Common Blind Spots in Ground Investigation, Design, Construction, - - PowerPoint PPT Presentation

common blind spots in ground investigation design
SMART_READER_LITE
LIVE PREVIEW

Common Blind Spots in Ground Investigation, Design, Construction, - - PowerPoint PPT Presentation

SEAGS 50 th Anniversary Symposium Proceedings: September 14-15,2017 Common Blind Spots in Ground Investigation, Design, Construction, Performance Monitoring and Feedbacks in Geotechnical Engineering Ir. Liew Shaw Shong G&P Geotechnics


slide-1
SLIDE 1

Common Blind Spots in Ground Investigation, Design, Construction, Performance Monitoring and Feedbacks in Geotechnical Engineering

  • Ir. Liew Shaw Shong

G&P Geotechnics Sdn Bhd, Kuala Lumpur, Malaysia

SEAGS 50th Anniversary Symposium Proceedings: September 14-15,2017

slide-2
SLIDE 2

Mission Statement

  • Site Investigation

– Planning, Execution & Interpretation

  • Forensic Investigation

– Stability of Piled Supported Retaining Wall – Embankment Distress (Strain Incompatibility) – Abutment Distress due to Piled Embankment Failure – Unreliable Facing Capacity of Soil Nailed Slope – Illusive End Bearing Pile Capacity – Non-linearity Elasto-Plastic & Hysteresis Phenomena

  • f Pile-Soil Interaction Performance
slide-3
SLIDE 3

Site Investigation

  • List CEO and key management by name.
  • Include previous accomplishments to show that these

are people with a record of success.

  • Summarize number of years of experience in this field.
slide-4
SLIDE 4

Lessons Learnt on Stability of a Piled Retaining Wall in Weak Soils

  • Ir. Liew Shaw-Shong
slide-5
SLIDE 5

Content

Chronological events Distress conditions of wall Desk study & subsurface conditions Forensic investigation (Geotechnical & Structural assessments) Probable Causations Remedial Solution Conclusion

slide-6
SLIDE 6

Chronological events

First SI : Jan 2005 (Within project site) Second SI : May 2005 (at wall area) Wall Distress : Feb 2006 (After prolonged rain) Forensic Investigation : Feb to Mar 2006

slide-7
SLIDE 7

Tension Crack & Wall Distresses

slide-8
SLIDE 8

Overall View of Site

slide-9
SLIDE 9

RL48m

Cross Section of Wall

1100 750

100mm Subsoil Pipe 50mm Thk Lean Concrete 150mm  Weephole T12-150 T20-100 T12-150 T12-150 T12-150 T16-100 T12-150 T12-150 T12-100 300mm Free Draining Granular Material Construction Joint

2500 2500 2500 600 600 750 1100 500 5 Rows of 200x200 RC piles @ 2m Spacing

slide-10
SLIDE 10

Weephole at RL47.5m Weephole at RL45m (Water staining) Weephole at RL42.5m

Weephole Drains

slide-11
SLIDE 11

Erosion by Weephole Discharge

slide-12
SLIDE 12

Erosion of Wall Base

slide-13
SLIDE 13

Aerial View (Pre-development)

Previous Stream Wall

slide-14
SLIDE 14

Wall Previous Stream

Site Topography & SI Works

BH8 BH9 BH10

2nd Stage BH 1st Stage BH Forensic BH

ABH1 ABH2

slide-15
SLIDE 15

Previous 2-Stage Boreholes

~ RL41m ~ RL40m ~ RL43m

slide-16
SLIDE 16

Forensic Boreholes

slide-17
SLIDE 17

Vane Shear Test Strength Profile

2 4 6 8 10 12 14 16 18 20 22 24 26 Undrained Shear Strength, Su (kPa) 10 9 8 7 6 5 4 3 2 1 Depth (m) 10 9 8 7 6 5 4 3 2 1 2 4 6 8 10 12 14 16 18 20 22 24 26

