COUNTY ADMINISTRATION and OPERATIONS REPORT 1 AGENDA Review - - PowerPoint PPT Presentation
COUNTY ADMINISTRATION and OPERATIONS REPORT 1 AGENDA Review - - PowerPoint PPT Presentation
COUNTY ADMINISTRATION and OPERATIONS REPORT 1 AGENDA Review background and process Review master plan options & recommendations for County Admin & Ops Review estimates of probable cost Update on Criminal Justice
- Review background and process
- Review master plan options &
recommendations for County Admin & Ops
- Review estimates of probable cost
- Update on Criminal Justice recommendations
AGENDA
2
BACKGROUND & PROCESS
BACKGROUND & PROCESS
County Stakeholder Engagement
- Surveys-All Departments
- Interviews-All Departments
- Facilities Tours and Assessments
- Visioning sessions: CJ and Admin/Ops
- Review and validation of Space Needs Program
- Alternatives Development Workshops: 2 ea. for CJ and Admin/Ops
- Advisory Committee review of In Progress Documents
Project Team
- Criminal Justice team
- Admin/Ops team
- Assessment team
3
FACILITY LOCATIONS
Midpoint Campus Downtown Campus Vine Street Blue Spruce
4
FACILITY LOCATIONS
Justice Center 200 W. Oak St.
B
Facilities Assessments Summary
All Buildings in Good Condition except:
- Horsetooth Facilities - Excellent Condition
- 2255 Midpoint (Comm. Corr.) & Detention Ctr - Poor to
Fair Condition
- Blue Spruce Buildings - Poor to Fair Condition
- Vine Street – Poor Condition
- Loveland – 6th Street deficiencies being addressed in
new LCLC
ADMIN & OPS BACKGROUND
ADMIN/OPS BACKGROUND Administration/County Services/Ops Background
- County population is growing at a greater rate than other parts of Colorado (as of
2014, it was the 6th fastest growing county in the state)
- Larimer County facilities are in a range of conditions. Older, owned and leased
facilities are in poorer condition
- Most facilities have little or no growth space available
- Some County functions have significant current deficits (Fleet, Weeds)
- Some functions have become widely dispersed over time due to lack of contiguous
space (Human Services)
5
FINDINGS SUMMARY
FINDINGS SUMMARY
6
Key Findings
- The current Vine Street facility and site is not large enough to accommodate the
recommended program for a new Road & Bridge/Fleet building and site storage
- Functions currently housed in 200 West Oak Street will outgrow their building within 10
years even with efforts to increase efficiencies in the building. Relocating “Internal Service” functions frees up sufficient space to meet 20 year requirements for all other functions
- Human Service functions are currently in 4 buildings and 2 campuses in Fort Collins.
Consolidation is important for operational efficiency and improving service delivery. There is no space for growth today in existing facilities which also drives the need to consider new or expanded facilities
- A more robust, year-round Emergency Operations Center (EOC) is needed and would ideally
be accommodated close to the Sheriff’s Office
ADMIN & OPS PROJECTIONS
GAP ANALYSIS Gap Analysis
- 200 West Oak occupants will outgrow the
building by 42,900 NSF (approx. 30%) in 20 years
- Occupants of the Blue Spruce buildings
will require almost 50% more space than is available in 20 years
- Fleet/R&B facilities will need to add
~45,000 NSF in the next five years to meet 20-year requirements
- Occupants of owned and leased space at
Midpoint will be short over 32,000 NSF in 20 years (39%)
7
SF Definitions
- Current and projected space needs are measured as Net
Square Footage (NSF) which = all occupied space except core/shaft space, mechanical space, and the depth of the exterior walls
- Cost estimates for interior remodel is also based on NSF. New
construction is estimated based on total building gross SF (GSF)
GAP: 45,125
SPACE NEEDS OVERVIEW
*Excluding Most CJ Functions, Solid Waste Facilities
Including Probation, AIIM office, Coroner space
SPACE NEEDS
8
Current NSF 413,240* Current Rightsized Req'd NSF 98,110 24% growth Addt'l NSF Req'd at 5 Yrs 19,790 4% growth Addt'l NSF Req'd by 20 Yrs 80,850 15% growth Total New NSF Required 611,990 48% growth Current Seats 1,207 Addt'l Seats Req'd at 5 Yrs 82 Addt'l Seats Req'd at 20 Yrs 405 Total New Seats Required 1,694 40% growth (Historic County Trend @ 20 Yrs) 1,751 45% growth
ADMIN & OPS PROJECTIONS
ADMIN & OPS PROJECTIONS
9
Most of the “rightsizing” is needed for Ops functions in the short term. By 20 Yrs the percent of total growth is more evenly split between Ops and Admin.
20-YEAR GOAL
PROPOSED 20-YEAR END GAME
INTERNAL SERVICES VINE STREET REDEVELOPMENT AT BLUE SPRUCE- NO OTHER FUNCTIONS AT BLUE SPRUCE- W/HLTH, HS, EXTENSION AT NEW LOCATION W/HLTH, HS, EXT REUSE EXTG. BLDGS NEW BLDG.
HEALTH & HUMAN SERVICES (& EXT) AT BLUE SPRUCE- W/INTERNAL SERVICES AT BLUE SPRUCE- NO OTHER FUNCTIONS AT NEW LOCATION W/INTERNAL SVCS AT NEW LOCATION
10 Internal Services: Finance, IT, Facilities, Elections from Midpoint, Human Resources
20-YEAR GOAL
PROPOSED 20-YEAR END GAME
OAK STREET "SERVICE CTR" "RIGHT SIZE" STDS, CAPTURE SF FOR 10 YRS AT 20 YRS MOVE WORKFORCECTR TO NEW STAND- ALONE OR SHARED LOCATION BY 10 YRS RELOCATE INTERNAL SVCS TO NEW BUILDING MIDPOINTFOR CJ FUNCTIONS RELOCATE PUB WKS & FAC. SHOP
- RELEASE 2643
LEASE BY 5 YRS BACKFILL2601 WITH HUM SVC GROWTH. MAINTAIN 2573 UNTIL HS BLDG IS BUILT CONTINUE LEASING 2619 UNTIL INT. SVCS
- BLDG. IS BUILT
(assume Prospect is kept) RELOCATE 2601 HS FUNCTIONS TO LOVELAND MOVE SOME HS FROM 2555 TO 2601 TO FREE UP GROWTH SPACE FOR PROBATION VACATE2601 LEASE VACATE2619 LEASE
11
20-YEAR GOAL
PROPOSED 20-YEAR END GAME
12
FLEET (R&B,WEEDS,FAC) VACATE VINE STREET & MOVE TO NEW SITE (Include Facilities Shop) REDEVELOP VINE ST FOR INTERNAL SERVICES SELL PROPERTY UPGRADE, EXPAND SATELLITES
OAK STREET OCCUPANCY
OAK STREET
CURRENT OCCUPANCY
13
5,000 10,000 15,000 20,000 25,000 Bsmt Flr 1 Flr 2 Flr 3 Flr 4 Flr 5
IT Vet Svcs Workforce Center C&R Engineering
IT
Econ Community Dev. Assessor Cty Mgr/BOCC Elections Finance Facilities IT Vacant HR Treasurer EM C&R Assessor
OAK STREET OCCUPANCY
OAK STREET
20 YR OCCUPANCY (INTERNAL SVCS IN NEW BLDG.
14
- 5,000
5,000 10,000 15,000 20,000 25,000 Bsmt Flr 1 Flr 2 Flr 3 Flr 4 Flr 5
IT Vet Svcs Workforce Center C&R Elections IT Econ Dev Community Dev. Cty Mgr/BOCC Treasurer C&R Assessor Assessor Engineering C&R Engin. Comm Dev. Space Deficit Space Deficit
At 20 years:
- Reduce Bldg.
Common
- Capture lobby
space
- Move Workforce
Ctr.
MIDPOINT CAMPUS OCCUPANCY
MIDPOINT CAMPUS
2555: Probation – grow in place AIIM – no growth Human Svcs – partially relocate to 2601 Elections – no change Facilities – relocate to new R&B facility 2573: Human Services – no change 2601: Wellness Clinic – no change Human Services – additional seats relocated from 2555 2619: Clerk & Recorder – no change 2643: DISCONTINUE LEASE Road & Bridge – relocate to new facility 2555: Probation – grow in place AIIM – no growth Human Svcs, Elections –relocate to new facility Wellness Clinic, EOC – move in 2573: DISCONTINUE LEASE Human Services – relocate to new facility 2601: DISCONTINUE LEASE Wellness Clinic – relocate to 2555 Human Services – relocate to new facility 2619: DISCONTINUE LEASE Clerk & Recorder – relocate to new facility 2643: VACATED
5 YEARS
15
10-15 YEARS
2555 2573 2601 2619 2643
BLUE SPRUCE CAMPUS OCCUPANCY
BLUE SPRUCE CAMPUS
16
At 20 years:
- 5 Yr Occupancy: All of Human Services
consolidated in a new building and Public Health & Environment in remodeled existing location
- Extension moves to The Ranch
- Demolish 2nd existing building
- At 10 Years, potentially build new Internal
Services Building (assumes a 3 story bldg.)
- At 20 Years the site is at full capacity
2555 MIDPOINT OCCUPANCY
PROBATION & AIIM DIRECTIONS
LONG TERM OCCUPANCY
17
VINE STREET CAPACITY
VINE STREET CAPACITY
18
Note: A new location for Fleet (with R&B/Weeds/Facilities Shop requires 30 acres 92 SPACES USING EXISTING CURB CUTS (72 Required) 17,900 GSF (INTERNAL SERVICES)
At 20 years:
- Existing building can be demolished
anytime after new Fleet/R&B facility is constructed
- At 10 Years, potentially build new
Internal Services Building (assumes a 4 story bldg.)
- Substantial growth space available
PROPOSED PRELIMINARY TIMELINE
TIMELINE
LEGEND: New Construction Remodel Health & Human Svcs Criminal Justice Expansion Construction Relocations/Vacate Oak St/Svc Center Internal Services Backfill Public Works Vacate or Sell
19 *includes Comm. Corrections and Alt. Sentencing
VINE STREET RANCH
EXTEN- SION
JAIL COMPLEX JUSTICE CENTER MIDPOINT
1/2 OF 2601 HS MOVES TO LVLND HS GROWTH & SOME 2555 FUNCTIONS BACKFILLS 2601 PROB BACKFILLS 2555 HS SPACE
FAC SHOP & R&B GO TO NEW OPS SITE
VACATE 2643 MIDPOINT LEASE VACATE ALL OF HS SPACE
REMODEL & BACKFILL 2555 FOR PROB., EOC
VACATE 2601 & 2573 LEASE
ELEC. MOVES to IS BLDG - VACATE 2619 LEASE
BLUE SPRUCE
EXTEN- SION TO RANCH HS/HLTH BACKFILLS
REMODEL 1501 FOR FUTURE HS OR SELL SITE
OAK STREET
RELOCATE WRKFRC CTR?
NEW LOCATIONS
Note: Fleet Satellites are currently already in planning and design phases. The planning and design for a new facility for the Coroner's Office/Lab is also underway.
0-5 YRS 5-10 YRS 10-15 YRS 15-20 YRS
VACATE/SELL VINE REDEVELOP VINE INTERNAL SVCS BLDG FIT OUT SHELL SPACE PH I EXPANSION & REMODEL PH II JAIL EXPANSION (DEMO EXTG) FIT OUT SHELL SPACE NEW HHS BLDG INTERNAL SVCS BLDG PH I EXPANSION & REMODEL TARGETED REMODEL RECONFIG/ REMODEL FOR SVC. CTR NEW ROAD & BRIDGE/FLEET BLDG NEW HHS BLDG INTERNAL SVCS BLDG
OPT 1 OPT 2 OPT 1 OPT 2 OPT 1 OPT 2 OPT 3
PRELIMINARY COST IMPLICATIONS
COST IMPLICATIONS
20
Facility Expansion/Improvement 5 Yr 10 Yr 15 Yr 20 Yr Total Remodel/Reconfigure 200 W. Oak for Yrs 1-10, Relocate Internal Svcs at Yr.10 4,707,000 $ 2,789,000 $ 2,142,000 $
- $
9,638,000 $ Construct New HHS Building at Blue Spruce at Yr. 5, with some Core/Shell Build Out at Yr. 10 41,207,000 $ 7,163,000 $
- $
- $
48,370,000 $ Construct New Internal Svcs Building at Blue Spruce or at Vine Street at Yr. 10
- $
28,865,000 $
- $
- $
28,865,000 $ Continue use of 1525 Blue Spruce, Demolish 1501 at Yr.10 9,746,100 $ 168,000 $ 361,000 $
- $
10,275,100 $ Remodel 2555 Midpoint for Probation, AIIM and a new EOC to backfill space vacated by Human Svcs. 1,649,000 $ 6,412,000 $ 1,594,000 $
- $
9,655,000 $ Construct New Road & Bridge/Fleet Facility at location TBD at Yr. 5 59,940,000 $
- $
- $
- $
59,940,000 $ Expand R&B Satellite Locations across the County 23,325,000 $
- $
- $
- $
23,325,000 $ Construct New Recycled Materials Building and upgrade remaining facilities at Landfill 9,813,000 $ 96,000 $ 14,000 $
- $
9,923,000 $ Implement Component Replacement upgrades at The Ranch 2,689,000 $ 63,000 $
- $
- $
2,752,000 $ Implement Component Replacement upgrades at Horsetooth Reservoir 95,000 $ 38,000 $ 51,000 $
- $
184,000 $ TOTAL 153,171,100 $ 45,594,000 $ 4,162,000 $
- $
202,927,100 $ NOTE: All existing facilities that remain occupied have component replacement costs shown as needed in each time period
Costs include total project construction costs and component replacement costs, but exclude specialized equipment, site development and site acquisition Escalation is 6% annually for Yrs 0-5, and 3% annually for all remaining timeframes
QUESTIONS
KEY DECISION POINTS
- Should Internal Services and Human Services be co-located to
keep County sites to a minimum?
