chris bason dr marianne walch delaware center for the
play

Chris Bason & Dr. Marianne Walch, Delaware Center for the Inland - PowerPoint PPT Presentation

Chris Bason & Dr. Marianne Walch, Delaware Center for the Inland Bays Presentation to CIB Board of Directors December 15, 2017 L. Assawoman Bay Nitrogen Load (lbs/day) 2,000 1,600 1,200 800 Goal 400 0 Create stormwater management


  1. Chris Bason & Dr. Marianne Walch, Delaware Center for the Inland Bays Presentation to CIB Board of Directors December 15, 2017

  2. L. Assawoman Bay Nitrogen Load (lbs/day) 2,000 1,600 1,200 800 Goal 400 0

  3. Create stormwater management facilities for 4,500 acres of urban and residential lands developed pre-1990 Stormwater Law. Center for Watershed Protection

  4. What Are Stormwater Retrofits? Stormwater retrofits are stormwater management practices in locations where stormwater controls did not previously exist or were ineffective

  5. ž Highly impervious drainage area (~50%), largest of all residential canals ž Receives runoff from storm drains under Rte. 1 ž High pollutant loads • 592 lbs N/yr • 33 lbs P/yr • First flush Coliforms 90,000- 800,000 units ž Highly eutrophic ž No MS4

  6. Anchorage Canal Surface Drainage Area & Communities Bethany Beach Sea Colony Middlesex Beach South Bethany Highway 1 (DelDOT Storm drain system outlet ) Anchorage Canal

  7. ž Installed in 2004 ž 16.5 yd 3 of sediment enter annually ž Initially 28% efficient at sediment capture Scarborough & Mensinger 2005 DNREC Coastal Programs Evaluation

  8. GOALS ž Reduce nutrient loads by 40% per TMDL ž Collaborative Demonstration ž Multiple benefits ž Cost Effective ž Coastal Aesthetic ž Consider climate change

  9. Native Maritime Shrubland

  10. ž Retrofit Scoping-Identify Objectives ž Desktop Analysis ž Retrofit Reconnaissance Investigation (RRI) ž Compile Retrofit Inventory ž Evaluation and Ranking ž Final Design and Construction

  11. Drainage Area Map View with Sites • Rapidly search for and identify potential retrofit sites across the subwatershed • Save time in the field

  12. • Purpose • Verify feasibility of candidate retrofit sites • Collect information • Key tasks • Evaluate potential retrofit sites, collect pertinent site information, and produce a basic concept design sketch Methodology developed by CWP

  13. ž 25 prioritized projects @ 30% design. ž Bioretention and infiltration focused. ž One keystone project. ž Dense development made finding space challenging. ž Maintenance schedule included. FUNDING: USACE Planning Assistance to the States Grant matched by the Center,Town of South Bethany, an DelDOT = $105,375 total.

  14. ž Treated 30 - 40 ac. of high rise condo facility ž Installed 19 parking lot curb cuts and infiltration pits ž Converted existing ditch to planted wet swale with roadside filter strips

  15. ž Converted existing ~1 mi. long ditch to wet swale with check dams and planted. ž Regraded along PA Ave. shoulder to provide filter strip. ž $190,913 total cost (cash + in-kind services)

  16. ž Exemplary vegetation maintenance by Sea Colony Condo Assoc. ž High plant diversity and habitat value • Fish • Turtles • Herons Widgeon grass: • Muskrats submerged aquatic ž No structural issues vegetation. ž Natural appreciation and education values 2015

  17. Note: closely mown road edge for aesthetics

  18. ž 33 highway bioretention areas treated ~20 ac. of highway and residential runoff. ž Utilized medians and ROWs. ž Conducted in two phases.

