clermont works during the april expert week cern 2014
play

Clermont works during the April expert week CERN (2014 April - PowerPoint PPT Presentation

Clermont works during the April expert week CERN (2014 April 14-15) Romeo Bonnefoy and Franois Vazeille Deported HV system: Implementation in the Building 175 Mechanics: Comments Next expert week ? 1 Deported HV system


  1. Clermont works during the April expert week CERN (2014 April 14-15) Romeo Bonnefoy and François Vazeille ● Deported HV system: Implementation in the Building 175 ● Mechanics: Comments ● Next expert week ? 1

  2. Deported HV system ● Implementation in the Building 175 HV Module HV Bus boards bus area and HV cables 4 Short HV cables 4 4 Long Round HV cables Connectors HV Crate HV HV DCS Prague Crate Electronics room 2

  3. Present option for the tests 3

  4. Prague HV Power Supply in Building 175 HV output #16 4

  5. DCS monitoring in Building 175 5

  6. 2 wrong channels  Bad round connector mounting - OK with  meter test. - Not OK with HV test  Short circuit destroying the 2 Zener diodes (channels 12, 24) of Opto card by using the Clermont-Fd HV Power Supply (and not the Prague HV). Too hard Clamping on Short cable #2  HV crate back to Clermont-Ferrand for repairs !  Improvement of the connector mounting.  System fully operational for the next tests with the Chicago/Stockholm readout for the investigation of noise levels with 20 m and 100 m long cables. 6

  7. ● Other comments ▪ Clermont- Fd making of a “load system” easy to connect replacing missing Mini-Drawers (1 to 4) in order to suppress the “under current protection" of the HV Prague source. ▪ Two additional difficulties to solve - Center-to-center distance in between the HV Bus fixation holes. 78 mm HV Bus card □ 78 mm on the Clermont-Ferrand drawings (given more than 1 year ago.) □ 80 mm on the Barcelona drawings and Mini-Drawers. - Present Patch Panel, not only too big for the Clermont-Fd Slider, but not enough space to slip the connectors through its hole  To machine holes close to the edge as foreseen by Clermont-Fd. 7

  8. Comments on mechanics ● Barcelona Patch Panel and Service tools not compatible with Clermont-Fd tools (Not new today!). ● No bearing screw on the Barcelona Slider  Strength fully on the Girder Rings Strongly screwed Clermont-Ferrand proposition (Several times explained) 8

  9. Next expert week ● New delivery of the deported HV system ready to work, supposing Patch Panel difficulties overcame ● Participation to the readout tests using this HV system, with comparisons with 20 m long and 100 m long cables, and also with the other system. ● Discussions strongly expected (before) about the mechanics. 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend