Community Meeting Transportation Around TJ New Elementary School August 10, 2016 Department of Environmental Services Division of Transportation and Development Services Community Meeting Transportation Around TJ New Elementary School


slide-1
SLIDE 1

Community Meeting –

Transportation Around TJ New Elementary School August 10, 2016

Department of Environmental Services

Division of Transportation and Development Services

slide-2
SLIDE 2

2

Community Meeting – Transportation Around TJ New Elementary School

  • Meeting Agenda:
  • Welcome & Background -

Katie Cristol, County Board Member

  • TJ School Site Transportation Review Process -

Robert Gibson, Principal Planner

  • Broader Area Transportation Projects & Programs -

Dennis Leach, Arlington Director of Transportation

  • Q&A
slide-3
SLIDE 3

3

Project Timeline by APS

Source: http://www.apsva.us/wp-content/uploads/2016/04/DC-072016-NES-at-TJ-Concept-Design-SB-action-item.pdf

slide-4
SLIDE 4

4

Transportation Projects/Issues to be Considered

As Part of Thomas Jefferson New Elementary School

Transportation Information and Input for Consideration & Evaluation

Community Comments Public Facility Review Committee (PFRC) Comments

APS Transportation Study for TJ by Toole Design Group

Capital Projects In the Pipeline within the Area

New Elementary School at Thomas Jefferson Site Public Review

slide-5
SLIDE 5

5

Review and Sorting of Information and Input

Transportation Information and Input for Consideration & Evaluation

School Related Transportation Improvements/Operations Long-Term Programmed Improvements Near-Term Improvements and Actions

slide-6
SLIDE 6

6

Review and Sorting of Information and Input

School Related Transportation Improvements/Operations

  • School related infrastructure improvements.

(Identified and required as part of use permit approval)

  • Development of school related transportation operational procedures.

(Required prior to school opening)

  • Safe Routes to School Plans
  • Drop-off and Pick-up Operations
  • Bus Arrival and Dismissal Operations
  • Review of school related transportation operational procedures.

(Required shortly after school opens)

slide-7
SLIDE 7

7

Review and Sorting of Information and Input

Near-Term Improvements and Actions

  • County Operations and Maintenance
  • Arlington Public Schools Operations Changes
  • Arlington County Police Department (ACPD) Enforcement
slide-8
SLIDE 8

8

Review and Sorting of Information and Input

Long-Term Programmed Improvements

  • Neighborhood Conservation
  • Neighborhood Complete Streets
  • Safe Routes to Schools
  • Arterial Streets Program
slide-9
SLIDE 9

9

Toole Design Group’s Transportation Analysis Study Area

Focus of School/Project Related Transportation Improvements Toole’s Study Area

slide-10
SLIDE 10

10

Toole Design Group’s Transportation Analysis Summary of Key Transportation Issues

Source: http://www.apsva.us/wp-content/uploads/2016/04/DC-160727-New-ES-as-TJ-Transportation-Presentation.pdf

  • Congestion at 2nd Street South and South Old Glebe Road
  • Vehicle Speed on 2nd Street South
  • Reported wrong way driving and speed on 1st Road South
  • Pedestrian/ADA and Bicycle Access to Site
slide-11
SLIDE 11

11

Community Comment

  • Arlington Heights Transportation Issues and Concerns - Winter 2016
  • Transportation Around TJ New Elementary School Meeting

Comments – August 2016

slide-12
SLIDE 12

12

Capital Project Pipeline

  • 5th Street South - Glebe Road to Jackson Street - Streetlight Project
  • Install new street lights

– Just recommended for funding by the NCAC in June of 2016 – Will be approved by the Board in September of 2016 – No timeline for construction

  • Arlington Boulevard Service Road from Fillmore to Irving Streets
  • Pedestrian safety and trail improvements and realignment
  • Drainage improvements
  • New streetlights, curb, and gutter and sidewalk in select locations

– In active design and expected construction is 2017, pending VDOT review

  • Arlington Boulevard & Irving Street Intersection Improvements
  • Improve safety for all modes; connection to trail
  • traffic signal upgrade
  • Crosswalks, ADA ramps, sidewalk connections
  • New bus facilities
  • Remove utility poles

– Design under review by VDOT prior to procurement – Expected construction spring 2017

slide-13
SLIDE 13

13

Capital Project Pipeline (cont.)

