conventional facilities status
play

Conventional Facilities Status S Dixon PIP-II Management Meeting - PowerPoint PPT Presentation

Conventional Facilities Status S Dixon PIP-II Management Meeting 02 September 2016 Thanks Alessandro Vivoli, Anindya Chakravarty, Anthony F Leveling, Arkadiy L Klebaner Beau F. Harrison, Curtis M. Baffes, David E Johnson, David W Peterson Don


  1. Conventional Facilities Status S Dixon PIP-II Management Meeting 02 September 2016

  2. Thanks Alessandro Vivoli, Anindya Chakravarty, Anthony F Leveling, Arkadiy L Klebaner Beau F. Harrison, Curtis M. Baffes, David E Johnson, David W Peterson Don Cossairt, Donald V Mitchell, Emil Huedem, Fernanda G Garcia Jerry R Leibfritz, Jerzy Czajkowski, John E Anderson Jr, Luisella Lari Matthew Quinn, Maurice Ball, Paul Derwent, Ralph J Pasquinelli Ronald Jedziniak, Thomas W. Lackowski; Todd M Sullivan Valeri A Lebedev, William A Pellico 2 S. Dixon | Conventional Facilities Status 02SEP16

  3. Agenda • Siting • Enclosures/Buildings • Cooling • What’s Next 3 S. Dixon | Conventional Facilities Status 02SEP16

  4. Agenda • Siting • Enclosures/Buildings • Cooling • What’s Next Goal: Document the spatial and infrastructure requirements for the PIP-II conventional facilities to support CD-1. 4 02SEP16 S. Dixon | Conventional Facilities Status

  5. Where We Started 5 S. Dixon | Conventional Facilities Status 02SEP16

  6. Key Plan 6 S. Dixon | Conventional Facilities Status 02SEP16

  7. Siting Updated wetlands from 2016 delineation (increase from 2010) 7 S. Dixon | Conventional Facilities Status 02SEP16

  8. Siting – Future Expansion 8 S. Dixon | Conventional Facilities Status 02SEP16

  9. PIP-II Campus Plan Transport Enclosure (with Beam Absorber) Linac and Linac Gallery Utility Building Cryo Plant 9 S. Dixon | Conventional Facilities Status 02SEP16

  10. Plan Staging Area RFQ Ion Source HWR 10 S. Dixon | Conventional Facilities Status 02SEP16

  11. Building Section at Front End Loading Dock HWR RFQ Ion Source Staging Area 11 S. Dixon | Conventional Facilities Status 02SEP16

  12. Preliminary Shielding Considerations Preliminary Shielding Depths shown below. Further analysis required, especially at the Booster. 7.5’ 6’ 18.5’ 17.5’ Used the 10W/m curve for the 18.5’ conceptual design (transport line and absorber) Thanks to D. Cossairt, T. Leveling and M. Quinn 12 S. Dixon | Conventional Facilities Status 02SEP16

  13. Typical Section – Linac Enclosure Cryo Zone 1’-10” Aisle 1’-10” LCW Zone Aisle RF Zone Thanks to C. Baffes, J. Leibfritz, R. Pasquinelli and M. Ball 13 S. Dixon | Conventional Facilities Status 02SEP16

  14. Plan at Linac Gallery (Coax) Only RF Amplifiers racks shown SSR1 SSR2 SSR2 SSR2 SSR2 SSR1 SSR2 SSR2 SSR2 14 S. Dixon | Conventional Facilities Status 02SEP16

  15. Section at Coax Coax at Top of Racks Arrangement Still Needs Shielding Analysis For Control and Power Cables 15 S. Dixon | Conventional Facilities Status 02SEP16

  16. Plan at Linac Gallery (Waveguides) Only RF Amplifiers racks shown Staggered RF Amplifers LB650 LB650 LB650 LB650 LB650 LB650 LB650 LB650 HB650 HB650 LB650 LB650 LB650 16 S. Dixon | Conventional Facilities Status 02SEP16

  17. Section at Waveguide Waveguides at Top of Racks Arrangement Still Needs Shielding Analysis For Control and Power Cables 17 S. Dixon | Conventional Facilities Status 02SEP16

  18. Transport Line/Main Ring Crossing In Progress 18 S. Dixon | Conventional Facilities Status 02SEP16

  19. Transport Line Connection at Booster In Progress 19 S. Dixon | Conventional Facilities Status 02SEP16

  20. Cryo Plant Thanks to A. Klebaner and A. Chakravarty 20 S. Dixon | Conventional Facilities Status 02SEP16

  21. Cryo Plant Cooling Requirements • Water Requirements – 1,200 – 1,500 gpm flow • Pond System – Chemical characteristics met by Pond system; – Solids content characteristics NOT met by Pond system; – No Pond - ~$500-$700k per acre; • ICW System – Chemical characteristics met by existing ICW system; – Solids content characteristics NOT met by ICW system; – Sampling ICW; 21 S. Dixon | Conventional Facilities Status 02SEP16

  22. Cryo Plant – Water Quality Requirements Thanks to A. Klebaner and A. Chakravarty 22 S. Dixon | Conventional Facilities Status 02SEP16