- If so, is it preferable to use Blue Spruce site vs. acquire new
property?
- If not, does the County want to repurpose or dispose of Vine
Street property for use by Internal Services and other future uses?
- Should Workforce Center be moved sooner vs. later?
- Extension – recent developments recommend that this function
go to the Ranch
21
CJ FINDINGS UPDATE
CJ FINDINGS UPDATE
Jail – Revised Phasing
22
Phase I
Continued Use of Existing Bed Units, partial construction of new Support Space, (10) new housing pods (vs. 12 as previously proposed)
CJ FINDINGS UPDATE
CJ FINDINGS UPDATE
Jail – Revised Phasing
23
Phase II
Final Build-out of 20 year requirements with (3) pods constructed as core/shell at 15 years & fit out as needed
Phase 1 Phase 2
CJ FINDINGS UPDATE
CJ FINDINGS UPDATE
Justice Center
24
Fifth Floor Third-Fourth Floor Second Floor First Floor Basement
CJ FINDINGS UPDATE
CJ FINDINGS UPDATE
Other CJ Functions
- Decisions to be made regarding future of Community Corrections and Alternative Sentencing
- programs. If operations continue status quo, expansion will be required. New construction
for Womens’ facilities allows expansion in accommodations for Men
- Communication Corrections currently requires County subsidy dollars to operate, and may
need to be reconsidered for budgetary reasons.
25
New Women’s Alt. Sentencing Expansion New Women’s Community Corrections
26
CJ FINDINGS UPDATE
Facility Expansion/Improvement 5 Yr 10 Yr 15 Yr 20 Yr Total Expansion of Justice Center to
- South. Core/Shell top floors
until needed. 106,728,000 $ 40,136,000 $ 2,759,000 $ 1,601,000 $ 151,224,000 $ Complete Phase I construction
- f jail expansion by Yr. 5.
Complete Phase II construction by Yr. 15, and demo existing bed
- units. Fit out final core/shell
units by Yr. 20 75,213,000 $ 5,825,000 $ 45,999,000 $ 23,483,000 $ 150,520,000 $ Expand and upgrade Sheriff's Office by Yr. 5 10,184,000 $ 4,473,000 $
- $
4,978,000 $ 19,635,000 $ Expand Community Corrections and Alt. Sentencing by Yr. 5 44,647,000 $ 9,105,000 $ 506,000 $ 9,319,000 $ 63,577,000 $ TOTAL 236,772,000 $ 59,539,000 $ 49,264,000 $ 39,381,000 $ 384,956,000 $ NOTE: All existing facilities that remain occupied have component replacement costs shown as needed in each time period
*
* Status of Community Corrections needs to be revisited
CJ FINDINGS UPDATE
Costs include total project construction costs and component replacement costs, but exclude specialized equipment, site development and site acquisition Escalation is 6% annually for Yrs 0-5, and 3% annually for all remaining timeframes
27
TOTAL COUNTY MP COST ESTIMATES
TOTAL COST
5 YR 10 YR 15 YR 20 YR TOTAL Total County Admin/Ops $153,171,100 $45,594,000 $4,162,000
- $202,927,100
Total Criminal Justice $236,772,000 $59,539,000 $49,264,000 $39,381,000 $384,956,000 TOTAL $389,943,100 $105,133,000 $53,426,000 $39,381,000 $587,883,100
Costs include total project construction costs and component replacement costs, but exclude specialized equipment, site development and site acquisition Escalation is 6% annually for Yrs 0-5, and 3% annually for all remaining timeframes