considerations March 2020 Pcoronavirus March 2020 Overview 2 - - PowerPoint PPT Presentation

considerations
SMART_READER_LITE
LIVE PREVIEW

considerations March 2020 Pcoronavirus March 2020 Overview 2 - - PowerPoint PPT Presentation

Coronavirus Contractual considerations March 2020 Pcoronavirus March 2020 Overview 2 Coronavirus March 2020 Overview If a business cannot comply with its contracts: What legal remedies might it have?: Force majeure


slide-1
SLIDE 1

Coronavirus – Contractual considerations

March 2020

slide-2
SLIDE 2

Pcoronavirus – March 2020

2

Overview

slide-3
SLIDE 3

Coronavirus – March 2020

  • If a business cannot comply with its contracts:
  • What legal remedies might it have?:
  • Force majeure clause
  • Doctrine of frustration
  • Try to negotiate a solution?
  • Some other practical considerations

3

Overview

slide-4
SLIDE 4

Pcoronavirus – March 2020

4

Force majeure clauses

slide-5
SLIDE 5

Coronavirus – March 2020

Wikipedia:

"a common clause in contracts that essentially frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties, such as a war, strike, riot, crime, plague, or an event described by the legal term act of God (hurricane, flood, earthquake, volcanic eruption, etc.), prevents one or both parties from fulfilling their

  • bligations under the contract"

NZ law: Force majeure does not have an independent, recognised meaning. It is vital to assess the specific wording

  • f the force majeure clause.

5

What is a Force majeure clause?

slide-6
SLIDE 6

Coronavirus – March 2020

  • Check your contract.
  • Courts will not imply a force majeure clause into a

contract.

  • If so, review and carefully analyse the exact wording of

the clause. (Also check the Governing Law clause in your contract).

6

Do I have a force majeure clause?

slide-7
SLIDE 7

Coronavirus – March 2020

  • Does the force majeure clause cover pandemics or

government orders?

  • Usually, but not always…
  • Sometimes there is a list of events which trigger

the rights under the force majeure clause.

  • Sometimes the clause refers to any “event beyond

the Parties’ reasonable control”.

  • Does the clause apply for both parties’ benefit?

7

Analyse the force majeure clause

slide-8
SLIDE 8

Coronavirus – March 2020

  • To rely on the clause you will need to prove the breach of

contract was caused by the pandemic / government

  • rder.
  • Has it become physically or legally impossible to perform

the contract because of the pandemic / government

  • rder? Or was the breach caused by other reasons?

Has it simply become uneconomic or inconvenient to perform the contract?

  • Are there reasonable steps that could have been taken to

mitigate or avoid the breach?

8

Was the breach caused by the pandemic / government

  • rder?
slide-9
SLIDE 9

Coronavirus – March 2020

  • To claim relief under the force majeure clause, what steps

need to be taken?

  • Written notice to the other party?
  • You are only excused from liability for that breach.

You still need to comply with the other obligations in the contract.

9

Analyse the force majeure clause – Need to given notice?

slide-10
SLIDE 10

Coronavirus – March 2020

  • Check the contract does have a force majeure clause and

that it applies to the circumstances at hand.

  • Request regular updates.

10

What if you receive a force majeure notice?

slide-11
SLIDE 11

Pcoronavirus – March 2020

11

Frustration

slide-12
SLIDE 12

Coronavirus – March 2020

  • If there is no force majeure clause, you might be able to

rely on the doctrine of frustration to bring the contract to an end.

  • Frustration is where, by no fault of either party, an

unforeseen intervening event makes performance of the contract impossible or radically different.

12

Frustration

slide-13
SLIDE 13

Pcoronavirus – March 2020

13

Negotiating changes

slide-14
SLIDE 14

Coronavirus – March 2020

  • Being in breach of a contract is not an ideal situation to

be in, but it is important to remain proactive and practical in finding a way out.

  • This may mean resorting to legal remedies or it may

mean trying to negotiate a solution.

  • A good understanding of your contractual rights might

give you leverage to negotiate solutions.

  • Be proactive and negotiate before you are in breach

(Especially for financing arrangements).

14

Negotiating changes

slide-15
SLIDE 15

Coronavirus – March 2020

  • During negotiations be mindful of:
  • important longer-term relationships;
  • the reality of the challenges that many businesses are

facing in the current environment (risk of insolvency?);

  • reputational risks.

15

Negotiating changes

slide-16
SLIDE 16

Coronavirus – March 2020

  • The solution might involve a variation to the contract or a

"waiver" of the breach.

  • Get these recorded in writing.
  • A variation agreement does not need to be signed in wet

ink: Under NZ law an electronic signature is considered just as valid as a written signature for almost all documents, and for almost all legal requirements.

16

Variation / Waiver

slide-17
SLIDE 17

Coronavirus – March 2020

17

p: +64 3 467 7184 m: +64 27 270 3907 e: sarah.simmers@al.nz

Partner, Commercial

Sarah Simmers

slide-18
SLIDE 18

Auckland Level 3 Australis Nathan Building 37 Galway Street, Britomart Auckland 1010 p: +64 9 338 8300 f: +64 9 337 1115 Christchurch Level 3 Anderson Lloyd House 70 Gloucester Street Christchurch 8013 p: +64 3 379 0037 f: +64 3 379 0039 Dunedin Level 10 Otago House 477 Moray Place Dunedin 9016 p: +64 3 477 3973 f: +64 3 477 3184 Queenstown Level 2 13 Camp Street Queenstown 9300 p: +64 3 450 0700 f: +64 3 450 0799

al.nz Auckland • Christchurch • Dunedin • Queenstown