Hempstead UFSD Prospect School Reconstruction Construction Update December 13, 2018 Committed to Excellence Project Overview Project Areas: Red Area (1906) Fire/ Water / Smoke Blue Area (1916/1918) Smoke / Soot Green Area


  1. Hempstead UFSD Prospect School Reconstruction Construction Update December 13, 2018

  2. Committed to Excellence Project Overview Project Areas:  Red Area (1906) – Fire/ Water / Smoke  Blue Area (1916/1918) – Smoke / Soot  Green Area (2013) – Light Smoke

  3. Committed to Excellence 1906 Classroom Area • Ceilings, flooring, wall finishes removed • All content (tables/ chairs/ books) have been relocated from classrooms in preparation of reconstruction efforts • Computers, IPads, printers, smartboards located in wing have been deemed unsalvageable

  4. Committed to Excellence 1916/ 1918 Classroom Area • Ceilings, flooring have been removed per survey • All content (tables/ chairs/ books) have been relocated from classrooms in preparation of reconstruction efforts • Computers, IPads, printers, smartboards located in wing have been reviewed for function ability

  5. Committed to Excellence • Review of mechanical, electrical, plumbing and structural components have been completed by their respective engineers; Information is used as the basis of the scope of work for reconstruction • Field inventory of damaged content has been accomplished; Replacement pricing is being established for claim discussion;

  6. Committed to Excellence Review of Roof Rafters in Attic

  7. Committed to Excellence Survey of Electrical Service and Data Wiring

  8. Committed to Excellence Renu Contracting has retained the following firms as part of the reconstruction efforts: • Roland’s Electric, Inc • Maccarone Plumbing • Anron Air Systems • Cardinal Controls • A-Plus Technology • Nickerson Corporation

  9. Committed to Excellence • Engineering for the scaffolding to support the existing fire damaged roof is completed and installed. • Scaffolding has been set-up in front and rear of building in order to facilitate roof repairs.

  10. Committed to Excellence Damaged Section of Roof Removed and Replaced

  11. Committed to Excellence Damaged Section of Roof Removed and Replaced

  12. Committed to Excellence Damaged Section of Roof Removed and Replaced

  13. Committed to Excellence New Roof Shingles installed

  14. Committed to Excellence • Masonry repair to the brick walls where new load bearing columns are to be installed is complete. • After completion of removal and replacement of all the fire damaged roof and framing material, the attic area was painstakingly cleaned so that the attic can be spray sealed. • Spray and seal is a 3 part process that is applied to all remaining building components that were not removed in order to eliminate any and all lingering smoke odors. This is carefully and systematically applied throughout the building.

  15. Committed to Excellence Installation of 8ea Roof Supports

  16. Committed to Excellence Ductwork/ Mechanical Installation in Attic

  17. Committed to Excellence Ductwork/ Mechanical Installation in Attic

  18. Committed to Excellence Framing of Walls and Ceilings - Corridor

  19. Committed to Excellence Framing of Walls and Ceilings - Classrooms

  20. Committed to Excellence Installation of Sheet Rock Ceilings & Electrical Rough-in

  21. Committed to Excellence • Firestopping in hallways and classrooms as part of creating fire-rated corridors • Roland’s Electric installing thru-wall sleeves for new electrical wires to be installed for fire-rated wall penetrations

  22. Committed to Excellence Action for Month of December • Continue with new electrical rough-in to classrooms • Continue with sheetrock installation and new wall framing • Continue with firestopping of all through wall and floor penetration to achieve fire rating • Continue with installation of ductwork • Start-up of temp heat • Spray insulation of exterior walls

  23. Committed to Excellence Community Employment • Renu has retained the services of 2 community members to be assigned to the Prospect School Reconstruction project • Resumes of workers were received through Genesus Construction Training Center

  24. HEMPSTEAD UFSD Construction Update Questions? December 13, 2018 Board Meeting

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.