COLUMBIA LOCK AND DAM PROJECT INFORMATION OUACHITA-BLACK RIVER 237 - - PowerPoint PPT Presentation

columbia lock and dam project information ouachita black
SMART_READER_LITE
LIVE PREVIEW

COLUMBIA LOCK AND DAM PROJECT INFORMATION OUACHITA-BLACK RIVER 237 - - PowerPoint PPT Presentation

1 2 COLUMBIA LOCK AND DAM PROJECT INFORMATION OUACHITA-BLACK RIVER 237 217 200 80 252 237 217 200 119 174 237 217 200 27 .59 N 255 0 163 131 239 110 112 62 102 130 255 0 163 132 65 135 92 102 56 120 255 0


slide-1
SLIDE 1

217 217 217 200 200 200 255 255 255 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130 120 111 237 237 237 80 119 27 252 174 .59

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an

  • fficial Department of the Army position, policy or decision,

unless so designated by other official documentation.”

Ryan Reves, P.E. Dam Safety Program Manager Vicksburg District

COLUMBIA LOCK AND DAM OUACHITA-BLACK RIVER

1

PROJECT INFORMATION

2

N PROJECT INFORMATION

3

N PROJECT INFORMATION

4

N

slide-2
SLIDE 2

PROJECT INFORMATION

5

N Flow

  • Lock width: 84 ft.
  • Useable length: 600 ft.
  • Provides 18 ft. of lift
  • Normal upper pool elevation is 52.0 ft. (NGVD)
  • Normal lower pool elevation is 34.0 ft. (NGVD)

2015 ISSUES

6

Entry Entry Sand Boil Sand Boil Upper Miter Gate

  • Issue first discovered

November 2015.

  • Lock master saw a plume of

material inside the lock chamber.

  • Performed multi-beam survey
  • f the project.
  • Lock closed to navigation for

repairs

2015 ISSUES

7

  • Temporary repair designed, installed, and completed

by December 2015 allowing navigation to continue.

  • District budgeted and requested funds to design a

permanent repair.

  • Request included funds for:
  • Seepage study
  • Drilling / installation of relief wells

2018 MULTI-BEAM SURVEYS

8

  • Multi-beam survey taken

at end of January 2018 revealed the issue has migrated.

  • Received funds to design

repair

  • Performed seepage study

in February/March.

slide-3
SLIDE 3

EXPLORATORY DRILLING

9

  • Seepage study is completed.
  • June 2018 Incorporating findings from study,

preparing to perform exploratory drilling in advance of installing relief wells.

PROJECT INFORMATION

10

Lock cross-section

  • These voids are not supposed to be here.
  • Completely changed our understanding of

the progression of the situation.

DS SAND BOIL

11

Sand Boil DS Miter Gate

  • It is now obvious that the situation is not

constrained to within the lock chamber only.

  • Issue can no longer be managed by

manipulation of the chamber pool.

PROBING DS SAND BOIL

12

Downstream approach slab

DS Miter Gate

View looking upstream

  • Approx. 5ft void
  • Declared Dam Safety Emergency

in July 2018, closed off navigation, and lowered upper pool.

  • Immediately began designing

emergency repair and developing P&S.

  • Tabletop meeting held in July with

surrounding communities, ORVA, industry, and local stakeholders to communicate the issue and impacts.

slide-4
SLIDE 4

ISSUES / REPAIRS

13

Sheet pile cutoff wall Cored grout holes Entry hole and void Sheet pile cutoff wall Cored grout holes used to inject grout / tremie concrete Entry hole and void

  • Sand Boils
  • Voids Under Wall
  • Void in Chamber Floor
  • Exploratory Drilling
  • Sheet Pile
  • Coring
  • Grouting / Tremie Concrete
  • Relief Wells
  • Floor Repair

FINDING A CONTRACTOR

14

  • Market research identified 6 technically capable contractors.
  • Many of the prime contractors were not interested in the work due to:
  • Complexity of work
  • Uncertainty of work in underwater conditions
  • Need for a quick turn-around to open project back for navigation
  • Engineering During Construction (EDC) flexibility to modify plans/specs in the

midst of changing conditions

  • Massman Construction Co. won the bid as the general contractor

CURRENT STATUS

15

  • Area 1 (Upstream Approach Slab)
  • COMPLETE
  • Sheet Pile Installed
  • Slab drilled
  • Grout placed
  • Area 2 (Upstream Poiree/Gate Sill)
  • COMPLETE
  • Holes drilled
  • Grout placed
  • Area 3 (Landside Lock Wall)
  • Relief wells installed
  • Laterals to be installed
  • Holes drilled and grouted
  • Handful of heel holes to completed
  • Area 4 (Downstream Poiree/Gate Sill)
  • Holes drilled
  • Some grout work remaining
  • Area 6 (Lock Floor)
  • Pending modification
  • Area 5 (Downstream Approach Slab)
  • Holes drilled
  • Some grout work remaining
  • Seal joint between slab and sill
  • Area 7 (Riverside Lock Wall)
  • COMPLETE
  • Exploratory drilling complete
  • No voids found
  • Area 8 (Tainter Gate #1)
  • Scour hole repairs delayed by

river stages

WHEN WILL IT BE COMPLETE?

16

  • End of April is targeted for completion.
  • High river could push completion in early to mid May.
  • Final grout quantities and lock floor repairs will drive final

completion date.

  • Relief well lateral drain installation and repair in front of

tainter gate are water level dependent.

WHEN WILL PROJECT BE OPEN?

  • Opening for navigation could be as early as end of May.
  • Drain installation and repair in front of tainter gate not

expected to delay opening the project.