontracting Goal = 23.0% 11.6% MBE 2.6% WBE 8.8% OBE
- Good Faith Efforts Exception, LBE = 31.0%
- Refer to Section 00 22 11 for details.
SLIDE 23
SLIDE 24
SLIDE 25
SLIDE 26
Presented by: Anna Liu anna.liu@sfgov.org
SLIDE 27
SLIDE 28
SLIDE 29
SLIDE 30
Presented by: Joyce Wong joyce.s.wong@sfgov.org
- Required per San Francisco Administrative Code Section 6.22(g) and Chapter 82
- See Section 00 73 30 for details
- Applies to both Prime Contractor and ALL Subcontractors
- Local Hire Requirement 30% by trade
- At least 50% of Apprentice project work hours within each trade shall be
performed by local residents.
SLIDE 31
Presented by: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements
- See Section 01 74 50 for details
- Minimum Diversion Rate of 75% Required
- Source‐separated C&D debris material must be taken to a facility that reuses
and/or recycles that material
- MIXED C&D debris material must be taken to a REGISTERED FACILITY by a
REGISTERED TRANSPORTER
- Diversion Reporting – Use Form C for initial, monthly, and final reports
- Weight Tags are required for monthly reporting
- Contractor MUST include materials from ALL Subcontractors in reports
- City Representative is responsible for reviewing, signing, and approving all
reports submitted by the Contractor.
SLIDE 32
QBD Addendum
1 4/5/19
SLIDE 33
Ensuing Site Visit at Crane Cove Park (701 Illinois St.) Hard Hat, Vests, & Boots Required (Addendum 01)
SLIDE 34