clean room and lock system status report and
play

Clean Room and Lock System Status report and 1 Bla Majorovits - PowerPoint PPT Presentation

GERDA Collaboration meeting, LNGS March 1-3, 2010 Clean Room and Lock System Status report and 1 Bla Majorovits GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Commissioning lock was fully mounted on 13 th of January


  1. GERDA Collaboration meeting, LNGS March 1-3, 2010 Clean Room and Lock System Status report and 1 Béla Majorovits

  2. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Commissioning lock was fully mounted on 13 th of January 2010 2 Béla Majorovits

  3. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Tests of cable behavior started immediately. Test volume flushed with dry nitrogen gas. Measured Class 1.000 surrounding 3 Béla Majorovits

  4. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock After few cycles cables started moving out from cable chain. At mounting cables had not been tightened much � Cable rearranged during movement and were damaged, partly at sharp edges of cable chain 4 Béla Majorovits

  5. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Bolt to keep cables from sharp edges during bending process Did complete remount (including laser welding to matrix). Introduced bolts to keep cables from sharp edges. Tightened cables properly. � Commissioning lock back on hoist on 12 th of February 5 Béla Majorovits

  6. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Let done cable chain on 15 th of February. Cable chain not straight. Cables started moving out of chain anyway 6 Béla Majorovits

  7. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock After one cycle: Two broken cables, many scratched. The system had been cycled 20 times before without seeing this problem. However, no bolts and half the amount of cables was installed. 7 Béla Majorovits

  8. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Conclusion: Actions taken: • The amount of cables was too high 1. Remove half the cables. Bypass • The bolts are counterproductive with cables only! respect of functionality of the cable 2. Chamfer sharp edges chain 3. Bundle cables in spiral coiled tube • The edges of the cable chain are too 4. Leave loop before strain relief sharp 8 Béla Majorovits

  9. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Actions Taken: 2 * 15 Habia signal cables in PTFE spiral coiled tubes • 20 LN cycles with subsequent 10 bending cycles each without bolts • 10 bending cycles with bolts 9 Béla Majorovits

  10. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock � Damage of PTFE piral coiled tube � Movement of spiral coiled tube � Winding of bundles 10 Béla Majorovits

  11. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Actions Taken: Removed sharp edges of cable segments 11 Béla Majorovits

  12. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Actions Taken: Redesigned bolts � Cable bundles can freely move inside cable chain 12 Béla Majorovits

  13. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Actions Taken: Redesigned strain relief 13 Béla Majorovits

  14. GERDA Collaboration meeting, LNGS March 1-3, 2010 Commissioning Lock Actions Taken: - Redesign bolts for cable chain (Until Mid CW8) - Redesign strain relief for cable bundle (Until end of CW8) - Remount cable chain (until end of CW8) - Redesign strain relief - Produce strain relief for cable bundles inside spiral coiled tube (Beginning of CW9). - Remount lock (CW9) - Testing newly mounted lock (CW10) - Shipment to LNSG CW11 - Test Spiral coiled tube to mount 30 Habia cables and 10 HV cables (end of CW8) - For 3 string arm two bundles will be used. They will be separated by additional guide laser welded to individual segments 14 Béla Majorovits

  15. GERDA Collaboration meeting, LNGS March 1-3, 2010 Clean Room Status Clean room has been cleaned. Not perfect, but please respect clean room rules from now on. � Presentation, Discussion and training of rules on Wednesday 15 Béla Majorovits

  16. GERDA Collaboration meeting, LNGS March 1-3, 2010 Clean Room Status Clean room Monitor is online. Please note: not the final IP address yet! Still to be implemented: Particle counter http://134.107.13.198:6666 16 Béla Majorovits

  17. GERDA Collaboration meeting, LNGS March 1-3, 2010 Clean Room Status Mounting of external gas and vacuum supply is going to be mounted by Linde. Will be finished CW10 (?). 17 Béla Majorovits

  18. GERDA Collaboration meeting, LNGS March 1-3, 2010 Clean Room Status Mounting of internal gas system starts tomorrow. Finished by CW 10 18 Béla Majorovits

  19. GERDA Collaboration meeting, LNGS March 1-3, 2010 Conclusions: • Commissioning Lock will hopefully installed this month start after loads of trouble. • Infrastructure close to being complete. • Before its getting boring, we will start installing the final lock. Cylinder is on its way 19 Béla Majorovits

  20. GERDA Collaboration meeting, LNGS March 1-3, 2010 Conclusions: • Commissioning Lock will hopefully installed this month start after loads of trouble. • Infrastructure close to being complete. • Before its getting boring, we will start installing the final lock. Cylinder is on its way 20 Béla Majorovits

  21. 4) electropolished cable chain segments: 5um 10um abrasion GERDA Collaboration meeting, LNGS March 1-3, 2010 5) Received protective PTFE spiral coiled tube for cable bundle a) Hellerman Tyton 4mm inner diameter 5m length b) EAP 4.5mm inner diameter 10m length 6) Tested spiral coiled tube: Two spiral coiled tubes with 15 Habia cables each were inserted into a 2m long cable chain segment that had not been chamfered. The Cable bundles were strain reliefed on one side of the cable chain. The second one was left open. One of the bundles was made out of two 1m pieces of spiral coiled tube. a) 20 LN cooldown cycles, after each cooldown 10 bending cycles at close to LN tempteratur --> No damage observed --> Winding of the two spiral coil tubes --> Spiral coiled tube increased its length on the not strain reliefed side on one of the cable bundles b) Inserted bolts each 7th segment pressing the spiral coiled tubes with Habia cables onto the sharp edge of the cable chain Did 20 bending cycles --> Scraping on the PTFE spiral coiled tube --> No damage on the Habia cables 21 Béla Majorovits

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend