Construction Update December 13, 2018 Committed to Excellence - - PowerPoint PPT Presentation

construction update
SMART_READER_LITE
LIVE PREVIEW

Construction Update December 13, 2018 Committed to Excellence - - PowerPoint PPT Presentation

Hempstead UFSD Prospect School Reconstruction Construction Update December 13, 2018 Committed to Excellence Project Overview Project Areas: Red Area (1906) Fire/ Water / Smoke Blue Area (1916/1918) Smoke / Soot Green Area


slide-1
SLIDE 1

Hempstead UFSD Prospect School Reconstruction Construction Update

December 13, 2018

slide-2
SLIDE 2

Committed to Excellence Project Overview Project Areas:

  • Red Area (1906) –

Fire/ Water / Smoke

  • Blue Area (1916/1918)

– Smoke / Soot

  • Green Area (2013) –

Light Smoke

slide-3
SLIDE 3

1906 Classroom Area

  • Ceilings, flooring, wall

finishes removed

  • All content (tables/ chairs/

books) have been relocated from classrooms in preparation of reconstruction efforts

Committed to Excellence

  • Computers, IPads, printers, smartboards located

in wing have been deemed unsalvageable

slide-4
SLIDE 4

1916/ 1918 Classroom Area

  • Ceilings, flooring have been

removed per survey

  • All content (tables/ chairs/

books) have been relocated from classrooms in preparation of reconstruction efforts

Committed to Excellence

  • Computers, IPads, printers, smartboards located

in wing have been reviewed for function ability

slide-5
SLIDE 5
  • Review of mechanical, electrical, plumbing and

structural components have been completed by their respective engineers; Information is used as the basis of the scope of work for reconstruction

  • Field inventory of damaged content has been

accomplished; Replacement pricing is being established for claim discussion;

Committed to Excellence

slide-6
SLIDE 6

Committed to Excellence Review of Roof Rafters in Attic

slide-7
SLIDE 7

Committed to Excellence Survey of Electrical Service and Data Wiring

slide-8
SLIDE 8

Renu Contracting has retained the following firms as part of the reconstruction efforts:

  • Roland’s Electric, Inc
  • Maccarone Plumbing
  • Anron Air Systems
  • Cardinal Controls
  • A-Plus Technology
  • Nickerson Corporation

Committed to Excellence

slide-9
SLIDE 9
  • Engineering for the

scaffolding to support the existing fire damaged roof is completed and installed.

  • Scaffolding has been

set-up in front and rear of building in

  • rder to facilitate roof

repairs.

Committed to Excellence

slide-10
SLIDE 10

Committed to Excellence Damaged Section of Roof Removed and Replaced

slide-11
SLIDE 11

Committed to Excellence Damaged Section of Roof Removed and Replaced

slide-12
SLIDE 12

Committed to Excellence Damaged Section of Roof Removed and Replaced

slide-13
SLIDE 13

Committed to Excellence New Roof Shingles installed

slide-14
SLIDE 14
  • Masonry repair to the brick walls where new load

bearing columns are to be installed is complete.

  • After completion of removal and replacement of all

the fire damaged roof and framing material, the attic area was painstakingly cleaned so that the attic can be spray sealed.

  • Spray and seal is a 3 part process that is applied to

all remaining building components that were not removed in order to eliminate any and all lingering smoke odors. This is carefully and systematically applied throughout the building.

Committed to Excellence

slide-15
SLIDE 15

Committed to Excellence Installation of 8ea Roof Supports

slide-16
SLIDE 16

Committed to Excellence Ductwork/ Mechanical Installation in Attic

slide-17
SLIDE 17

Committed to Excellence Ductwork/ Mechanical Installation in Attic

slide-18
SLIDE 18

Committed to Excellence Framing of Walls and Ceilings - Corridor

slide-19
SLIDE 19

Committed to Excellence Framing of Walls and Ceilings - Classrooms

slide-20
SLIDE 20

Committed to Excellence Installation of Sheet Rock Ceilings & Electrical Rough-in

slide-21
SLIDE 21
  • Firestopping in

hallways and classrooms as part of creating fire-rated corridors

  • Roland’s Electric

installing thru-wall sleeves for new electrical wires to be installed for fire-rated wall penetrations

Committed to Excellence

slide-22
SLIDE 22
  • Continue with new electrical rough-in to

classrooms

  • Continue with sheetrock installation and new wall

framing

  • Continue with firestopping of all through wall and

floor penetration to achieve fire rating

  • Continue with installation of ductwork
  • Start-up of temp heat
  • Spray insulation of exterior walls

Committed to Excellence Action for Month of December

slide-23
SLIDE 23
  • Renu has retained the services of 2 community

members to be assigned to the Prospect School Reconstruction project

  • Resumes of workers were received through

Genesus Construction Training Center

Committed to Excellence Community Employment

slide-24
SLIDE 24

HEMPSTEAD UFSD Construction Update Questions?

December 13, 2018 Board Meeting