Components in the Basic Model Presenters: Tess Thompson Virginia - - PowerPoint PPT Presentation

components in the basic model
SMART_READER_LITE
LIVE PREVIEW

Components in the Basic Model Presenters: Tess Thompson Virginia - - PowerPoint PPT Presentation

Wetbud Surface Water Components in the Basic Model Presenters: Tess Thompson Virginia Tech Zach Agioutantis University of Kentucky Special thanks to Dillon Conner with WSSI for the wetland graphics! Piedmont wetlands are the interface


slide-1
SLIDE 1

Wetbud Surface Water Components in the Basic Model

Presenters: Tess Thompson Virginia Tech Zach Agioutantis University of Kentucky

Special thanks to Dillon Conner with WSSI for the wetland graphics!

slide-2
SLIDE 2

Piedmont wetlands are the interface between uplands, groundwater, and surface water

slide-3
SLIDE 3

Water Inflows and Outflows

Inflows can be due to groundwater seepage, runoff from the surrounding hillslopes, or flood flows from adjacent streams.

slide-4
SLIDE 4

Surface water inflows can be runoff from the wetland watershed or overbank flows from an adjacent stream.

slide-5
SLIDE 5

Hillslope runoff is computed using the NRCS curve number equation.

Wetbud assumes all of the “precipitation excess” enters the wetland each day – there is no flow routing or hydrograph generation for inflows from the wetland watershed.

S P S P Q

a

8 . ) 2 . (

2

  

for P > Ia

where Q =actual runoff, aka “precipitation excess” (inches) P = actual rainfall (inches) S = potential maximum retention after runoff begins (inches); Ia = initial abstraction = interception plus infiltration during early parts of the storm plus surface depression storage = 0.2S (inches) CN = runoff curve number

10

  • CN

1000 = S

slide-6
SLIDE 6
slide-7
SLIDE 7

Overbank flows are determined using three steps:

  • 1. Compute a daily stream

Hydrograph (stream discharge versus time) using 24-hr precipitation excess and NRCS dimensionless unit hydrograph or import stream discharge as a time series file

  • 2. Calculate water depth in the stream each day and check to see if

the stream is high enough to overflow into the wetland

  • 3. Calculate amount of water that enters wetland from that 24-hr

storm event

slide-8
SLIDE 8

Overbank Step 1: Calculate stream flows

slide-9
SLIDE 9

Overbank Step 1: Calculate stream flows

slide-10
SLIDE 10

Overbank Step 1: Calculate stream flows

slide-11
SLIDE 11

Stream flows are calculated in Wetbud using the NRCS Dimensionless Unit Hydrograph (DUH)

slide-12
SLIDE 12

Overbank Step 1: Calculate stream watershed time to peak (Tp) and unit peak runoff (qp, 1 in./day) as part of the overall project

slide-13
SLIDE 13

Time to peak is the sum of the travel times as sheet flow, shallow concentrated flow, and concentrated channel flow

Compute flow velocities and divide flow length by the velocity.

slide-14
SLIDE 14

Pocahontas Example Wetland

Calculate Time to Peak for longest flow path

Shallow sheet flow Shallow concentrated flow Channel flow

slide-15
SLIDE 15

Overbank Step 1: Calculate stream flows

slide-16
SLIDE 16

Overbank Step 1: Multiply DUH by watershed Tp and qp resulting from 1 inch of precipitation excess, to determine the stream watershed unit hydrograph

Then, to develop a hydrograph for each day, multiple the unit hydrograph flow (resulting from 1 in. of precipitation excess) by the total precipitation excess for that day.

slide-17
SLIDE 17

Stream discharge unit hydrograph for Pocahontas example

This graph shows the response of the stream to 1 inch of surface runoff (“precipitation excess”) .

slide-18
SLIDE 18

Calculate precipitation excess for stream watershed

Wetbud assumes all of the “precipitation excess” enters the wetland each day – there is no flow routing or hydrograph generation for inflows from the wetland watershed.

