Tullamarine Landfill Community Meeting 30 March 2016 Stormwater Connection Improved Design Landscaped Channel No Pipe Concrete Pits and Pipes Amended Landscaped Channel Weir Landscaped Channel Road Crossing Instead of Concrete Pipe.


slide-1
SLIDE 1

Tullamarine Landfill Community Meeting

30 March 2016

slide-2
SLIDE 2

Stormwater Connection – Improved Design

Landscaped Channel Landscaped Channel Road Crossing Landscaped Channel Instead of Concrete Pipe. No Pipe Weir Concrete Pits and Pipes Amended

slide-3
SLIDE 3

Stormwater Connection Improvements in Design

 Increased frog habitat area  Less concrete  Softer Landscaping approach  Less likelihood of erosion  Improved water quality  Increased safety

slide-4
SLIDE 4

Groundwater Update

Currently Updating the Management and Monitoring Plan

Information on current monitoring frequency will be provided with Technical Review information

TECHNICAL REVIEW

Currently with the Auditor

The Technical Review Report will be ready for the community by end of April

Monitoring & Management Plan, including contingency requirements, will be included

Upon receipt of final report, welcome a special briefing session with community before next meeting

slide-5
SLIDE 5

New Landfill Gas Perimeter Boreholes

Proposed Locations On Airport Land Prepared by Cardno Lane Piper for Cleanaway

slide-6
SLIDE 6

New Groundwater Monitoring Boreholes

Proposed Locations Proposed Locations Non regulatory requirement

slide-7
SLIDE 7

Air Quality Testing Update

 Flare sampling for methane destruction efficiency will take

place in April 2016.

 A second full emissions test is to be completed after methane

testing is undertaken during May/June when climate conditions are colder.

 Ambient

air monitoring design and procedure being developed by our experts. This will be ready in June.

 Ambient air monitoring will be undertaken concurrently with

next emissions testing in second half of 2016.

slide-8
SLIDE 8

Flare Sampling Equipment - Calibrated In-Situ Equipment

Methane (CH4), Temp, Pressure, Flow

slide-9
SLIDE 9

Flare Equipment - New Sample Location

slide-10
SLIDE 10

Flare Equipment

Outlet Sample Point Blower Water Knock Out Pot Inlet Sample Point Calibrated Data Collection System Flow Temperature Methane %

Landfill Gas Inlet Combustion Air Inlet Methane Detector Sample Canister for Laboratory Sample Canister for Laboratory

slide-11
SLIDE 11