Cherokee Regional Park Trail Connections and Ohio Street Lighting WSCO Voices Forum March 10, 2020 Brett Hussong brett.hussong@ci.stpaul.mn.us Trail Segment along Cherokee Boulevard (2007) Remove existing parking lot Replace with


slide-1
SLIDE 1

Cherokee Regional Park Trail Connections and Ohio Street Lighting

WSCO Voices Forum March 10, 2020 Brett Hussong brett.hussong@ci.stpaul.mn.us

slide-2
SLIDE 2

Cherokee Regional Trail

Current Trail Configuration

  • Remove existing parking lot
  • Replace with on-road parallel

parking

  • Install traffic calming measures in

conjunction with trail crossing

  • Bid Alternate to provide internal

trail connection to restrooms/drinking fountain

  • Bid Alternate to provide trail

connection along Annapolis Street

  • Future overlook connection to

Pickerel Lake

  • Future trail enhancement to

develop entrance gateway/signage at Annapolis and Cherokee Boulevard

Trail Segment along Cherokee Boulevard

Annapolis Street Chippewa Avenue

(2007) (2007)

slide-3
SLIDE 3

9 8 1 982 983 981

SCALE IN FEET NORTH 15' 30' 60'

Parks and Recreation 400 City Hall Annex 25 West 4th Street Saint Paul, MN 55102

PLAY AREA RESTROOM FACILITY

C H E R O K E E R E G I O N A L T R A I L

PROPOSED TRAIL ALIGNMENT

BASKETBALL COURT SERVICE ROUTE

SIDEWALK

SWING SET PICNIC SHELTER PICNIC SHELTER SWINGING BENCH

P R O P O S E D T R A I L A L I G N M E N T

PICNICKING AREA MATURE OAK TREES

PROPOSED BENCH PROPOSED BENCH

Tentative Schedule: Design Spring 2020 Bidding Summer 2020 Construction Fall 2020 (pending bids) Project Manager: Brett Hussong brett.hussong@ci.stpaul.mn.us Website: www.stpaul.gov/CherokeeTrailConnections Scope of Work: Construct an internal trail network to facilitate better connections between the regional trail and park features. Trail Features: Asphalt trail 8'-0" wide ADA accessible Site Furnishings Funding: Parks and Trail Legacy Funding $315,000 Design and Construction

slide-4
SLIDE 4

OHIO STREET - TRAIL LIGHTING

PROJECT PLAN

FEBRUARY 2020 LEGEND PROPOSED LIGHT LOCATION TYPICAL TRAIL LIGHT

*

PROJECT LOCATION

NORTH