Interpretation of Vane Shear Test Results

Mesri Line = 0.22v' Peak Strength Remoulded Strength Peak strength and remoulded strength are obtained from vane shear test results. Peak Strength adopted in analysis, Su=25kPa Undrained shear strength profile of normally consolidated fine soils

RL42.34m RL38.34m (Possible Slip Surface)

slide-18
SLIDE 18

RL48m 1100 750

100mm Subsoil Pipe 50mm Thk Lean Concrete 150mm  Weephole T12-150 T20-100 T12-150 T12-150 T12-150 T16-100 T12-150 T12-150 T12-100 300mm Free Draining Granular Material Construction Joint

2500 2500 2500 600 600 750 1100 500 5 Rows

  • f

200x200 RC piles @ 2m Spacing

FOS Adequacy

GWT Over- turning Sliding Global Stability

RL45m

2.9>2.0

0.97<1.0 (Failure)

1.13/1.17 RL42.5m

3.7>2.0

1.34<1.5

✓/

1.19/1.25 RL40.4m

3.8>2.0

1.5

✓/

1.16/1.24

Stability Assessments

Bearing Capacity is never a concern as pile foundation is designed to take the vertical loading of wall

slide-19
SLIDE 19

‘v  = = ’vTan Tan’ + c’

More prominent in effective stress analysis, but less for total stress analysis

slide-20
SLIDE 20

Pile Integrity Testing

6 PIT : Discontinuity detected at depths from 1m to 4m below pile top

slide-21
SLIDE 21

Rankine Pressure Brom’s Lateral Pile Capacity:

Fixed Head : 32kN/pile (Likely the case) Free Head : 20kN/pile

Ultimate lateral pile capacity reached when RL42.5m<GWT<RL45m

Pile Structural Assessments

slide-22
SLIDE 22

Probable Causes of Wall Distress

Potential perched water regime in natural valley terrain after raining Rise of groundwater increases the lateral force on wall Inadequate lateral pile resistance Reduction of effective soil strength due to reduction of vertical stress as wall loading carried by piles

slide-23
SLIDE 23

Remedial Solution

Soil Replacement for upper weak soil Overcut existing piles below new wall base Construct stabilising berm in front of new wall Provide subsoil drainage behind wall to control rise of groundwater seepage

slide-24
SLIDE 24

3m Soil Replacement below RL39.3m

Remedial Solution

Disconnect piles by over cutting below cut-off level Collector Pipe Drain Drainage Blanket

slide-25
SLIDE 25

Potential perched water regime in natural valley terrain after raining Rise of groundwater (inefficient sub-terrain drainage) increases the lateral force on wall Inadequate lateral pile resistance Reduction of effective soil strength due to reduction

  • f vertical stress as wall loading carried by piles

Slender vertical piles not suitable for supporting wall

  • n weak & compressible soils (Poor lateral resistance)

Remedial works : Soil Replacement + Subsoil drainage + Stabilising berm Solution : Raked piles in combination of vertical piles (Serviceability limit state)

Conclusion

slide-26
SLIDE 26

Role of Extendible Basal Reinforcement for Embankment Construction Over Soft Soils

 Introduction  Problem Statements & Distress  Back Analysis  Discussions  Conclusions  Recommendations

slide-27
SLIDE 27

Introduction

  • Embankment  Raised fill platform with

side slopes to support structure and infrastructure developments.

  • Stage construction + additional

reinforcement  Ensure acceptable side slope stability

  • Basal reinforcement  To minimise

spreading failure of compacted embankment fill over weak supporting subsoils

slide-28
SLIDE 28

Basal Reinforcement

  • Shall be designed in accordance with

BS8006.

  • Consideration  Strain compatibility

between embankment fill and basal reinforcement system.

  • Tensile strain in basal reinforcement shall be

controlled to avoid cracking in embankment fill.

slide-29
SLIDE 29

Basal Reinforcement

  • If the embankment is strained to excessive

tensile crack, the embankment fill material strength is doubtful.

  • Thus, case study of an instrumented

embankment construction with extendible basal reinforcement have been used.

