Conventional Facilities Status S Dixon PIP-II Management Meeting - - PowerPoint PPT Presentation
Conventional Facilities Status S Dixon PIP-II Management Meeting - - PowerPoint PPT Presentation
Conventional Facilities Status S Dixon PIP-II Management Meeting 02 September 2016 Thanks Alessandro Vivoli, Anindya Chakravarty, Anthony F Leveling, Arkadiy L Klebaner Beau F. Harrison, Curtis M. Baffes, David E Johnson, David W Peterson Don
Thanks
Alessandro Vivoli, Anindya Chakravarty, Anthony F Leveling, Arkadiy L Klebaner Beau F. Harrison, Curtis M. Baffes, David E Johnson, David W Peterson Don Cossairt, Donald V Mitchell, Emil Huedem, Fernanda G Garcia Jerry R Leibfritz, Jerzy Czajkowski, John E Anderson Jr, Luisella Lari Matthew Quinn, Maurice Ball, Paul Derwent, Ralph J Pasquinelli Ronald Jedziniak, Thomas W. Lackowski; Todd M Sullivan Valeri A Lebedev, William A Pellico
02SEP16
- S. Dixon | Conventional Facilities Status
2
Agenda
- Siting
- Enclosures/Buildings
- Cooling
- What’s Next
02SEP16
- S. Dixon | Conventional Facilities Status
3
Agenda
- Siting
- Enclosures/Buildings
- Cooling
- What’s Next
02SEP16
- S. Dixon | Conventional Facilities Status
4
Goal: Document the spatial and infrastructure requirements for the PIP-II conventional facilities to support CD-1.
Where We Started
02SEP16 5
- S. Dixon | Conventional Facilities Status
Key Plan
02SEP16 6
- S. Dixon | Conventional Facilities Status
Siting
02SEP16 7
- S. Dixon | Conventional Facilities Status
Updated wetlands from 2016 delineation (increase from 2010)
Siting – Future Expansion
02SEP16 8
- S. Dixon | Conventional Facilities Status
PIP-II Campus Plan
02SEP16 9
- S. Dixon | Conventional Facilities Status
Cryo Plant Utility Building Linac and Linac Gallery Transport Enclosure (with Beam Absorber)
Plan
02SEP16 10
- S. Dixon | Conventional Facilities Status
Ion Source HWR RFQ
Staging Area
Building Section at Front End
02SEP16 11
- S. Dixon | Conventional Facilities Status
Ion Source HWR RFQ Loading Dock Staging Area
Preliminary Shielding Considerations
02SEP16
- S. Dixon | Conventional Facilities Status
12
6’ 17.5’ 7.5’ 18.5’ 18.5’
(transport line and absorber)
Preliminary Shielding Depths shown below. Further analysis required, especially at the Booster.
Thanks to D. Cossairt, T. Leveling and M. Quinn
Used the 10W/m curve for the conceptual design
Typical Section – Linac Enclosure
02SEP16 13
- S. Dixon | Conventional Facilities Status
RF Zone Cryo Zone LCW Zone 1’-10” Aisle 1’-10” Aisle
Thanks to C. Baffes, J. Leibfritz, R. Pasquinelli and M. Ball
Plan at Linac Gallery (Coax)
02SEP16 14
- S. Dixon | Conventional Facilities Status
Only RF Amplifiers racks shown
SSR1 SSR2 SSR2 SSR2 SSR2 SSR2 SSR2 SSR2 SSR1
Section at Coax
02SEP16 15
- S. Dixon | Conventional Facilities Status
Coax at Top of Racks Arrangement Still Needs Shielding Analysis For Control and Power Cables
Plan at Linac Gallery (Waveguides)
02SEP16 16
- S. Dixon | Conventional Facilities Status
Staggered RF Amplifers
LB650 LB650 LB650 LB650 LB650 LB650 LB650 LB650 LB650 LB650 LB650 HB650 HB650
Only RF Amplifiers racks shown
Section at Waveguide
02SEP16 17
- S. Dixon | Conventional Facilities Status
Waveguides at Top of Racks Arrangement Still Needs Shielding Analysis For Control and Power Cables
Transport Line/Main Ring Crossing
02SEP16 18
- S. Dixon | Conventional Facilities Status
In Progress
Transport Line Connection at Booster
02SEP16 19
- S. Dixon | Conventional Facilities Status
In Progress
Cryo Plant
02SEP16 20
- S. Dixon | Conventional Facilities Status
Thanks to A. Klebaner and A. Chakravarty
Cryo Plant Cooling Requirements
- Water Requirements
– 1,200 – 1,500 gpm flow
- Pond System
– Chemical characteristics met by Pond system; – Solids content characteristics NOT met by Pond system; – No Pond - ~$500-$700k per acre;
- ICW System
– Chemical characteristics met by existing ICW system; – Solids content characteristics NOT met by ICW system; – Sampling ICW;
02SEP16
- S. Dixon | Conventional Facilities Status
21
Cryo Plant – Water Quality Requirements
02SEP16 22
- S. Dixon | Conventional Facilities Status
Thanks to A. Klebaner and A. Chakravarty
Cryo Plant – Water Quality Test Stand
02SEP16 23
- S. Dixon | Conventional Facilities Status
BZero Compressor Building
- Installed as part of the Mu2e Cryo
work for CDF;
- Installed test ports to sample the ICW
before and after the strainer;
- Includes a Adams strainer with
“standard” slot sizes (baseline);
- Two month rental of a Lakos strainer to
reduce the solids;
- Replacement filter elements in Adams
strainer with smaller slot size;
- Arranged for FESS/O water testing
service to increase the testing to include solids;
- Scheduled testing on same duration as
CUB;
- Compare strainer options with water
quality requirements.
