City of Toronto Tower Renewal Program CAIC Presentation September 7, 2016 Photo by Jesse Colin Jackson 1 Tower Renewal A program to drive broad environmental, social, economic, and cultural change by improving Torontos concrete


slide-1
SLIDE 1

City of Toronto Tower Renewal Program

CAIC Presentation – September 7, 2016

1

Photo by Jesse Colin Jackson

slide-2
SLIDE 2

2

A program to drive broad environmental, social, economic, and cultural change by improving Toronto’s concrete apartment towers and the neighbourhoods that surround them.

Tower Renewal

slide-3
SLIDE 3

3

Inefficient buildings State

  • f good repair

Underused space Lack of services

Photo by Jesse Colin Jackson

Challenges

slide-4
SLIDE 4

4 Photo by Jesse Colin Jackson

Invested people Solid structures Significant change possible Affordable

  • ption

Opportunities

slide-5
SLIDE 5

5

48%

Towers Across Toronto

slide-6
SLIDE 6

6

Revitalization?

slide-7
SLIDE 7

7

Efficiency, Conservation , Renewables and Diversion

Improving Performance

slide-8
SLIDE 8

Benchmarking

STEP

Site assessment Action planning

Site Focused Support

slide-9
SLIDE 9
  • Pay for improvements over time

using savings to offset costs

  • Low, fixed interest rates and

longer payment terms

  • Payments via the property tax bill
  • Access to utility incentives
  • Pilot ends December 2016

Hi-RIS Financing

Low Interest Loans for Energy Retrofits

Save Money. Save Energy. Renew.

slide-10
SLIDE 10

Window and Balcony Door Replacement Results:

  • over 90% of financing costs offset by savings
  • Energy consumption savings: 25%+
  • Improved overall building value
  • Improved building condition & aesthetics
  • Improved resident comfort & tenant retention

Hi-RIS Financing

slide-11
SLIDE 11

11

Beautification, Gathering Areas, Social Supports, Complaint Response

Improving Quality of Place

slide-12
SLIDE 12

San Romanoway Revitalization

slide-13
SLIDE 13

Master Plan

San Romanoway Outdoor Revitalization

slide-14
SLIDE 14

RAC Zoning

Commercial and Community Uses

  • n Ground Floor and Outside
slide-15
SLIDE 15

15

Revitalization?

  • … Holistic
  • … Cost saving
  • … Value enhancing
slide-16
SLIDE 16

16

www.toronto.ca/tower_renewal

Follow us on Twitter @TOTower_Renewal Like us on Facebook

Aderonke Akande Project Manager aakande@toronto.ca