COUNCIL MEETING
January 31, 2019
- S. G. Nesbitt Memorial Arena & Community Centre
COUNCIL MEETING January 31, 2019 AGENDA TEAM INTRODUCTION 5m - - PowerPoint PPT Presentation
S. G. Nesbitt Memorial Arena & Community Centre COUNCIL MEETING January 31, 2019 AGENDA TEAM INTRODUCTION 5m BACKGROUND 15m ASSESSMENT 10m PROPOSED SOLUTION 10m TEAM INTRODUCTION WELCOME Team Introduction BACKGROUND Delivery Model
January 31, 2019
TEAM INTRODUCTION BACKGROUND ASSESSMENT PROPOSED SOLUTION
10m 10m 5m 15m
Design Bid Build Design Build IPD
CONTRACTOR
ARCHITECT OWNER
SUB - CONTRACTOR
ARCHITECT OWNER
GENERAL CONTRACTOR
ENGINEERS & CONSULTANTS
OWNER ARCHITECT
ENGINEERS & CONSULTANTS
SUB - CONTRACTOR GENERAL CONTRACTOR
1972 Construction start of arena 1972 Wood structure revised to steel alternative 1989 McEwen Report 1992 Expansion of Community Hall, Repairs to Arena 2010 AECOM structural report 2014 Greer Galloway structural report 2018 McIntosh Perry structural report
2014 Greer Galloway Report provided a cost estimate of $2.4M to retrofit the existing arena The analysis did not include areas that were inaccessible (including foundations) The IPD team had Mcintosh Perry review the existing conditions to assess the scope of work for structure re-use / expansion
load (code, new insulation)?
additional loads of the roof and walls (insulated)?
The IPD exposed the foundation to the footing and found:
primarily to limit frost damage)
and is deteriorated (not salvageable)
The IPD team’s structural engineer assessed the steel structure and determined:
existing steel
Two key options:
COST OF RE-USE: $905,000k 185’ rink COST OF NEW RIGID FRAME: $1,583,619 COST OF NEW ‘FRAMELESS’ $1,118,437
10 20 30 40 50 60 70 Roof Insulation R-Value Wall Insulation R-Value New Frameless Refurbish
Building envelope thermal efficiency: The higher the R-value, the greater the insulating effectiveness.
Community Hub Offices Change Areas Program Space
Washroom
extension of the existing rink life to 2035 (17 years remaining)
years (beyond 2060)
efficiency, Indoor Air Quality.
efficiency, Indoor Air Quality.
Source: Green Globes vs LEED by Arium, 08 29 2017, https://www.ariumae.com/green-globes-vs-leed/
performing structure
quality
life cycle
construction
events will be impacted for a few months to connect the new addition to the existing facility
Source: Inspection Report – SG Nesbitt, Minden, 2014 by Greer Galloway Consulting Engineers
Report does not address:
AODA compliant facilities 40 year durability Hockey Canada compliant rink Modern, efficient ice plant Improved ventilation Connect scout room to facility Improved security through office centralization Accessible drop off Safer parking areas Sprinklering existing (asset protection) Code improvements New Refurbish Accessible connection between 1st and 2nd floor Energy efficient building Certified sustainable design
ARENA + LOBBY: $8.64M RENOVATIONS: $0.4M ACTIVITY SPACE (GYM): $2.81M SITE + LANDSCAPE: $0.64M
Defer Gym
$3,520,000
$360,600
$880,800
defer to start in 2021
$4,909,000 (x 3.1%) = $152,100 $5,061,100
defer to start in 2020
$4,761,400 (x 3.1%) = $147,600 $4,909,000
$85,500 $23,000
sizes & amenities
for reduced footprint
$8,500
185’ rink in lieu of 200’ rink
$100,000
the building department shuts the facility down?
extend working life of the building, also notes the arena to be re-inspected in 5 years
restoration required within 5-8 years (Ie. 2019- 2022)
the costs?
moving past Validation?
energy efficiencies savings
costs, to be offset by annual increase contributions to reserves for future capital maintenance
keep current ice plant operational and safe for another one to two years?
EXISTING TO REMAIN EXISTING TO BE DEMOLISHED EXISTING TO BE RENOVATED
6 7 DROP-OFF ACCESS ROUTE 5 1 4 3 2 1 MAIN ENTRY & DROP OFF 2 ACCESSIBLE PARKING 3 PARKSIDE STREET 4 CONNECTION TO REDEVELOPMENT 5 HOUSING REDEVELOPMENT 6 PARKING LOT SECONDARY ENTRY
1 NEW RINK 2 2 ICE PLANT 3 RINK CHANGEROOMS 4 REF/FLEX CHANGEROOMS 5 CHANGEROOMS 6 UNIVERSAL WASHROOM 7 ACTIVITY SPACE 7 3 8 9 4 5
10
CONCESSION
11
WASHROOMS
12
SCOUT HALL ELEVATOR 9 ADMINISTRATION
11 12
1 5 8 COMMUNITY HUB
10
6 3 3 3 3 3
5 4 6 7 2 5 WALKING TRACK 6 INTERIOR LINK TO HALL & WARM VIEWING 7 COMMUNITY HALL ELEVATOR 1 NEW RINK 2 BLEACHERS 3 WASHROOMS 4 FITNESS ROOM 3 3 3 1
Building approach
Community Hub
Community Hub
Gymnasium / Walking track
Ice rink and seating
JAN 2019 APRIL 2019 AUGUST 2020