SLIDE 1 Common Blind Spots in Ground Investigation, Design, Construction, Performance Monitoring and Feedbacks in Geotechnical Engineering
G&P Geotechnics Sdn Bhd, Kuala Lumpur, Malaysia
SEAGS 50th Anniversary Symposium Proceedings: September 14-15,2017
SLIDE 2 Mission Statement
– Planning, Execution & Interpretation
– Stability of Piled Supported Retaining Wall – Embankment Distress (Strain Incompatibility) – Abutment Distress due to Piled Embankment Failure – Unreliable Facing Capacity of Soil Nailed Slope – Illusive End Bearing Pile Capacity – Non-linearity Elasto-Plastic & Hysteresis Phenomena
- f Pile-Soil Interaction Performance
SLIDE 3 Site Investigation
- List CEO and key management by name.
- Include previous accomplishments to show that these
are people with a record of success.
- Summarize number of years of experience in this field.
SLIDE 4 Lessons Learnt on Stability of a Piled Retaining Wall in Weak Soils
SLIDE 5
Content
Chronological events Distress conditions of wall Desk study & subsurface conditions Forensic investigation (Geotechnical & Structural assessments) Probable Causations Remedial Solution Conclusion
SLIDE 6
Chronological events
First SI : Jan 2005 (Within project site) Second SI : May 2005 (at wall area) Wall Distress : Feb 2006 (After prolonged rain) Forensic Investigation : Feb to Mar 2006
SLIDE 7
Tension Crack & Wall Distresses
SLIDE 8
Overall View of Site
SLIDE 9 RL48m
Cross Section of Wall
1100 750
100mm Subsoil Pipe 50mm Thk Lean Concrete 150mm Weephole T12-150 T20-100 T12-150 T12-150 T12-150 T16-100 T12-150 T12-150 T12-100 300mm Free Draining Granular Material Construction Joint
2500 2500 2500 600 600 750 1100 500 5 Rows of 200x200 RC piles @ 2m Spacing
SLIDE 10 Weephole at RL47.5m Weephole at RL45m (Water staining) Weephole at RL42.5m
Weephole Drains
SLIDE 11
Erosion by Weephole Discharge
SLIDE 12
Erosion of Wall Base
SLIDE 13 Aerial View (Pre-development)
Previous Stream Wall
SLIDE 14 Wall Previous Stream
Site Topography & SI Works
BH8 BH9 BH10
2nd Stage BH 1st Stage BH Forensic BH
ABH1 ABH2
SLIDE 15 Previous 2-Stage Boreholes
~ RL41m ~ RL40m ~ RL43m
SLIDE 16
Forensic Boreholes
SLIDE 17 Vane Shear Test Strength Profile
2 4 6 8 10 12 14 16 18 20 22 24 26 Undrained Shear Strength, Su (kPa) 10 9 8 7 6 5 4 3 2 1 Depth (m) 10 9 8 7 6 5 4 3 2 1 2 4 6 8 10 12 14 16 18 20 22 24 26
Interpretation of Vane Shear Test Results
Mesri Line = 0.22v' Peak Strength Remoulded Strength Peak strength and remoulded strength are obtained from vane shear test results. Peak Strength adopted in analysis, Su=25kPa Undrained shear strength profile of normally consolidated fine soils
RL42.34m RL38.34m (Possible Slip Surface)
SLIDE 18 RL48m 1100 750
100mm Subsoil Pipe 50mm Thk Lean Concrete 150mm Weephole T12-150 T20-100 T12-150 T12-150 T12-150 T16-100 T12-150 T12-150 T12-100 300mm Free Draining Granular Material Construction Joint
2500 2500 2500 600 600 750 1100 500 5 Rows
200x200 RC piles @ 2m Spacing
FOS Adequacy
GWT Over- turning Sliding Global Stability
RL45m
✓
2.9>2.0
0.97<1.0 (Failure)
1.13/1.17 RL42.5m
✓
3.7>2.0
1.34<1.5
✓/
1.19/1.25 RL40.4m
✓
3.8>2.0
1.5
✓/
1.16/1.24
Stability Assessments
Bearing Capacity is never a concern as pile foundation is designed to take the vertical loading of wall
SLIDE 19 ‘v = = ’vTan Tan’ + c’
More prominent in effective stress analysis, but less for total stress analysis
SLIDE 20 Pile Integrity Testing
6 PIT : Discontinuity detected at depths from 1m to 4m below pile top
SLIDE 21
Rankine Pressure Brom’s Lateral Pile Capacity:
Fixed Head : 32kN/pile (Likely the case) Free Head : 20kN/pile
Ultimate lateral pile capacity reached when RL42.5m<GWT<RL45m
Pile Structural Assessments
SLIDE 22
Probable Causes of Wall Distress
Potential perched water regime in natural valley terrain after raining Rise of groundwater increases the lateral force on wall Inadequate lateral pile resistance Reduction of effective soil strength due to reduction of vertical stress as wall loading carried by piles
SLIDE 23
Remedial Solution
Soil Replacement for upper weak soil Overcut existing piles below new wall base Construct stabilising berm in front of new wall Provide subsoil drainage behind wall to control rise of groundwater seepage
SLIDE 24 3m Soil Replacement below RL39.3m
Remedial Solution
Disconnect piles by over cutting below cut-off level Collector Pipe Drain Drainage Blanket
SLIDE 25 Potential perched water regime in natural valley terrain after raining Rise of groundwater (inefficient sub-terrain drainage) increases the lateral force on wall Inadequate lateral pile resistance Reduction of effective soil strength due to reduction
- f vertical stress as wall loading carried by piles
Slender vertical piles not suitable for supporting wall
- n weak & compressible soils (Poor lateral resistance)
Remedial works : Soil Replacement + Subsoil drainage + Stabilising berm Solution : Raked piles in combination of vertical piles (Serviceability limit state)
Conclusion
SLIDE 26 Role of Extendible Basal Reinforcement for Embankment Construction Over Soft Soils
Introduction Problem Statements & Distress Back Analysis Discussions Conclusions Recommendations
SLIDE 27 Introduction
- Embankment Raised fill platform with
side slopes to support structure and infrastructure developments.
- Stage construction + additional
reinforcement Ensure acceptable side slope stability
- Basal reinforcement To minimise
spreading failure of compacted embankment fill over weak supporting subsoils
SLIDE 28 Basal Reinforcement
- Shall be designed in accordance with
BS8006.
- Consideration Strain compatibility
between embankment fill and basal reinforcement system.
- Tensile strain in basal reinforcement shall be
controlled to avoid cracking in embankment fill.
SLIDE 29 Basal Reinforcement
- If the embankment is strained to excessive
tensile crack, the embankment fill material strength is doubtful.
- Thus, case study of an instrumented
embankment construction with extendible basal reinforcement have been used.
- This may call for a review of the permissible
strain of extendible basal reinforcement with brittle compacted fill.
SLIDE 30 Problem Statement & Distresses
Problem Statements
Embankment Fill over Soft Deposits PVD with Staged Construction Basal Reinforcement for T
emporary Embankment Stability
BS8006 Strain Incompatibility
Distresses
Longitudinal flexural cracks on embankment surface
SLIDE 31 Embankment Distresses
Cracks locations of distressed embankment Crack line observed.
SLIDE 32
Embankment Distresses
SLIDE 33 Embankment Distresses
Alligator cracks
SLIDE 34 Embankment Distresses
1m surcharge removal after distresses observed
SLIDE 35 Embankment Distresses
Cracks found after 1m surcharge removal.