  • This may call for a review of the permissible

strain of extendible basal reinforcement with brittle compacted fill.

slide-30
SLIDE 30

Problem Statement & Distresses

 Problem Statements

 Embankment Fill over Soft Deposits  PVD with Staged Construction  Basal Reinforcement for T

emporary Embankment Stability

 BS8006  Strain Incompatibility

 Distresses

 Longitudinal flexural cracks on embankment surface

slide-31
SLIDE 31

Embankment Distresses

Cracks locations of distressed embankment Crack line observed.

slide-32
SLIDE 32

Embankment Distresses

slide-33
SLIDE 33

Embankment Distresses

Alligator cracks

  • bserved on site.
slide-34
SLIDE 34

Embankment Distresses

1m surcharge removal after distresses observed

slide-35
SLIDE 35

Embankment Distresses

Cracks found after 1m surcharge removal.

slide-36
SLIDE 36

Embankment Distresses

Excavation on cracks found after 1m surcharge removal

slide-37
SLIDE 37

Instrumentation Layout

Instrumentation Layout Plan at Distresses area

slide-38
SLIDE 38

Instrumentation Results

Fill Thickness and Settlement of Embankment with time monitoring by SG580

slide-39
SLIDE 39

Instrumentation Results

Inclinometer I6 Monitoring Results R1 S2 R2

slide-40
SLIDE 40

Finite Element Model

Backfill material Drainage Blanket Basal Reinforcement Installed PVD Soft Clay Layer

slide-41
SLIDE 41

Finite Element Model

Back analysis to match lateral deformation and settlement profiles. Two cases were modelled for back analysis:- Case 1: Ultimate strength (600kN/m) mobilized at 10% Case 2: Ultimate strength (140kN/m) mobilized at 1%

slide-42
SLIDE 42

Finite Element Model

Comparison of Back Analysed Settlement Trend With Actual Measurement (Case 1)

slide-43
SLIDE 43

Finite Element Model

Comparison of Lateral Displacement Profile (Case 1) R1 S2 R2

slide-44
SLIDE 44

Summary of Back Analyses

Stage T ensile Stiffness Mobilised T ensile Load / T ensile Strain Maximum Lateral Deflection at Edge of Embankment (mm) S1 Case 1 Case 2 40.6kN/m / 0.68% 65.9kN/m / 0.47% 267 (173) R1 Case 1 Case 2 41.8kN/m / 0.70% 67.4kN/m / 0.48% 295 (180) S2 Case 1 Case 2 64.6kN/m / 1.08% 106.8kN/m / 0.76% 400 (253) R2 Case 1 Case 2 67.4kN/m / 1.12% 110.3kN/m / 0.79% 425 (265)

slide-45
SLIDE 45

Probable Mechanism

slide-46
SLIDE 46

Discussion

 Strain incompatibility between basal reinforcement

and embankment fill could potentially cause embankment cracking.

 Average tensile strain of underlying weak subsoils is

more than max. tensile strain in basal reinforcement.

 Results of back-analysis  indicated mobilised tensile

strength and strain < conventional assumed values for LEA stability analysis.

slide-47
SLIDE 47

Conclusion

 Longitudinal cracks  Outcome of plastic straining

  • f upper weak alluvium within the underlying subsoil

below the embankment loading.

 Review on current design practice by arbitrarily

adopting unrealistic high mobilised strength is needed.

 Wishful high tensile strain assumed in LEA can lead to

misrepresentation on safety margin of embankment.

slide-48
SLIDE 48

Recommendations

 Counterweight berm was proposed to solve the

strain incompatibility between basal reinforcement and the subsoil.

 Instrument on basal reinforcement to reveal the

distribution profile and performance of installed basal reinforcement.

slide-49
SLIDE 49

Case 2: Case study on Piled Supported Embankment Failure

49

slide-50
SLIDE 50

P3 P2 P1 P

A Abutment A Abutment B Pier P1 Pier P2 Piled Embankment PVD + EVD Area

P

A Lower Firm Stratum

Filled Working Platform

Upper Weak Soil EVD PVD

Site Conditions

 Embankment (maximum 5.4m high) with Piles & Ground

Improvements

 Ch3328 to Ch3375 (Top 10m soft Clay, Su = 10~15kPa)

 Distressed Abutment

 Abutment A @ Ch3266 (Top 15m soft Clay, Su = 13~18kPa)  Abutment B @ Ch3328 (Top 9m soft Clay, Su = 7~12kPa)

50

slide-51
SLIDE 51

Findings from Site Inspection

 Piles & slab of piled embankment suffered structural distress  Settlement of 0.4 to1.0m beneath piled embankment due to

consolidation of subsoils under the working filled platform.

 Bearing distortions confirmed : Bridge deck moving from

Abutment B towards Abutment A

51

slide-52
SLIDE 52

Site Inspection Findings

 Piled Embankment 30m from Abutment B shown structural

distress

52

slide-53
SLIDE 53

Site Inspections Findings

 Piles of Piled Embankment has shown flexural cracks

53

slide-54
SLIDE 54

Site Inspections Findings

 Damaged piled embankment slab damaged & 100mm gap at

slab joint

54

slide-55
SLIDE 55

Site Inspections Findings

 Settlement of 0.4 to 1.0m under the Piled Embankment

55

slide-56
SLIDE 56

Site Inspections Findings

 Bearing distortion at Pier P2

56

slide-57
SLIDE 57

Site Inspections Findings

 Bearing distortion at Pier P1

57

slide-58
SLIDE 58

P3 P2 P1 P

A

FOS

Abutment A Abutment B Pier P1 Pier P2 Piled Embankment PVD + EVD Area

P

A

PA : Active Earth Pressure P1 : Action/Reaction Force between Piled Embankment Slab & Abutment P2 : Ultimate Lateral Pile Group Capacity of Embankment Piles P3 : Mobilised Thrust on Stability Soil Mass with Corresponding FOS

Lower Firm Stratum

Filled Working Platform

Upper Weak Soil EVD PVD

58

slide-59
SLIDE 59

Movement Direction

P3 P

A

FOS

Abutment A Abutment B Pier P1 Pier P2 Piled Embankment PVD + EVD Area

P

A

PA : Active Earth Pressure P1 : Action/Reaction Force between Piled Embankment Slab & Abutment P2 : Ultimate Lateral Pile Group Capacity of Embankment Piles P3 : Mobilised Thrust on Stability Soil Mass with Corresponding FOS Clockwise Rotation Anti-Clockwise Rotation Developing Pile Plastic Hinge

T ension Cracks

Bearing Distortion

P2 P1

Abutment B Pier P1 Abutment A Pier P2 EVD Area Piled Embankment

P

A + P1 A B C D E F Ch 3360 Ch 3307.42 Ch 3266.02 Ch 3286.72 Ch 3328.12 Deck 1 Deck 2 Deck 3 Displacement Markers (by LDC) : 02 Mar – 18 Jun 2006 1 2 3 4 5 6 7 8 8 10 11 12 13 14 15 16 18 19 Displacement Markers (by G&P) : 25 Apr – 7 May 2007 M1 M2 M3 M4 M5 M6 M13 M14 M7 M8 M9 M10 M12 M13 Settlement Markers (LDC) : 28 May -31 Jul 2005 PVD Area

59

slide-60
SLIDE 60

Investigation Findings

 Embankment (5.4m high)

 Ch3375 : FOS  1.0 at Embankment on Ground Treatments  Causation : Inadequate FOS => Embankment instability exerting

lateral stress to Piled Embankment on free standing piles due to subsoil consolidation

 Distressed Abutment

 Abutment B : Laterally pushed by unstable embankment behind

piled embankment

 Abutment A & T

wo piers : Affected by lateral thrust from Abutment B (No observable distresses at the abutment pile foundation after exposure of piles)

60

slide-61
SLIDE 61

Abutment Remedial Design

 Abutment Distress (Ch3266 to Ch3328)