S P S P Q

a

8 . ) 2 . (

2

  

for P > Ia

where Q =actual runoff, aka “precipitation excess” (inches) P = actual rainfall (inches) S = potential maximum retention after runoff begins (inches); Ia = initial abstraction = interception plus infiltration during early parts of the storm plus surface depression storage = 0.2S (inches) CN = runoff curve number

10

  • CN

1000 = S

slide-19
SLIDE 19

Overbank Step 1: Calculate stream flows for each day

* =

slide-20
SLIDE 20

Cautions with having Wetbud calculate stream flows!!

  • Only simulates one small watershed (< ?

acres)

  • Cannot have multiple sub-watersheds
  • Does not route flow
  • Does not simulate structures, such as ponds

For large, complex watersheds, compute continuous streamflow time series outside of Wetbud (e.g. HEC- RAS, SWMM, SWAT) and then import into Wetbud.

slide-21
SLIDE 21

Caution: The overbank flow routine includes

  • nly a single watershed and NO STRUCTURES

If the stream watershed is more than a few hundred acres or if there are significant structures in the watershed, use HEC-HMS or similar program and import stream discharge.

slide-22
SLIDE 22

This is the end of the Project-Level surface flow inputs (i.e. you can’t change these through your design).

The rest of the calculations are at the Scenario-Level (because they can be changed through wetland design).

slide-23
SLIDE 23

Overbank Step 2: Calculate water surface elevation in the stream

slide-24
SLIDE 24

Overbank Step 2: Calculate water surface elevation in the stream

slide-25
SLIDE 25

The stream overbank flow routine assumes there is an inflow weir or channel constructed in the wetland berm.

If there is no inflow structure, the entire berm can be modeled as a broad-crested weir.

slide-26
SLIDE 26
slide-27
SLIDE 27

Overbank Step 2: Calculate water surface elevation in the stream

q = flow (ft/s) n = roughness coefficient A = cross-sectional area (ft2) P = wetted perimeter (ft) S = hydraulic gradient (ft/ft)

𝑟 = 1.49 𝑜 𝐵 ൗ

5 3

𝑄 ൗ

2 3

𝑇 ൗ

1 2 Depth is included in A and P: knowing q, n, S and width, we can solve for depth.

slide-28
SLIDE 28

Overbank Step 2: Calculate water surface elevation in the stream

For stream restoration design, can change channel dimensions and roughness here.

slide-29
SLIDE 29

Overbank Step 2: Check to see if water in the stream is high enough to overflow into the wetland

slide-30
SLIDE 30

Overbank Step 2: Check to see if water in the stream is high enough to overflow into the wetland

Design inflow structure here

slide-31
SLIDE 31

Overbank Step 2: Check to see if water in the stream is high enough to overflow into the wetland

  • a. Calculate water

depth in stream

  • b. Add water depth

to stream bed elevation

  • c. Compare water

depth to inflow structure elevation

slide-32
SLIDE 32

Overbank Step 3: Calculate amount of water that enters wetland from that 24-hr storm event

slide-33
SLIDE 33

The depth of water above the inflow structure (hydraulic head, h) determines the inflow rate to calculate monthly overbank volume.

slide-34
SLIDE 34

In the Basic Model, water greater than the “weir depth” is lost from the wetland as

  • utflow each month.

Wetland bottom elevation Precipitation Groundwater In Runoff Overbank Evapotranspiration Groundwater Out Outflow Water in wetland at start of month Inflows - Outflows Inflows Outflows Water depth at end of month without outflow Weir depth

slide-35
SLIDE 35

Outflow assumed to occur through a weir

slide-36
SLIDE 36
slide-37
SLIDE 37

In the Basic Model, water greater than the “weir depth” is lost from the wetland as

  • utflow each month.
slide-38
SLIDE 38

Questions?