SLIDE 36 Embankment Distresses
Excavation on cracks found after 1m surcharge removal
SLIDE 37 Instrumentation Layout
Instrumentation Layout Plan at Distresses area
SLIDE 38 Instrumentation Results
Fill Thickness and Settlement of Embankment with time monitoring by SG580
SLIDE 39 Instrumentation Results
Inclinometer I6 Monitoring Results R1 S2 R2
SLIDE 40 Finite Element Model
Backfill material Drainage Blanket Basal Reinforcement Installed PVD Soft Clay Layer
SLIDE 41
Finite Element Model
Back analysis to match lateral deformation and settlement profiles. Two cases were modelled for back analysis:- Case 1: Ultimate strength (600kN/m) mobilized at 10% Case 2: Ultimate strength (140kN/m) mobilized at 1%
SLIDE 42 Finite Element Model
Comparison of Back Analysed Settlement Trend With Actual Measurement (Case 1)
SLIDE 43 Finite Element Model
Comparison of Lateral Displacement Profile (Case 1) R1 S2 R2
SLIDE 44 Summary of Back Analyses
Stage T ensile Stiffness Mobilised T ensile Load / T ensile Strain Maximum Lateral Deflection at Edge of Embankment (mm) S1 Case 1 Case 2 40.6kN/m / 0.68% 65.9kN/m / 0.47% 267 (173) R1 Case 1 Case 2 41.8kN/m / 0.70% 67.4kN/m / 0.48% 295 (180) S2 Case 1 Case 2 64.6kN/m / 1.08% 106.8kN/m / 0.76% 400 (253) R2 Case 1 Case 2 67.4kN/m / 1.12% 110.3kN/m / 0.79% 425 (265)
SLIDE 45
Probable Mechanism
SLIDE 46 Discussion
Strain incompatibility between basal reinforcement
and embankment fill could potentially cause embankment cracking.
Average tensile strain of underlying weak subsoils is
more than max. tensile strain in basal reinforcement.
Results of back-analysis indicated mobilised tensile
strength and strain < conventional assumed values for LEA stability analysis.
SLIDE 47 Conclusion
Longitudinal cracks Outcome of plastic straining
- f upper weak alluvium within the underlying subsoil
below the embankment loading.
Review on current design practice by arbitrarily
adopting unrealistic high mobilised strength is needed.
Wishful high tensile strain assumed in LEA can lead to
misrepresentation on safety margin of embankment.
SLIDE 48 Recommendations
Counterweight berm was proposed to solve the
strain incompatibility between basal reinforcement and the subsoil.
Instrument on basal reinforcement to reveal the
distribution profile and performance of installed basal reinforcement.
SLIDE 49 Case 2: Case study on Piled Supported Embankment Failure
49
SLIDE 50 P3 P2 P1 P
A Abutment A Abutment B Pier P1 Pier P2 Piled Embankment PVD + EVD Area
P
A Lower Firm Stratum
Filled Working Platform
Upper Weak Soil EVD PVD
Site Conditions
Embankment (maximum 5.4m high) with Piles & Ground
Improvements
Ch3328 to Ch3375 (Top 10m soft Clay, Su = 10~15kPa)
Distressed Abutment
Abutment A @ Ch3266 (Top 15m soft Clay, Su = 13~18kPa) Abutment B @ Ch3328 (Top 9m soft Clay, Su = 7~12kPa)
50
SLIDE 51 Findings from Site Inspection
Piles & slab of piled embankment suffered structural distress Settlement of 0.4 to1.0m beneath piled embankment due to
consolidation of subsoils under the working filled platform.
Bearing distortions confirmed : Bridge deck moving from
Abutment B towards Abutment A
51
SLIDE 52 Site Inspection Findings
Piled Embankment 30m from Abutment B shown structural
distress
52
SLIDE 53 Site Inspections Findings
Piles of Piled Embankment has shown flexural cracks
53
SLIDE 54 Site Inspections Findings
Damaged piled embankment slab damaged & 100mm gap at
slab joint
54
SLIDE 55 Site Inspections Findings
Settlement of 0.4 to 1.0m under the Piled Embankment
55
SLIDE 56 Site Inspections Findings
Bearing distortion at Pier P2
56
SLIDE 57 Site Inspections Findings
Bearing distortion at Pier P1
57
SLIDE 58 P3 P2 P1 P
A
FOS
Abutment A Abutment B Pier P1 Pier P2 Piled Embankment PVD + EVD Area
P
A
PA : Active Earth Pressure P1 : Action/Reaction Force between Piled Embankment Slab & Abutment P2 : Ultimate Lateral Pile Group Capacity of Embankment Piles P3 : Mobilised Thrust on Stability Soil Mass with Corresponding FOS
Lower Firm Stratum
Filled Working Platform
Upper Weak Soil EVD PVD
58
SLIDE 59 Movement Direction
P3 P
A
FOS
Abutment A Abutment B Pier P1 Pier P2 Piled Embankment PVD + EVD Area
P
A
PA : Active Earth Pressure P1 : Action/Reaction Force between Piled Embankment Slab & Abutment P2 : Ultimate Lateral Pile Group Capacity of Embankment Piles P3 : Mobilised Thrust on Stability Soil Mass with Corresponding FOS Clockwise Rotation Anti-Clockwise Rotation Developing Pile Plastic Hinge
T ension Cracks
Bearing Distortion
P2 P1
Abutment B Pier P1 Abutment A Pier P2 EVD Area Piled Embankment
P
A + P1 A B C D E F Ch 3360 Ch 3307.42 Ch 3266.02 Ch 3286.72 Ch 3328.12 Deck 1 Deck 2 Deck 3 Displacement Markers (by LDC) : 02 Mar – 18 Jun 2006 1 2 3 4 5 6 7 8 8 10 11 12 13 14 15 16 18 19 Displacement Markers (by G&P) : 25 Apr – 7 May 2007 M1 M2 M3 M4 M5 M6 M13 M14 M7 M8 M9 M10 M12 M13 Settlement Markers (LDC) : 28 May -31 Jul 2005 PVD Area
59
SLIDE 60 Investigation Findings
Embankment (5.4m high)
Ch3375 : FOS 1.0 at Embankment on Ground Treatments Causation : Inadequate FOS => Embankment instability exerting
lateral stress to Piled Embankment on free standing piles due to subsoil consolidation
Distressed Abutment
Abutment B : Laterally pushed by unstable embankment behind
piled embankment
Abutment A & T
wo piers : Affected by lateral thrust from Abutment B (No observable distresses at the abutment pile foundation after exposure of piles)
60
SLIDE 61 Abutment Remedial Design
Abutment Distress (Ch3266 to Ch3328)
Remedial proposal : Isolation Gap
61
SLIDE 62 Conclusions
Weak post-treatment soil strength unable to support
embankment
Creep movement of weak subsoil beneath embankment
coupled with embankment instability due to low FOS
Further consolidation of weak overburden soil, the lateral
resistance of piled embankment in free standing pile conditions is weaken
Monitored bridge displacement confirmed pattern of lateral
movement of entire bridge & piled embankment
Structural damage on embankment piles was expected as
structural threshold has reached
Use of residual strength is needed for rectifying failed
embankment
62
SLIDE 63 Recommendations
Construct new embankment slab at least 1m below the
failed slab to prevent further consolidation settlement
Extend piled embankment for embankment fill higher than
2m & provide isolation gap at the slab/abutment interfaces
Use of higher strength RC pile for embankment piles Use of geotextile reinforcement to isolate embankment fill
from both abutments to reduce direct lateral earth pressure
63
SLIDE 64 Unreliable Facing Capacity of Soil Nailed Slope
- With intention of minimized earthwork cutting forming
any platform, soil nailed slope profile is normally steep
- Facing capacity has remarkable effect on Internal
Stability of steep soil nailed slope
- Volumetric swelling & shrinkage of soils with moisture
variation are realistic observation
- Moisture depletion after covering with shotcrete surface
results in volumetric shrinkage of slope soil face leaving air gap with separation of contact with shotcrete
- Mobilisation of face capacity in uncontacted slope
surface is unrealistic, thus giving incorrect safety margin
SLIDE 65
Volumetric Shrinkage of Exposed Soil
SLIDE 66
Gap below Shotcrete Surface with Depleting Moisture
SLIDE 67 Nail Force Diagram
Slip Surface S2 S1 TN TH fs,p Soil Nail fs,a
SLIDE 68 Case Study 1 : Reduced Empty Pre-bored Jack-in Pile Capacity in Meta-Sedimentary Formation
- Overview of pile installation & Performance
- Subsurface Information
- Contractually Scheduled MLT Results
- Additional MLT Results
- Investigation Findings
- Conclusions & Recommendations
SLIDE 69 Overview Foundation System
- 400mm RC square pile
- Pre-boring was deployed to
- Overcome intermittent hard layer
- Avoid shallow pile penetration
- Jack-in pile installed inside pre-bored hole
SLIDE 70 Pre-bored Hole Diameter
600mm diameter 500mm diameter 550mm diameter Too large pre-bored hole Too small pre-bored hole Compromised pre- bored hole
(Adopted)
Pre-bored hole 400mm dia. RC Pile
SLIDE 71
Void in Pre-bored Hole Annulus
SLIDE 72
Collapsed Debris in Pre-bored Hole Annulus
SLIDE 73 Actual Scenario of Installed Piles
L – Pre-bored Length P – Actual Penetration Length P = L P > L P >> L 9m deep prebored
SLIDE 74 MLT Results
Maintained Load Test (MLT) Pre-bored Diameter (mm) Pile Penetration below Piling Platform (m)
Load at Termination (kN) Achieved Maximum Test Load (kN) Pile Top Settlement At Working Load (mm) At Max. Test Load (mm) MLT 1 600 9.40 2160 2220 (1.71xWL) 14.0 46.00 MLT 2 500 9.30 2600 2220 (1.71xWL) 23.50 42.00 MLT 3 550 12.50 2860 2600 (2.00xWL) 5.80 21.80 MLT 4 550 9.50 2860 1406 (1.50xWL) 16.50 24.50 MLT 5 550 13.50 2860 1950 (1.50xWL) 8.50 13.00
SLIDE 75 Jack-in Pile Termination Criteria
- All piles were jacked to 2.2 times pile working load
- Settlement < 5mm during 30 seconds holding
period for 2 consecutive times
SLIDE 76 Boreholes Information
SPT-N>50
Piling Platform End of Pre- bored 9m Pre- bored
SLIDE 77
Photos of Exposed Subsoils
SLIDE 78
Contractually Scheduled MLT Results
SLIDE 79 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m
MLT 1
SLIDE 80 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m
MLT 1 MLT 2
SLIDE 81 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m
MLT 1 MLT 2 MLT 3
SLIDE 82 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m
MLT 1 MLT 2 MLT 3 MLT 4
SLIDE 83 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m
MLT 1 MLT 2 MLT 3 MLT 4 MLT 5
SLIDE 84 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 1 - 9.4m MLT 2 - 9.3m MLT 3 - 12.5m MLT 4 - 9.5m MLT 5 - 13.5m
MLT3 & MLT5: Longer Pile Penetration below pre- bored base performs better
SLIDE 85
Additional MLT Results
SLIDE 86 Additional MLT
- 3 nos additional MLT at various penetration below pre-
bored base:
- MLT6 – 0.5m below pre-bored base
- MLT7 – 1.5m below pre-bored base
- MLT8 – 2.0m below pre-bored base
SLIDE 87
Additional MLT
SLIDE 88 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 6 - 9.5m MLT 7 - 10.5m MLT 8 - 11.0m
MLT 6
SLIDE 89 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 6 - 9.5m MLT 7 - 10.5m MLT 8 - 11.0m
MLT 6 MLT 7
SLIDE 90 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 PILE TOP SETTLEMENT (mm) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 PILE TOP LOADING (kN) 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 Legend MLT 6 - 9.5m MLT 7 - 10.5m MLT 8 - 11.0m
MLT 6 MLT 8 MLT 7
SLIDE 91 MLT Pre-bored Diameter (mm) Pile Penetration below Piling Platform (m)
Load at Termination (kN) Achieved Maximum Test Load (kN) Pile Top Settlement At Working Load (mm) At Max. Test Load (mm) MLT 1 600 9.40 2160 2220 (1.71xWL) 14.0 46.00 MLT 2 500 9.30 2600 2220 (1.71xWL) 23.50 42.00 MLT 3 550 12.50 2860 2600 (2.00xWL) 5.80 21.80 MLT 4 550 9.50 2860 1406 (1.50xWL) 16.50 24.50 MLT 5 550 13.50 2860 1950 (1.50xWL) 8.50 13.00 MLT 6 550 9.50 2860 1950 (1.50xWL) 15.08 42.38 MLT 7 550 10.50 2860 2400 (1.85xWL) 11.29 41.93 MLT 8 550 11.00 2860 2600 (2.00xWL) 10.30 50.35
SLIDE 92 Pre-bored Penetration below base of pre-bored
Investigation Findings
SLIDE 93
Analogy of Footing
SLIDE 94
Bearing Improvement with Toe Confinement
SLIDE 95 Conclusions & Recommendations
- Pile performance improved with longer
pile penetration below pre-bored base
- Existence of pile toe softening due to
relaxation of pile tip founding material
- Sufficient pile penetration below pre-
bored base is important
to seal the pre-bored hole with grout
SLIDE 96 Case Study 2: Pile Heave & Lateral Soil Displacement
Rapid pile installation in incompressible soft soil induces
Vertical heave in shallow depth (relatively less confinement from weight of
Lateral displacement in deeper depth (with soil confinement)
Consequences :
Up-heaving soil movement causes tensile stress on pile & toe lift up during driving &
downdrag after pore presure dissipation
Lateral soil displacement causes flexural stress on pile & pile deviation Excessive combined tensile and flexural stresses lead to pile joint dislodgement Excessive foundation settlement in post construction (pile toe uplifting & downdrag
settlement)
SLIDE 97 Pile Joint Dislodgement
Pile joints could be dislodged due to excessive flexural and tensile stresses
induced by ground heave and radial soil displacement
Detectable using High Strain Dynamic Pile T
est (HSDPT)
SLIDE 98 Mechanism of Pile Heave & Soil Displacement
SLIDE 99 Case Study - HSDPT
Monitoring of pile top settlement during the HSDPT re-strike tests is
summarised as below:
Cumulative Pile T
Settlement (mm) Pile C Pile A Pile B Pile D Pile E Upon resting 7-ton hammer on pile top 80 98 125 103 92 At the end of Restriking Test 275 399 497 186 182
SLIDE 100 Case Study - HSDPT
Pile B Initial Blow One Pile Length (12m) was DETECTED with Major Discontinuity at ‘toe’ (reflection)
SLIDE 101 Case Study - HSDPT
Pile B Blow No. 4 First Joint Discontinuity closed up after few blows; Two Pile Lengths was revealed with another Major Discontinuity at new ‘toe’ (reflection)
SLIDE 102 Case Study - HSDPT
Pile B Blow No. 17 Second Major Joint Discontinuity also disappeared; Total of Three Pile Lengths was observed
SLIDE 103 Case Study - HSDPT
Pile B End of Blow Minor velocity reflections were
second pile joints
SLIDE 104 Pile Heave Monitoring Program
X Y Z
SLIDE 105 Pile Heave Monitoring Result
5 10 15 20 25 30 1 2 3 4 5 6 7 8 9 10 11 12 Measured Pile Heave (mm) Pile Installation in Sequence Pile No.1 Pile No.3 Pile No.4 Pile No.5 Pile No.6 Pile No.7 Pile No.8 Pile No.9 Pile No.10 Pile No.11 Pile No.12
SLIDE 106 Summary
Ground heave & radial soil displacement due to rapid installation of
displacement pile in soft incompressible soft clay can pose serious integrity problem on pile foundation.
Solutions :
Use larger pile spacing & reduce rate of clustered pile installation for adequate time
for dissipation of excess pore pressure
Simultaneous pile installation at mirror pile location from centre outwards to
minimise net lateral displacement, but this improves nothing on ground heave
Stronger pile structural strength & joint to withstand tensile & flexural stresses Staggered pile installation sequence or install piles at alternate locations Restrike all piles with HSDPT to detect pile integrity if ground or soil heave is
SLIDE 107 Opportunities
- Identify problems and opportunities.
– State consumer problems, and define the nature of product/service opportunities that are created by those problems.
SLIDE 108 Business Concept
- Summarize the key technology, concept, or strategy on
which your business is based.
SLIDE 109 Competition
- Summarize the competition.
- Outline your company’s competitive advantage.
SLIDE 110 Goals and Objectives
- List five-year goals.
- State specific, measurable objectives for achieving your
five-year goals. – List market-share objectives. – List revenue/profitability objectives.
SLIDE 111 Financial Plan
- Outline a high-level financial plan that defines your
financial model and pricing assumptions. – This plan should include expected annual sales and profits for the next three years. – Use several slides to cover this material appropriately.
SLIDE 112 Resource Requirements
- List requirements for the following resources:
– Personnel – Technology – Finances – Distribution – Promotion – Products – Services
SLIDE 113 Risks and Rewards
- Summarize the risks of the proposed project and how
they will be addressed.
- Estimate expected rewards, particularly if you are
seeking funding.
SLIDE 114 Key Issues
– Identify key decisions and issues that need immediate or near-term resolution. – State consequences of decision postponement.
– Identify issues needing long-term resolution. – State consequences of decision postponement.
- If you are seeking funding, be specific about any issues
that require financial resources for resolution.