 Remedial proposal : Isolation Gap

61

slide-62
SLIDE 62

Conclusions

 Weak post-treatment soil strength unable to support

embankment

 Creep movement of weak subsoil beneath embankment

coupled with embankment instability due to low FOS

 Further consolidation of weak overburden soil, the lateral

resistance of piled embankment in free standing pile conditions is weaken

 Monitored bridge displacement confirmed pattern of lateral

movement of entire bridge & piled embankment

 Structural damage on embankment piles was expected as

structural threshold has reached

 Use of residual strength is needed for rectifying failed

embankment

62

slide-63
SLIDE 63

Recommendations

 Construct new embankment slab at least 1m below the

failed slab to prevent further consolidation settlement

 Extend piled embankment for embankment fill higher than

2m & provide isolation gap at the slab/abutment interfaces

 Use of higher strength RC pile for embankment piles  Use of geotextile reinforcement to isolate embankment fill

from both abutments to reduce direct lateral earth pressure

  • n abutments

63

slide-64
SLIDE 64

Unreliable Facing Capacity of Soil Nailed Slope

  • With intention of minimized earthwork cutting forming

any platform, soil nailed slope profile is normally steep

  • Facing capacity has remarkable effect on Internal

Stability of steep soil nailed slope

  • Volumetric swelling & shrinkage of soils with moisture

variation are realistic observation

  • Moisture depletion after covering with shotcrete surface

results in volumetric shrinkage of slope soil face leaving air gap with separation of contact with shotcrete

  • Mobilisation of face capacity in uncontacted slope

surface is unrealistic, thus giving incorrect safety margin

  • f slope stability
slide-65
SLIDE 65

Volumetric Shrinkage of Exposed Soil

slide-66
SLIDE 66

Gap below Shotcrete Surface with Depleting Moisture

slide-67
SLIDE 67

Nail Force Diagram

Slip Surface S2 S1 TN TH fs,p Soil Nail fs,a

slide-68
SLIDE 68

Case Study 1 : Reduced Empty Pre-bored Jack-in Pile Capacity in Meta-Sedimentary Formation

  • Overview of pile installation & Performance
  • Subsurface Information
  • Contractually Scheduled MLT Results
  • Additional MLT Results
  • Investigation Findings
  • Conclusions & Recommendations
slide-69
SLIDE 69

Overview Foundation System

  • 400mm RC square pile
  • Pre-boring was deployed to
  • Overcome intermittent hard layer
  • Avoid shallow pile penetration
  • Jack-in pile installed inside pre-bored hole
slide-70
SLIDE 70

Pre-bored Hole Diameter

600mm diameter 500mm diameter 550mm diameter Too large pre-bored hole Too small pre-bored hole Compromised pre- bored hole

(Adopted)

Pre-bored hole 400mm dia. RC Pile

slide-71
SLIDE 71

Void in Pre-bored Hole Annulus

slide-72
SLIDE 72

Collapsed Debris in Pre-bored Hole Annulus

slide-73
SLIDE 73

Actual Scenario of Installed Piles

L – Pre-bored Length P – Actual Penetration Length P = L P > L P >> L 9m deep prebored

slide-74
SLIDE 74

MLT Results

Maintained Load Test (MLT) Pre-bored Diameter (mm) Pile Penetration below Piling Platform (m)

  • Max. Jack-in

Load at Termination (kN) Achieved Maximum Test Load (kN) Pile Top Settlement At Working Load (mm) At Max. Test Load (mm) MLT 1 600 9.40 2160 2220 (1.71xWL) 14.0 46.00 MLT 2 500 9.30 2600 2220 (1.71xWL) 23.50 42.00 MLT 3 550 12.50 2860 2600 (2.00xWL) 5.80 21.80 MLT 4 550 9.50 2860 1406 (1.50xWL) 16.50 24.50 MLT 5 550 13.50 2860 1950 (1.50xWL) 8.50 13.00

slide-75
SLIDE 75

Jack-in Pile Termination Criteria

  • All piles were jacked to 2.2 times pile working load
  • Settlement < 5mm during 30 seconds holding

