CITY COUNTY DRAIN FLOOD MITIGATION PROJECT OUTLINE 1 What - - PowerPoint PPT Presentation
CITY COUNTY DRAIN FLOOD MITIGATION PROJECT OUTLINE 1 What - - PowerPoint PPT Presentation
CITY COUNTY DRAIN FLOOD MITIGATION PROJECT OUTLINE 1 What Happened in 2018? 2 Overview of the Project 3 Challenges 4 Solutions 5 Construction Photos 2 Project Area Downtown Billings City County Drain CCD Project Area South Billings
OUTLINE
2
1 What Happened in 2018? 2 Overview of the Project 3 Challenges 4 Solutions 5 Construction Photos
3
Project Area
City County Drain
King Avenue Interchange South Billings Boulevard Interchange CCD Project Area Downtown Billings
- Significant Runoff in the Yellowstone River
− Prolonged flows greater than 40,000 cfs (2-Year) − Erosion along the North Bank of the River
- Intense Rainstorm Occurring in Billings
− Significant flows down City County Drain
What Happened in 2018?
4
5
2018 Conditions 2019 Conditions
6
Abrupt Change in Backwater Conditions
City County Drain 2123.52 2131.02 2133.28 7.5’ 2.3’ Island Provides 2-Year Protection Bank Provides 10-Year Protection
7
8
Challenges
9
1 Schedule – Provide Protection By Spring 2019 2 Conflicting Objectives A Prevent Backwater from Yellowstone River B Maintain Capacity in CCD for Storm Runoff
Alternative #1
10
NOT SELECTED
- Right of Way Costs
- Schedule
- Grey Eagle Ditch
Crossing
Reconstruct New Drainage Ditch
Alternative #2
11
NOT SELECTED
- Cost
- Schedule
- Limited Room
New RCB Storm Drain
Recommended Solution
12
Flood Control Gate Inlet Structure
- Typical Design-Bid-Build Contract would not have met the schedule
- City of Billings requested proposals from Construction Contractors
− COP Construction was selected
- Benefits
− COP Construction provided Value Engineering recommendations for 30% Design − Early procurement of pipe allowed construction to begin before final design was completed − Contractor paid T&M plus an agreed-upon markup, with a maximum guaranteed price. − Allowed for efficient processing of minor field changes.
Accelerate Schedule
13
Construction Manager / General Contractor Contract (CMGC)
- All permits were in hand for February 2019 Start
− 2nd Coldest February in Billings History − 29.4” of Snow (3rd Snowiest February in Billings)
- Construction
− 4,250 LF 48” RCP Pipeline
− Started 3-4-2019 and finished 4-15-2019
− Crest Gate Installed on 7-16-2019 (temporary sheet piling for water control) − Project Completed on 8-15-2019
Construction
14
48-inch RCP Pipeline
Yellowstone Outlet Structure
Pipeline Inlet Structure
Fish Bypass
Flood Control Crest Gate
Gate Automation
Gate Automation – Typical Position
Yellowstone River WSEL Baseflow in CCD Through 48-inch Pipe
Gate Automation – Runoff From CCD
Yellowstone River WSEL Baseflow Gate Lays Down Providing additional flow capacity for stormwater runoff
Gate Automation – Return to Typical Position
Yellowstone River WSEL Baseflow in CCD Through 48-inch Pipe
24
Frozen Ground & Compaction
25
Groundwater
26
Backwater from Yellowstone River
27
City County Drain Stormwater Flows
- Protected Upstream Residence from 2019 Runoff Condition
- Project came within the $2.85 million budget
- Gate Automation Provided Limited Work for the City Maintenance Staff
Project is Completed
28
29