  23. Cryo Plant – Water Quality Test Stand • Installed as part of the Mu2e Cryo work for CDF; • Installed test ports to sample the ICW before and after the strainer; • Includes a Adams strainer with “standard” slot sizes (baseline); Port for Rental Strainer Port for Rental Strainer • Two month rental of a Lakos strainer to reduce the solids; • Replacement filter elements in Adams strainer with smaller slot size; • Arranged for FESS/O water testing Strainer service to increase the testing to include solids; • Scheduled testing on same duration as CUB; • Compare strainer options with water quality requirements. BZero Compressor Building 23 S. Dixon | Conventional Facilities Status 02SEP16

  24. PM vs. CW Considerations • Driven by duty factor of the equipment – 15% for Pulsed Mode – 100% for Continuous Wave Mode • Common For Both Modes – Physical arrangement of heat producing equipment; – Electrical power supply (not usage); – Conventional Facilities handles the heat load to air (HLA); • Difference is Primarily Cooling – 5.0 mw in pulsed mode; – 10.5 mw in continuous wave mode; 24 02SEP16 S. Dixon | Conventional Facilities Status

  25. PM vs. CW Considerations - Cooling Heat Loads Continuous Pulsed Mode Wave Mode (MW) (MW) 1.65 7.07 Low Conductivity Water (LCW) 3.4 3.4 Cryoplant Cooling (Cryo) Total (MW) 5.05 10.47 Industrial Cooling Water (ICW) Cooling Ponds (PW) Towers (close) Towers (open) MW to GPM Conversion 682.79 MW to Acres Conversion 800 kw/acre Pulsed Mode LCW 1,125 gpm LCW 1.98acres LCW 1.0towers LCW 1.0towers Cryo gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 1,400 2,525 gpm 6.06acres 3.00towers 2.00towers exclude standby exclude standby MW to GPM Conversion 682.79 MW to Acres Conversion 800 kw/acre CW Mode LCW 4,827 gpm LCW 8.48acres LCW 4.0towers LCW 2.0towers Cryo 1,400 gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 6,227 gpm 12.56acres 6.00towers 3.00towers exclude standby exclude standby Other Considerations Other Considerations Other Considerations Other Considerations Strainers, Drought Conditions Strainers, Heat Exchangers, Treatment Heat Exchangers, Treatment, Make Up Heat Exchangers, Treatment, Make Up Drought Conditions Building Costs Building Costs Note: 1,400 gpm is the highest flow currently available from the existing ICW system Thanks to E. Huedem 25 02SEP16 S. Dixon | Conventional Facilities Status

  26. PM vs. CW Considerations - Cooling Heat Loads Continuous Basis for Estimate Pulsed Mode Wave Mode (MW) (MW) 1.65 7.07 Low Conductivity Water (LCW) 3.4 3.4 Cryoplant Cooling (Cryo) Total (MW) 5.05 10.47 Industrial Cooling Water (ICW) Cooling Ponds (PW) Towers (close) Towers (open) MW to GPM Conversion 682.79 MW to Acres Conversion 800kw/acre Pulsed Mode LCW 1,125 gpm LCW 1.98acres LCW 1.0towers LCW 1.0towers Cryo gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 1,400 2,525 gpm 6.06acres 3.00towers 2.00towers exclude standby exclude standby MW to GPM Conversion 682.79 MW to Acres Conversion 800kw/acre CW Mode LCW 4,827 gpm LCW 8.48acres LCW 4.0towers LCW 2.0towers Cryo 1,400 gpm @17 Fdt Cryo 4.08acres Cryo 2.0towers Cryo 1.0towers 6,227 gpm 12.56acres 6.00towers 3.00towers exclude standby exclude standby Other Considerations Other Considerations Other Considerations Other Considerations Strainers, Drought Conditions Strainers, Heat Exchangers, Treatment Heat Exchangers, Treatment, Make Up Heat Exchangers, Treatment, Make Up Drought Conditions Building Costs Building Costs Note: 1,400 gpm is the highest flow currently available from the existing ICW system Thanks to E. Huedem 26 02SEP16 S. Dixon | Conventional Facilities Status

  27. Cooling Design Approach • Goal: Modular approach that allows for efficient operation in both modes; • Pulsed Mode – Heat Load to Air (HLA): Utilize chilled water from existing CUB for equipment cooling (this utilizes the available headroom at CUB); – LCW: (1) Cooling tower – Cryo: (2) Cooling towers • Continuous Wave Mode – Heat Load to Air (HLA): Install a chilled water loop to supplement the pulsed mode system with (2) cooling towers; – LCW: Add (1) Cooling tower – Cryo: No change 27 02SEP16 S. Dixon | Conventional Facilities Status

  28. PIP-II Utility Building 7 Towers: HLA: 0 in PM, 2 for CW Separate Piping Runs LCW: 1 for PM, 2 for CW For PM and CW modes Cryo: 2 for both modes N+1 Standby: 1 28 S. Dixon | Conventional Facilities Status 02SEP16

  29. What’s Next • September/October – Complete conceptual design for Main Ring Crossing; – Complete conceptual design for Booster Tower; – Develop conceptual design for High Voltage Electrical; • October/November – Life Safety Analysis with outside consultant; – Renderings of Surface Buildings; • November – January/February – Select a design firm for Detailed Design/Final Design; • March-September 2017 – Update drawings; – Develop a detailed cost estimate; 29 02SEP16 S. Dixon | Conventional Facilities Status

  30. Questions 30 02SEP16 S. Dixon | Conventional Facilities Status

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend