Construction PM St Bartholomews Hospital City of London 1.2 - - PowerPoint PPT Presentation

construction pm st bartholomew s hospital city of london
SMART_READER_LITE
LIVE PREVIEW

Construction PM St Bartholomews Hospital City of London 1.2 - - PowerPoint PPT Presentation

Construction PM St Bartholomews Hospital City of London 1.2 billion PFI given the go ahead January 2006 Complete re-development of Royal London & St Bartholomews hospitals Barts - 10 year programme over 3 Phases Start


slide-1
SLIDE 1

Construction PM St Bartholomew’s Hospital City of London

slide-2
SLIDE 2
slide-3
SLIDE 3

 £1.2 billion PFI given the go ahead January

2006

 Complete re-development of Royal London

& St Bartholomew’s hospitals

 Barts - 10 year programme over 3 Phases  Start Date 24/04/2006 – Finish date

29/02/2016

slide-4
SLIDE 4

 Trust picks up the costs for:

  • Buildings completely empty
  • Free from clinical contamination
  • Archaeology
  • Asbestos
  • Contaminated soil

Fixed contractual dates for Vacant Possession

Circa £900k per week delay costs

slide-5
SLIDE 5

 Radium Bore Hole  Buried Radium Benches

These were both located within the basement area of our Out-Patient Department, due to be demolished in Phase 3 - October 2014. The basement area housed our entire Medical Records department, some 7500 linear meters of records and approximately 25 staff.

slide-6
SLIDE 6
slide-7
SLIDE 7

In the mid 1980s an ex member of staff, who was in his late eighties, reported to our RPA that during the mid 1930s they had buried some Radium contaminated (benches/tables) in the basement area of the OPD. He provided a hand drawn sketch of the area where they were buried, unfortunately shortly after this he passed away. I was made aware of this issue in January 2003, three years prior to the PFI commencing.

slide-8
SLIDE 8

 March 2003 - GPR survey carried out in accessible

areas (corridors), 9 targets found.

 July 2005 - Aurora brought in to carry out intrusive

radiological survey, nothing found.

 January 2006 - PFI commenced, OPD building to be

demolished in 2014.

 March 2006 – 150 sqm of medical records storage

re-located to facilitate GPR and radiological survey. A number of areas were found to be contaminated with Radium-226.

 December 2006 – Contaminated areas cleared and

made safe. Benche ches s not found! und!!

slide-9
SLIDE 9

 November 2013 – Medical Records moved out

to allow archaeological dig and asbestos removal.

 February 2014 – GPR survey of remaining

basement floor, 9 targets found

 April 2014 – Aurora carry out intrusive

radiological survey, nothing found.

 June 2014 – Aurora & Zetica conducted a

desk top review.

slide-10
SLIDE 10

The contaminated benches never existed, it was the floor that had been contaminated then subsequently covered in concrete.

slide-11
SLIDE 11

 The OPD from ground floor up was clinically

fully operational

 We had approximately 30 archaeologists on

site carrying out a large scale excavation

 We were also conducting asbestos removal  Aurora’s method statement was designed in

conjunction with all of these parties

slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14

 September 2014 – Aurora removed all of the

contaminated flooring and made the area safe.

 October 4th 2014 – Phase 3 was handed over

to our construction contactor on time and clear of all contamination.

 10 years

rs & 10 months hs to complete ete

slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

 Record on your Risk Register  Involve your Environmental Officer as early as

possible

 Be open and honest with staff and contractors  Use a professionally qualified & experienced

company for advice, removal and disposal

 How can you record individuals knowledge

for future use?

slide-18
SLIDE 18