period for 2 consecutive times

slide-76
SLIDE 76

Boreholes Information

SPT-N>50

Piling Platform End of Pre- bored 9m Pre- bored

slide-77
SLIDE 77

Photos of Exposed Subsoils

slide-78
SLIDE 78

Contractually Scheduled MLT Results

slide-79
SLIDE 79

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m

MLT 1

slide-80
SLIDE 80

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m

MLT 1 MLT 2

slide-81
SLIDE 81

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m

MLT 1 MLT 2 MLT 3

slide-82
SLIDE 82

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m

MLT 1 MLT 2 MLT 3 MLT 4

slide-83
SLIDE 83

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m

MLT 1 MLT 2 MLT 3 MLT 4 MLT 5

slide-84
SLIDE 84

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m

MLT3 & MLT5: Longer Pile Penetration below pre- bored base performs better

slide-85
SLIDE 85

Additional MLT Results

slide-86
SLIDE 86

Additional MLT

  • 3 nos additional MLT at various penetration below pre-

bored base:

  • MLT6 – 0.5m below pre-bored base
  • MLT7 – 1.5m below pre-bored base
  • MLT8 – 2.0m below pre-bored base
slide-87
SLIDE 87

Additional MLT

slide-88
SLIDE 88

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 6 - 9.5m MLT 7 - 10.5m MLT 8 - 11.0m

MLT 6

slide-89
SLIDE 89

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 6 - 9.5m MLT 7 - 10.5m MLT 8 - 11.0m

MLT 6 MLT 7

slide-90
SLIDE 90

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 6 - 9.5m MLT 7 - 10.5m MLT 8 - 11.0m

MLT 6 MLT 8 MLT 7

slide-91
SLIDE 91

MLT Pre-bored Diameter (mm) Pile Penetration below Piling Platform (m)

  • Max. Jack-in

Load at Termination (kN) Achieved Maximum Test Load (kN) Pile Top Settlement At Working Load (mm) At Max. Test Load (mm) MLT 1 600 9.40 2160 2220 (1.71xWL) 14.0 46.00 MLT 2 500 9.30 2600 2220 (1.71xWL) 23.50 42.00 MLT 3 550 12.50 2860 2600 (2.00xWL) 5.80 21.80 MLT 4 550 9.50 2860 1406 (1.50xWL) 16.50 24.50 MLT 5 550 13.50 2860 1950 (1.50xWL) 8.50 13.00 MLT 6 550 9.50 2860 1950 (1.50xWL) 15.08 42.38 MLT 7 550 10.50 2860 2400 (1.85xWL) 11.29 41.93 MLT 8 550 11.00 2860 2600 (2.00xWL) 10.30 50.35

slide-92
SLIDE 92

Pre-bored Penetration below base of pre-bored

Investigation Findings

slide-93
SLIDE 93

Analogy of Footing

slide-94
SLIDE 94

Bearing Improvement with Toe Confinement

slide-95
SLIDE 95

Conclusions & Recommendations

  • Pile performance improved with longer

pile penetration below pre-bored base

  • Existence of pile toe softening due to

relaxation of pile tip founding material

  • Sufficient pile penetration below pre-

bored base is important

  • Recommend

to seal the pre-bored hole with grout

slide-96
SLIDE 96

Case Study 2: Pile Heave & Lateral Soil Displacement

 Rapid pile installation in incompressible soft soil induces

 Vertical heave in shallow depth (relatively less confinement from weight of

  • verburden soils)

 Lateral displacement in deeper depth (with soil confinement)

 Consequences :

 Up-heaving soil movement causes tensile stress on pile & toe lift up during driving &

downdrag after pore presure dissipation

 Lateral soil displacement causes flexural stress on pile & pile deviation  Excessive combined tensile and flexural stresses lead to pile joint dislodgement  Excessive foundation settlement in post construction (pile toe uplifting & downdrag

settlement)

slide-97
SLIDE 97

Pile Joint Dislodgement

 Pile joints could be dislodged due to excessive flexural and tensile stresses

induced by ground heave and radial soil displacement

 Detectable using High Strain Dynamic Pile T

est (HSDPT)

slide-98
SLIDE 98

Mechanism of Pile Heave & Soil Displacement

slide-99
SLIDE 99

Case Study - HSDPT

 Monitoring of pile top settlement during the HSDPT re-strike tests is

summarised as below:

Cumulative Pile T

  • p

Settlement (mm) Pile C Pile A Pile B Pile D Pile E Upon resting 7-ton hammer on pile top 80 98 125 103 92 At the end of Restriking Test 275 399 497 186 182

slide-100
SLIDE 100

Case Study - HSDPT

 Pile B  Initial Blow One Pile Length (12m) was DETECTED with Major Discontinuity at ‘toe’ (reflection)

slide-101
SLIDE 101

Case Study - HSDPT

 Pile B  Blow No. 4 First Joint Discontinuity closed up after few blows; Two Pile Lengths was revealed with another Major Discontinuity at new ‘toe’ (reflection)

slide-102
SLIDE 102

Case Study - HSDPT

 Pile B  Blow No. 17 Second Major Joint Discontinuity also disappeared; Total of Three Pile Lengths was observed

slide-103
SLIDE 103

Case Study - HSDPT

 Pile B  End of Blow Minor velocity reflections were

  • bservable at first and

second pile joints

slide-104
SLIDE 104

Pile Heave Monitoring Program

X Y Z

slide-105
SLIDE 105

Pile Heave Monitoring Result

5 10 15 20 25 30 1 2 3 4 5 6 7 8 9 10 11 12 Measured Pile Heave (mm) Pile Installation in Sequence Pile No.1 Pile No.3 Pile No.4 Pile No.5 Pile No.6 Pile No.7 Pile No.8 Pile No.9 Pile No.10 Pile No.11 Pile No.12

slide-106
SLIDE 106

Summary

 Ground heave & radial soil displacement due to rapid installation of

displacement pile in soft incompressible soft clay can pose serious integrity problem on pile foundation.

 Solutions :

 Use larger pile spacing & reduce rate of clustered pile installation for adequate time

for dissipation of excess pore pressure

 Simultaneous pile installation at mirror pile location from centre outwards to

minimise net lateral displacement, but this improves nothing on ground heave

 Stronger pile structural strength & joint to withstand tensile & flexural stresses  Staggered pile installation sequence or install piles at alternate locations  Restrike all piles with HSDPT to detect pile integrity if ground or soil heave is

  • bserved.
slide-107
SLIDE 107

Opportunities

  • Identify problems and opportunities.

– State consumer problems, and define the nature of product/service opportunities that are created by those problems.

slide-108
SLIDE 108

Business Concept

  • Summarize the key technology, concept, or strategy on

which your business is based.

slide-109
SLIDE 109

Competition

  • Summarize the competition.
  • Outline your company’s competitive advantage.
slide-110
SLIDE 110

Goals and Objectives

  • List five-year goals.
  • State specific, measurable objectives for achieving your

five-year goals. – List market-share objectives. – List revenue/profitability objectives.

slide-111
SLIDE 111

Financial Plan

  • Outline a high-level financial plan that defines your

financial model and pricing assumptions. – This plan should include expected annual sales and profits for the next three years. – Use several slides to cover this material appropriately.

slide-112
SLIDE 112

Resource Requirements

  • List requirements for the following resources:

– Personnel – Technology – Finances – Distribution – Promotion – Products – Services

slide-113
SLIDE 113

Risks and Rewards

  • Summarize the risks of the proposed project and how

they will be addressed.

  • Estimate expected rewards, particularly if you are

seeking funding.

slide-114
SLIDE 114

Key Issues

  • Near term

– Identify key decisions and issues that need immediate or near-term resolution. – State consequences of decision postponement.

  • Long term

– Identify issues needing long-term resolution. – State consequences of decision postponement.

  • If you are seeking funding, be specific about any issues

that require financial resources for resolution.