  • South Fillmore Street from Arlington Boulevard to 5th Street South
  • South Fillmore Street sidewalk widening
  • Relocation of utility poles
  • New pavement markings and signage

– Under construction currently with completion fall 2016

  • South Walter Reed Drive from 5th to 9th Streets South
  • Installing medians and landscaping in some medians
  • Adding curb extensions “nubs”, and ADA curb ramps
  • Bioretention facilities at 5th Street South and 9th Street South
  • New signal at Walter Reed Drive and 9th Street South
  • New striping and signage

– In design at 60%, working on incorporating design comments including community comments

slide-14
SLIDE 14

14

Recently Completed Projects in the Area

  • South Fenwick Street - Arlington Boulevard to 2nd Street South
  • New Carlyle street lights along west side of street
  • New sidewalk, curb and gutter
  • New grass utility strip
  • New pavement markings and signage
  • South Garfield Street - Arlington Boulevard to 2nd Street South
  • New Carlyle street lights along west side of street
  • New sidewalk, curb and gutter, on west side of street
  • New grass utility strip on west side of street
  • New curb and gutter on east side of street
  • New pavement markings and signage
  • Full depth repaving
  • South Irving Street - Arlington Boulevard to 2nd Street South
  • New roadway, curb and gutter, widening the street for two travel lanes and parking on

east side of street

  • Provision of existing trees, with some new street trees added
  • New crosswalk and gateway treatment added to north end of block
slide-15
SLIDE 15

15

Recently Completed Projects in the Area (cont.)

  • South Highland Street, South Ivy Street and 9th Street South
  • New Carlyle street lights along South Highland Street and South Ivy Street from 7th

Street South and 9th Street South

  • New Carlyle street lights along 9th Street South from South Glebe Road to Walter Reed

Drive

  • Arlington Boulevard/Glebe Road Bridge Reconstruction
  • Bridge deck replacement
  • New northbound left-turn lane
  • New traffic signals
  • Improved sidewalks/shared-use paths 11 and 17 feet respectively
  • 2nd Street South Bike Lanes
  • Narrowed travel lanes adding striped on-street bike lanes
  • Installed curb extensions “nubs” and warning signs
  • Upgraded and replaced handicapped ramps
  • Improved crosswalks at South Jackson Street and South Ivy Street
  • Replaced some sidewalk segments with new concrete
slide-16
SLIDE 16

16

Recent Operational Changes in the Area

  • 1St Road South between South Glebe Road and South Old Glebe Road
  • Installed new No U-Turn sign and One-Way sign (July 2016)
  • Enhanced signage on Old Glebe Road entrance (2013)
  • New speed limit sign (2012)
  • Speed study 2012 (85th percentile 24 mph and 19 mph average speed)
  • 2nd Street South and Glebe Road Intersection
  • Request to restripe crosswalk crossing west side of 2nd Street South
  • Reviewing South Old Glebe Road for Residential Permit Parking
slide-17
SLIDE 17

17

Programs to Consider for Long Term Improvements

  • Neighborhood Conservation
  • Neighborhood Complete Streets
  • Safe Routes to Schools
  • Arterial Streets Program
  • Transportation Operations
slide-18
SLIDE 18

18

Next Steps (Coordinated with PFRC Process)

  • Summary of Inputs – October, 2016
  • Identification of Transportation Related Projects to be Included in

TJ Use Permit – January 2017

  • Designed as part of TJ Project
  • Included in Use Permit Review
  • Final Determination of Non-School Short & Long-Term Projects –

March 2017

  • Handoff to various partners
slide-19
SLIDE 19

19

Questions?

RESOURCES FOR MORE INFORMATION:

  • Website: PFRC’s Thomas Jefferson (New Elementary School)

– Visit www.arlingtonva.us; search “PFRC” or “TJ School”

  • PFRC Members
  • Arlington’s Transportation Website

– https://transportation.arlingtonva.us/ – Report a Problem: 703-228-6570