SLIDE 1
Conservation, Site Enhancements, Re-siting Projects and current loans
February 23, 2018
1
Conservation, Site Enhancements, Re-siting Projects and current - - PowerPoint PPT Presentation
Conservation, Site Enhancements, Re-siting Projects and current loans February 23, 2018 1 Removal of Carlos Cruz-Diez, Double Physichromie for conservation Feb. 15-20, 2018 Install of Double Physichromie at new site scheduled for April 20 th 2
1
2
3
4
5
6
7
December 2017 Construction documents completed and RFP posted January 2018 RFP responses received and evaluated February 2018 Contract issued to Jerdon Enterprises March 1, 2018 Projects launch Spring-Summer 2018 Phased project completion with Carlos Cruz-Diez completed for April event October 2018 Substantial completion