Strainer
Port for Rental Strainer Port for Rental Strainer
PM vs. CW Considerations
- Driven by duty factor of the equipment
– 15% for Pulsed Mode – 100% for Continuous Wave Mode
- Common For Both Modes
– Physical arrangement of heat producing equipment; – Electrical power supply (not usage); – Conventional Facilities handles the heat load to air (HLA);
- Difference is Primarily Cooling
– 5.0 mw in pulsed mode; – 10.5 mw in continuous wave mode;
02SEP16
- S. Dixon | Conventional Facilities Status
24
PM vs. CW Considerations - Cooling
02SEP16
- S. Dixon | Conventional Facilities Status
25
Heat Loads Pulsed Mode (MW) Continuous Wave Mode (MW) Low Conductivity Water (LCW) 1.65 7.07 Cryoplant Cooling (Cryo) 3.4 3.4 Total (MW) 5.05 10.47
Industrial Cooling Water (ICW) Cooling Ponds (PW) Towers (close) Towers (open)
Pulsed Mode
MW to GPM Conversion 682.79 MW to Acres Conversion 800 kw/acre
LCW 1,125 gpm LCW 1.98acres LCW 1.0towers LCW 1.0towers Cryo 1,400 gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 2,525 gpm 6.06acres 3.00towers 2.00towers exclude standby exclude standby
CW Mode
MW to GPM Conversion 682.79 MW to Acres Conversion 800 kw/acre
LCW 4,827 gpm LCW 8.48acres LCW 4.0towers LCW 2.0towers Cryo 1,400 gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 6,227 gpm 12.56acres 6.00towers 3.00towers exclude standby exclude standby
Other Considerations Other Considerations Other Considerations Other Considerations Strainers, Drought Conditions Strainers, Heat Exchangers, Treatment Heat Exchangers, Treatment, Make Up Heat Exchangers, Treatment, Make Up Drought Conditions Building Costs Building Costs
Note: 1,400 gpm is the highest flow currently available from the existing ICW system
Thanks to E. Huedem
PM vs. CW Considerations - Cooling
02SEP16
- S. Dixon | Conventional Facilities Status
26
Heat Loads Pulsed Mode (MW) Continuous Wave Mode (MW) Low Conductivity Water (LCW) 1.65 7.07 Cryoplant Cooling (Cryo) 3.4 3.4 Total (MW) 5.05 10.47
Industrial Cooling Water (ICW) Cooling Ponds (PW) Towers (close) Towers (open)
Pulsed Mode
MW to GPM Conversion 682.79 MW to Acres Conversion 800kw/acre
LCW 1,125 gpm LCW 1.98acres LCW 1.0towers LCW 1.0towers Cryo 1,400 gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 2,525 gpm 6.06acres 3.00towers 2.00towers exclude standby exclude standby
CW Mode
MW to GPM Conversion 682.79 MW to Acres Conversion 800kw/acre
LCW 4,827 gpm LCW 8.48acres LCW 4.0towers LCW 2.0towers Cryo 1,400 gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 6,227 gpm 12.56acres 6.00towers 3.00towers exclude standby exclude standby
Other Considerations Other Considerations Other Considerations Other Considerations Strainers, Drought Conditions Strainers, Heat Exchangers, Treatment Heat Exchangers, Treatment, Make Up Heat Exchangers, Treatment, Make Up Drought Conditions Building Costs Building Costs
Note: 1,400 gpm is the highest flow currently available from the existing ICW system
Thanks to E. Huedem
Basis for Estimate
Cooling Design Approach
- Goal: Modular approach that allows for efficient operation in
both modes;
- Pulsed Mode
– Heat Load to Air (HLA): Utilize chilled water from existing CUB for equipment cooling (this utilizes the available headroom at CUB); – LCW: (1) Cooling tower – Cryo: (2) Cooling towers
- Continuous Wave Mode
– Heat Load to Air (HLA): Install a chilled water loop to supplement the pulsed mode system with (2) cooling towers; – LCW: Add (1) Cooling tower – Cryo: No change
02SEP16
- S. Dixon | Conventional Facilities Status
27
PIP-II Utility Building
02SEP16 28
- S. Dixon | Conventional Facilities Status
7 Towers: HLA: 0 in PM, 2 for CW LCW: 1 for PM, 2 for CW Cryo: 2 for both modes N+1 Standby: 1 Separate Piping Runs For PM and CW modes
What’s Next
- September/October
– Complete conceptual design for Main Ring Crossing; – Complete conceptual design for Booster Tower; – Develop conceptual design for High Voltage Electrical;
- October/November
– Life Safety Analysis with outside consultant; – Renderings of Surface Buildings;
- November – January/February
– Select a design firm for Detailed Design/Final Design;
- March-September 2017
– Update drawings; – Develop a detailed cost estimate;
02SEP16
- S. Dixon | Conventional Facilities Status
29
Questions
02SEP16
- S. Dixon | Conventional Facilities Status
30