  19. Grade-all excavation was careful not to damage catch basins.

  20. On some medians we exposed a former wetland surface (inter-dunal swale) higher in organic matter.

  21. Six areas received bio-char amendment from 5 – 15%.

  22. ž Variable vegetation establishment and related sediment transport within areas ž Areas of bare, slightly eroding ground common flow ž Many established wetland conditions ž Typically drain within 48 hrs

  23. Typical vegetation coverage after five yrs.

  24. Median Bioretention Wetswale & Pits Source Amount Source Amount DNREC Grant $44,297 DNREC Grant $95,866 CIB $21,000 CIB $31,235 South Bethany $18185 Seacolony $21,000 Middlesex Beach $700 TOTAL CASH $148,101 DE Forest Service $30,000 LEVERAGED IN-KIND $42,812 TOTAL CASH $84,182 TOTAL $190,913 LEVERAGED IN-KIND $19,589 Lbs TP reduced 3.44 TOTAL $103,771 Lbs TN reduced 23.7 Lbs TP reduced 3.28 $/lb/TP over 30 yrs. $1,850 Lbs TN reduced 27.35 $/lb/TN over 30 yrs. $268 $/lb/TP over 30 yrs. $1054 $/lb/TN over 30 yrs. $126 Excludes maintenance costs $/lb calculated separately for TP and TN.

  25. ž Concept design for 12 facilities around residential catch basins. ž Individual drainages mapped ž 6 in-situ bioretention /infiltration trenches and 2 infiltration trenches selected for implementation ž 10 total acres treated • 15 lbs nitrogen removed • 2 lbs phosphorus removed • 452 lbs sediment removed

  26. Infiltration trench/bioretention area completed: 2016.

  27. Catch basin Infiltration trench/bioretention area completed: 2016.

  28. Sandpiper Pines Source Amount ž Excludes EPA Planning $35,000 maintenance Assistance ž Costs for nutrients DNREC Implementation $136,900 calculated separately Grant ž Extensive planning South Bethany Match $7,530 TOTAL CASH $179,430 and design + low LEVERAGED IN-KIND $10,441 efficiency of practice TOTAL $189,871 infiltration = low cost Lbs TP reduced 2 effectiveness Lbs TN reduced 15 $/lb/TP over 30 yrs. $3,165 $/lb/TN over 30 yrs. $421

  29. Wetland – Wetpond Demo Project Location Aerial

  30. ‘Slip-ramp’ highly used during summer by pedestrian and bi- cyclists that conflict with sometimes speeding autos.

  31. Sea Colony High Rise Complex Proposed Facility Area

  32. ž Treat 6.4 acres of high rise complex runoff. ž Part of existing treatment train ž Estimated removal of 25.6 lbs. of nitrogen and 4.6 lbs. of phosphorus ž Estimated cost of $500,000 funded 80% by DelDOT and 20% by SeaColony and CIB

  33. ž Micro-rain gardens around additional highway ROW catch basins ž Town of South Bethany ordinances • Ban on new outdoor showers draining to canals • Impervious surface ordinance ž Floating Filters Demonstration & Research Project in Canals • 100 floating cages with 2 bushels ea. of adult oysters • 10 floating treatment wetlands

  34. Town of Dewey Beach

  35. • Phase II Stormwater Master Plan completed August 2017. • Identifies/prioritizes retrofit opportunities.

  36. Read Ave. Living Shoreline Project

  37. Little Store Stormwater Retrofit

  38. ž Multiple benefits – hallmark of stormwater retrofits; non-water quality likely key. ž Like any mid-large scale effort, persistence and continuity of leadership pays off. ž Delaware’s Clean Water Revolving Fund (SRF) has been an essential funder: be and advocate for clean water funding!

  39. ž Plantings in coastal highway environments are expensive for install and maintenance, add little water quality benefit, and have mixed success for purpose. ž Expect nutrient reductions (and cost effectiveness) to decrease from concept to actual construction.

  40. 1000 $/lb. N removed 100 10 1 This Project Avg. Forested Buffer Wetland Restoration Weiland et al. 2009. Costs & Cost Efficiencies for some Nutrient Reduction Practices in MD.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend