CITY COUNTY DRAIN FLOOD MITIGATION PROJECT OUTLINE 1 What - - PowerPoint PPT Presentation

city county drain flood mitigation project outline
SMART_READER_LITE
LIVE PREVIEW

CITY COUNTY DRAIN FLOOD MITIGATION PROJECT OUTLINE 1 What - - PowerPoint PPT Presentation

CITY COUNTY DRAIN FLOOD MITIGATION PROJECT OUTLINE 1 What Happened in 2018? 2 Overview of the Project 3 Challenges 4 Solutions 5 Construction Photos 2 Project Area Downtown Billings City County Drain CCD Project Area South Billings


slide-1
SLIDE 1

CITY COUNTY DRAIN FLOOD MITIGATION PROJECT

slide-2
SLIDE 2

OUTLINE

2

1 What Happened in 2018? 2 Overview of the Project 3 Challenges 4 Solutions 5 Construction Photos

slide-3
SLIDE 3

3

Project Area

City County Drain

King Avenue Interchange South Billings Boulevard Interchange CCD Project Area Downtown Billings

slide-4
SLIDE 4
  • Significant Runoff in the Yellowstone River

− Prolonged flows greater than 40,000 cfs (2-Year) − Erosion along the North Bank of the River

  • Intense Rainstorm Occurring in Billings

− Significant flows down City County Drain

What Happened in 2018?

4

slide-5
SLIDE 5

5

2018 Conditions 2019 Conditions

slide-6
SLIDE 6

6

Abrupt Change in Backwater Conditions

City County Drain 2123.52 2131.02 2133.28 7.5’ 2.3’ Island Provides 2-Year Protection Bank Provides 10-Year Protection

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

Challenges

9

1 Schedule – Provide Protection By Spring 2019 2 Conflicting Objectives A Prevent Backwater from Yellowstone River B Maintain Capacity in CCD for Storm Runoff

slide-10
SLIDE 10

Alternative #1

10

NOT SELECTED

  • Right of Way Costs
  • Schedule
  • Grey Eagle Ditch

Crossing

Reconstruct New Drainage Ditch

slide-11
SLIDE 11

Alternative #2

11

NOT SELECTED

  • Cost
  • Schedule
  • Limited Room

New RCB Storm Drain

slide-12
SLIDE 12

Recommended Solution

12

Flood Control Gate Inlet Structure

slide-13
SLIDE 13
  • Typical Design-Bid-Build Contract would not have met the schedule
  • City of Billings requested proposals from Construction Contractors

− COP Construction was selected

  • Benefits

− COP Construction provided Value Engineering recommendations for 30% Design − Early procurement of pipe allowed construction to begin before final design was completed − Contractor paid T&M plus an agreed-upon markup, with a maximum guaranteed price. − Allowed for efficient processing of minor field changes.

Accelerate Schedule

13

Construction Manager / General Contractor Contract (CMGC)

slide-14
SLIDE 14
  • All permits were in hand for February 2019 Start

− 2nd Coldest February in Billings History − 29.4” of Snow (3rd Snowiest February in Billings)

  • Construction

− 4,250 LF 48” RCP Pipeline

− Started 3-4-2019 and finished 4-15-2019

− Crest Gate Installed on 7-16-2019 (temporary sheet piling for water control) − Project Completed on 8-15-2019

Construction

14

slide-15
SLIDE 15

48-inch RCP Pipeline

slide-16
SLIDE 16

Yellowstone Outlet Structure

slide-17
SLIDE 17

Pipeline Inlet Structure

slide-18
SLIDE 18

Fish Bypass

slide-19
SLIDE 19

Flood Control Crest Gate

slide-20
SLIDE 20

Gate Automation

slide-21
SLIDE 21

Gate Automation – Typical Position

Yellowstone River WSEL Baseflow in CCD Through 48-inch Pipe

slide-22
SLIDE 22

Gate Automation – Runoff From CCD

Yellowstone River WSEL Baseflow Gate Lays Down Providing additional flow capacity for stormwater runoff

slide-23
SLIDE 23

Gate Automation – Return to Typical Position

Yellowstone River WSEL Baseflow in CCD Through 48-inch Pipe

slide-24
SLIDE 24

24

Frozen Ground & Compaction

slide-25
SLIDE 25

25

Groundwater

slide-26
SLIDE 26

26

Backwater from Yellowstone River

slide-27
SLIDE 27

27

City County Drain Stormwater Flows

slide-28
SLIDE 28
  • Protected Upstream Residence from 2019 Runoff Condition
  • Project came within the $2.85 million budget
  • Gate Automation Provided Limited Work for the City Maintenance Staff

Project is Completed

28

slide-29
SLIDE 29

29

Questions?