Corridor Projects

Troy Creasy – CSX Public Projects

slide-2
SLIDE 2

Presentation Overview

 Territory Overview  Crossings by the Numbers  Corridor Project Success

2

slide-3
SLIDE 3

Company Overview

3

  • CSXT operates in 23 States,

2 Canadian Provinces, and the District of Columbia

slide-4
SLIDE 4

4

Active Crossings

Signaled

Public - 10797 Private - 226

Non-Signaled Public - 4394

Private - 7043

slide-5
SLIDE 5

What is a Corridor project?

 A partnership between CSX and a State Highway Authority to improve crossing safety at each crossing within a targeted area.  Crossing safety improvements at each crossing are achieved via a combination of crossing closures, grade separations, warning system upgrades, and roadway geometry improvements.

5

slide-6
SLIDE 6

Fayetteville Traffic Separation Study (TSS)

 43 total crossings reviewed by NCDOT  9 crossings were closed  20 crossings had warning device system upgrades  2 crossing had roadway geometric improvements  CSX made a 15% contribution at the end of the project to expedite project delivery.  Project successfully delivered on 4/15/16

6

slide-7
SLIDE 7

Rankin Street Closure

7

slide-8
SLIDE 8

Greenville Traffic Separation Study (TSS)

 New wye to reduce switching downtown  1 new grade separation  Relocated rail yard from downtown to a new rail yard  4 closures  7 crossings had warning device system upgrades  The CSX contribution was 25%

8

slide-9
SLIDE 9

Conclusion