CHAMPAIGN UNIT #4 INTERNATIONAL PREP ACADEMY Board of Education Meeting 12.09.19 Our Char Our Charge ge 3 Strand K-5 (Referendum Minimum) 3 Strand K-5 (+ HVAC/Windows) 3 Strand K-5 (+ HVAC/Windows/Facelift) Ideal 3 Strand K-5


  1. CHAMPAIGN UNIT #4 INTERNATIONAL PREP ACADEMY Board of Education Meeting 12.09.19

  2. Our Char Our Charge ge ▪ 3 Strand K-5 (Referendum Minimum) ▪ 3 Strand K-5 (+ HVAC/Windows) ▪ 3 Strand K-5 (+ HVAC/Windows/Facelift) ▪ Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) ▪ Ideal 4 Strand K-5 (Parity to Garden Hills) ▪ NEW Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) ▪ NEW Ideal 4 Strand K-5 (Parity to Garden Hills) ▪ 150 Student 6-8 Addition ▪ 225 Student 6-8 Addition

  3. Site Plan

  4. Opt 1: 3 Strand K-5 (Referendum Minimum) Cost: $6,710,000

  5. Opt 1: 3 Strand K-5 (Referendum Minimum) Cost: $6,710,000 INCLUDES • 10,000 sf of total additions • 3,500 sf gym • Renovation of admin/secure entry • Renovations of kitchen/dining areas • Renovation of existing toilet rooms • Addition of single user toilets at 1st • New corridor ceilings and lighting • Parking expansion on west side (25 cars) • Minimal technology FF&E at new/reno

  6. Opt 1: 3 Strand K-5 (Referendum Minimum) Cost: $6,710,000 DOES NOT INCLUDE • 7,800 sf of addition for program equity - $2,520,000 OTHER ITEMS • Larger gym (5,000 sf) - $500,000 • Abatement at classrooms - in others • Elimination of portable classrooms • New electrical system - $95,000 HVAC SYSTEMS • Replace exterior lighting - $10,000 • System upgrades (MEP) at classrooms - $2,425,000 • Restoration of existing roof - $410,000 • New windows - $590,000 • Tornado shelter - $385,000 FACELIFT • Future 6-8 electrical capacity - $70,000 • New interior doors & hardware - $135,000 • Full plumbing replacement - $325,000 • New casework at classrooms - $245,000 • Abatement at crawlspace - $105,000 • New paint/signage, etc. - $350,000 • Playground drainage - $65,000 • New flooring - $375,000 • Playground re-surfacing - $35,000 OTHER ITEMS • Bus drop off expansion on north side - $210,000 • New technology - $360,000 • 3 strand 6-8 addition (51,000 sf) • New furniture - $315,000 - $14M-$15.8M • Entry canopy - $135,000

  7. Opt 2: 3 Strand K-5 (+ HVAC/Windows) Cost: $9,890,000

  8. Opt 2: 3 Strand K-5 (+ HVAC/Windows) Cost: $9,890,000 INCLUDES • 10,000 sf of total additions • 3,500 sf gym • Renovation of admin/secure entry • Renovations of kitchen/dining areas • Renovation of existing toilet rooms • Addition of single user toilets at 1st • New corridor ceilings and lighting • Parking expansion on west side (25 cars) • Minimal technology FF&E at new/reno HVAC SYSTEMS • System upgrades (MEP) at classrooms • New windows

  9. Opt 2: 3 Strand K-5 (+ HVAC/Windows) Cost: $9,890,000 DOES NOT INCLUDE • 7,800 sf of addition for program equity - $2,520,000 • Larger gym (5,000 sf) - $500,000 • Elimination of portable classrooms FACELIFT OTHER ITEMS • Restoration of existing roof - $410,000 • New interior doors & hardware - $135,000 • Tornado shelter - $385,000 • New casework at classrooms - $245,000 • Future 6-8 electrical capacity - $70,000 • New paint/signage, etc. - $350,000 • New flooring - $375,000 • Full plumbing replacement - $325,000 OTHER ITEMS • Abatement at crawlspace - $105,000 • New technology - $360,000 • Playground drainage - $65,000 • Playground re-surfacing - $35,000 • New furniture - $315,000 • Bus drop off expansion on north side • Entry canopy - $135,000 - $210,000 • Abatement at classrooms - in others • 3 strand 6-8 addition (51,000 sf) • New electrical system - $95,000 - $14M-$15.8M • Replace exterior lighting - $10,000

  10. Opt 3: 3 Strand K-5 (+ HVAC/Windows/Facelift) Cost: $12,920,000

  11. Opt 3: 3 Strand K-5 (+ HVAC/Windows/Facelift) Cost: $12,920,000 INCLUDES • 10,000 sf of total additions FACELIFT • 3,500 sf gym • New interior doors & hardware • Renovation of admin/secure entry • New casework at classrooms • Renovations of kitchen/dining areas • New paint/signage, etc. • Renovation of existing toilet rooms • New flooring • Addition of single user toilets at 1st OTHER ITEMS • New corridor ceilings and lighting • New technology • Parking expansion on west side (25 cars) • New furniture HVAC SYSTEMS • Entry canopy • System upgrades (MEP) at classrooms • Abatement at classrooms - in others • New windows • New electrical system • Replace exterior lighting • Restoration of existing roof

  12. Opt 3: 3 Strand K-5 (+ HVAC/Windows/Facelift) Cost: $12,920,000 DOES NOT INCLUDE • 7,800 sf of addition for program equity - $2,520,000 • Larger gym (5,000 sf) - $500,000 • Elimination of portable classrooms • Tornado shelter - $385,000 • Future 6-8 electrical capacity - $70,000 • Full plumbing replacement - $325,000 • Abatement at crawlspace - $105,000 • Playground drainage - $65,000 • Playground re-surfacing - $35,000 • Bus drop off expansion on north side - $210,000 • 3 strand 6-8 addition (51,000 sf) - $14M-$15.8M

  13. Opt 4: Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) Cost: $15,050,000

  14. Opt 4: Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) Cost: $15,050,000 INCLUDES • Eliminates portables FACELIFT • 17,800 sf of total additions • New interior doors & hardware • 3,500 sf gym • New casework at classrooms • Renovation of admin/secure entry • New paint/signage, etc. • Renovations of kitchen/dining areas • New flooring • Renovation of existing toilet rooms OTHER ITEMS • Addition of single user toilets at 1st • New technology • New corridor ceilings and lighting • New furniture • Parking expansion on west side (25 cars) • Entry canopy HVAC/SYSTEMS • Abatement at classrooms • System upgrades (MEP) at classrooms • New electrical system • New windows • Replace exterior lighting

  15. Opt 4: Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) Cost: $15,050,000 DOES NOT INCLUDE • Restoration of existing roof - $410,000 • Larger gym (5,000 sf) - $500,000 • Tornado shelter - $385,000 • Future 6-8 electrical capacity - $70,000 • Full plumbing replacement - $325,000 • Abatement at crawlspace - $105,000 • Playground drainage - $65,000 • Playground re-surfacing - $35,000 • Bus drop off expansion on north side - $210,000 • 3 strand 6-8 addition (51,000 sf) - $14M-$15.8M

  16. Option 5: Ideal 4 Strand K-5 (Parity to Garden Hills) Cost: $19,680,000

  17. Option 5: Ideal 4 Strand K-5 (Parity to Garden Hills) Cost: $19,680,000 INCLUDES • Eliminates portables FACELIFT • 27,000 sf of total additions • New interior doors & hardware • 5,000 sf gym • New casework at classrooms • Renovation of admin/secure entry • New paint/signage, etc. • Renovations of kitchen/dining areas • New flooring • Renovation of existing toilet rooms OTHER ITEMS • Addition of single user toilets at 1st • New technology • New corridor ceilings and lighting • New furniture • Parking expansion on west side (30+ cars) • Entry canopy HVAC/SYSTEMS • Abatement at classrooms • System upgrades (MEP) at classrooms • New electrical system • New windows • Replace exterior lighting • Tornado shelter • Bus drop off expansion on north side

  18. Option 5: Ideal 4 Strand K-5 (Parity to Garden Hills) Cost: $19,680,000 DOES NOT INCLUDE • Restoration of existing roof - $410,000 • Future 6-8 electrical capacity - $70,000 • Full plumbing replacement - $325,000 • Abatement at crawlspace - $105,000 • Playground drainage - $65,000 • Playground re-surfacing - $35,000 • 4 strand 6-8 addition (56,000 sf) - $15.4M-$17.4M

  19. Opt 6: NEW Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) Cost: $20.3M-$22.3M

  20. Opt 6: NEW Ideal 3 Strand K-5 (Parity to South Side & Dr. Howard) Cost: $20.3M-$22.3M

  21. Opt 7: NEW Ideal 4 Strand K-5 (Parity to Garden Hills) Cost: $23.6M-$25.9M

  22. Opt 1 Opt 2 Opt 3 Opt 4 Opt 5 Opt 6 Opt 7 $20.3M- $23.6M- Cost $6.7M $9.9M $12.9M $15M $19.7M $22.3M $25.9M ✓ ✓ ✓ ✓ ✓ n/a n/a 10,000sf Add. Gym/Library ✓ ✓ ✓ ✓ ✓ n/a n/a Admin/Secure Entry ✓ ✓ ✓ ✓ ✓ n/a n/a Kitchen/Dining Reno ✓ ✓ ✓ ✓ ✓ ✓ ✓ Enhanced Car Drop ✓ ✓ ✓ ✓ n/a n/a HVAC/Windows ✓ ✓ ✓ n/a n/a Facelift ✓ ✓ ✓ ✓ ✓ New Technology ✓ ✓ ✓ ✓ ✓ New Furniture ✓ ✓ ✓ n/a n/a Roof Restoration ✓ ✓ ✓ ✓ Eliminates Portables ✓ ✓ n/a n/a Additions for Parity ✓ ✓ ✓ Enhanced Bus Drive ✓ ✓ ✓ Tornado Shelter ✓ ✓ ✓ 5000 sf Gym ✓ ✓ New Facility $20.7M- $23.9M- $26.9M- $29M- $35.1M- $34.3M- $39M- Cost with 6-8 Addition $22.5M $25.7M $28.7M $30.8M $37.1M $38.1M $43.3M

  23. Thank you! Board of Education Meeting 12.09.19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.